Supplement Three - Financial Supplement.pdfSupplement Three - Financial Supplement.pdf
PDF 41 KB Posted
- Attached to
- Deaf Community Needs Assessment
- Solicitation number
- SRC0000041714
- Issued by
- Ohio
About this file
This is a Financial Supplement document issued by Opportunities for Ohioans with Disabilities (OOD) for the Deaf Community Needs Assessment project (SRC0000041714) in Ohio. The project is structured in three phases: Phase One involves identification of the deaf community in Ohio with a deliverable of a draft written report on a one-time basis; Phase Two and Three encompass a comprehensive needs assessment with a final report and presentation including requested clarifications and additions, also delivered on a one-time basis. The total contract budget is established at $30,000, which must not be exceeded.
Contractors are required to complete budget tables detailing costs for each phase and provide a total project cost not to exceed $30,000. The financial supplement allows contractors to request a one-time advance payment of up to 25 percent of the proposed cost to facilitate project development, with the advance amount to be deducted from subsequent invoices. All costs must be submitted in U.S. dollars, and OOD assumes no responsibility for costs not identified in the proposal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUPPLEMENT THREE
FINANCIAL SUPPLEMENT
SRC0000041714
Deaf Community Needs Assessment
Budget: $30,000
Total Cost must not exceed the listed budget of $30,000.
Instructions: Contractor must complete the tables below.
DESCRIPTION FREQUENCY COST
Phase One: Identification of the deaf community in Ohio
Deliverable for payment Draft written report.
One-time $
Phase Two: Comprehensive Needs Assessment and Phase Three: Report and Presentation
Deliverable for payment Final Report and Presentation including requested clarifications and additions.
One-time $
Deaf Community Needs Assessment Total Cost $
The Contractor may elect to submit a request for a one-time advance payment to assist in the development of the project. Said payment is not to exceed 25% of the proposed cost for the Deaf Community Needs Assessment. If Contractor elects to receive a one-time advanced payment, Contractor shall deduct the amount of the one-time advanced payment from a future invoice or invoice(s) for the project.
DESCRIPTION FREQUENCY Amount Initial funding needed for start-up. (Not to exceed 25% of the total award.) One-time $
All costs must be in U.S. Dollars.
OOD will not be responsible for any costs not identified.
File details come from the government source that posted it. Updated .