This is a Financial Supplement document issued by Opportunities for Ohioans with Disabilities (OOD) for the Deaf Community Needs Assessment project (SRC0000041714) in Ohio. The project is structured in three phases: Phase One involves identification of the deaf community in Ohio with a deliverable of a draft written report on a one-time basis; Phase Two and Three encompass a comprehensive needs assessment with a final report and presentation including requested clarifications and additions, also delivered on a one-time basis. The total contract budget is established at $30,000, which must not be exceeded.

Contractors are required to complete budget tables detailing costs for each phase and provide a total project cost not to exceed $30,000. The financial supplement allows contractors to request a one-time advance payment of up to 25 percent of the proposed cost to facilitate project development, with the advance amount to be deducted from subsequent invoices. All costs must be submitted in U.S. dollars, and OOD assumes no responsibility for costs not identified in the proposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLEMENT THREE

FINANCIAL SUPPLEMENT

SRC0000041714

Deaf Community Needs Assessment

Budget: $30,000

Total Cost must not exceed the listed budget of $30,000.

Instructions: Contractor must complete the tables below.

DESCRIPTION FREQUENCY COST

Phase One: Identification of the deaf community in Ohio

Deliverable for payment Draft written report.

One-time $

Phase Two: Comprehensive Needs Assessment and Phase Three: Report and Presentation

Deliverable for payment Final Report and Presentation including requested clarifications and additions.

One-time $

Deaf Community Needs Assessment Total Cost $

The Contractor may elect to submit a request for a one-time advance payment to assist in the development of the project. Said payment is not to exceed 25% of the proposed cost for the Deaf Community Needs Assessment. If Contractor elects to receive a one-time advanced payment, Contractor shall deduct the amount of the one-time advanced payment from a future invoice or invoice(s) for the project.

DESCRIPTION FREQUENCY Amount Initial funding needed for start-up. (Not to exceed 25% of the total award.) One-time $

All costs must be in U.S. Dollars.

OOD will not be responsible for any costs not identified.