About this file
This is an asbestos abatement specification document issued by Harbor Springs Public Schools (HSPS) in Harbor Springs, Michigan, for summer 2025 bond program work at Harbor Springs High School. The project involves the removal of asbestos-containing materials including floor tile/mastic, carpet over suspected asbestos floor tile/mastic, stair tread, and fire doors from various locations within the high school building. A mandatory pre-bid meeting and walkthrough is scheduled for February 11, 2025 at 11:30 AM, with bids due February 25, 2025 at 10:00 AM. The work is to be completed between June 16, 2025 and July 18, 2025, with specific phase completion dates outlined for different areas of the building.
The project is divided into multiple work areas including Unit A (first through third floors) and the Wood Shop, with approximately 60,000 square feet of carpet/floor tile removal in the Academic Wing and 4,400 square feet in the Wood Shop. The contractor must maintain negative pressure enclosures and follow specific decontamination procedures throughout the work. A 5% bid bond is required with the submission, and the selected contractor must provide 100% performance and payment bonds. The project requires TEM clearance air sampling for areas where grinding methods are used for mastic removal. The specification includes detailed requirements for worker protection, respiratory equipment, containment procedures, and waste disposal protocols.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 64658 ACM Bid-Specification. Addendum No. One.2.13.25.with attachments (1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASBESTOS/Haz-Mat
ABATEMENT
SPECIFICATIONS
Abatement for Summer 2025 - Bond Program at The High School
Owner:
Harbor Springs Public Schools 800 S. State Street
Harbor Springs, Michigan 49740
Building(s):
High School 500 N. Spring St.
TEC Project #: 64658 Issue Date: Monday, January 20, 2025 Pre-Bid: 11:30 A.M., Tuesday February 11, 2025 Bids Due: 10:00 A.M., Tuesday, February 25, 2025
ASBESTOS/Haz-Mat
ABATEMENT
SPECIFICATIONS
Abatement for Summer 2025 - Bond Program at The High School
AHERA PROJECT DESIGNER ASBESTOS CONSULTANT
Name: Joseph T. Konrad Testing Engineers and Consultants, Inc. (TEC) State of Accreditation: Michigan 1343 Rochester Road Accreditation Number: A5594 Troy, Michigan 48083 State Expiration Date: October 11, 2025 Phone: (248) 588-6200 Training Expiration Date: October 03, 2025 Fax: (248) 588-6232
TABLE OF CONTENTS
SECTION I
Bid Advertisement and Project Summary ......................................................................................................... 3-11
Bid Advertisement ........................................................................................................................................4-6 Project Summary Map to HSPS Sites ..................................................................................................................................... 8-11
BID Packet ...................................................................................................................................................... 12-21
Bidder’s Agreement & Certification and Bidder Acknowledgment ......................................................... 13-14 Bid No. 19.01 – High School Bid No. 19.02 – Unit Price Schedule Familial Relationship Disclosure Statement Affidavit of Compliance – Iran Economics Sanctions Act Bidder’s Statement of Qualifications and Statement of Bid Preparation ................................................ 22-24
SECTION II
Project Scope of Work and Requirements ....................................................................................................... 24-46
Bid Nos. 19.01-19.02 ................................................................................................................................ 25-38 General Information and Requirements .................................................................................................. 39-40 Project Schedule Information ...................................................................................................................41-46
SECTION III
General Conditions .................................................................................................................................................47-55 General Procedures for Asbestos Abatement ........................................................................................................56-81 Bidder’s Checklist for Submittals Project Designer Accreditation Information
SECTION IV
Pre-Project Submittals Post-Project Submittals
APPENDICIES
APPENDIX A – HAZARDOUS MATERIAL REMOVAL/DISPOSAL GUIDELINES
APPENDIX B – FLOOR PLANS FOR UNIT A & D
ASBESTOS ABATEMENT
HSPS
Abatement for Summer 2025 Bond Program Page 3
SECTION I
BID ADVERTISEMENT and PROJECT SUMMARY
BID PACKET
Abatement for Summer 2025 Bond Program Page 4
HARBOR SPRINGS PUBLIC SCHOOL SYSTEM
ADVERTISEMENT
The Board of Education of the Harbor Springs Public School System (“Owner” or “School District” or “HSPS”) will receive sealed Bid Proposals for:
SUMMER 2025 WORK PROGRAM – HIGH SCHOOL ASBESTOS/HAZ-MAT ABATEMENT PROJECT
Bid Proposals will be received by Mr. Brad Plackemeier, Superintendent for the Harbor Springs Public School System, at 800 South Street Harbor Springs, Michigan 49740, on or before 10:00 a.m. (local time) on February 25, 2025 (“Due Date”). All portions of the BID’s should be submitted as listed below and the entire hard copy packet must be submitted in triplicate. The Board of Education will not consider or accept a Bid Proposal received after the Due Date, the date and time specified for Bid Proposal submission. Bid Proposals will be publicly opened and read aloud immediately following the Due Date at the same location.
A mandatory pre-Bid Proposal meeting will be held on February 11, 2025. Bidders must attend a walkthrough of the school.
The walk sequence and meeting locations are as follows:
a. 11:00 a.m. at the High School located at 500 N. Spring St., Harbor Springs, MI. All persons attending the Pre-Bid will be required to park in the front parking lot and meet at the front entrance.
Each Bid Proposal must be accompanied by a sworn and notarized statement disclosing any familial relationship that exists between the owner or any employee of the bidder and any member of the Board of Education or the Superintendent of the Harbor Springs Public School System. The Board of Education will not accept a Bid Proposal that does not include this sworn and notarized disclosure statement.
Each Bid Proposal must also be accompanied by a sworn and notarized statement certifying that the Contractor is not an Iran Linked Business. The Board of Education will not accept a Bid Proposal that does not include this sworn and notarized statement.
Each Bid Proposal must also be accompanied by a bid bond in the amount no less than five percent (5%) of the total bid amount(s).
The Harbor Springs Public School System’s Board of Education reserves the right to accept or reject any and all Bid Proposals, either in whole or in part, to waive any informalities or irregularities therein, or to award the contract to other than the contractor(s) submitting the best financial Bid Proposal (low bidder), in its sole and absolute discretion.
Bid documents, including Bidders Information Manual, scopes of work, Drawing and Specifications will be made available Friday, February 7, 2025 at the following website:
https://app.e-builder.net/public/publicLanding.aspx?QS=cb6a98e01dff4fd094c7e29e5c4c05c0
If you have any questions, please do not hesitate to contact Joseph T. Konrad at (734) 707-6571 or email at jkonrad@tectest.com, and/or Joseph Lang Konrad at (734) 255-9159 or email at langkonrad004@hotmail.com
Directions: A map of the HSPS building(s) discussed in this Bid Advertisement follows the Project Summary.
Schedule: The format of the Pre-Bid Examination will be an initial presentation on the bidding process and the scope of work. This activity will be conducted in the Harbor Springs Public Schools (HSPS) High School Building, Cafeteria from approximately 11:00 A.M. - 12:00 P.M. Afterwards, Testing Engineers and Consultants, Inc.
(TEC) will provide a brief tour of the buildings and host a question & answer session for interested bidders.
Additional access will be made to the Contractors on an as needed basis. Please schedule with TEC.
Additional building specific review(s) with TEC are non-mandatory.
https://app.e-builder.net/public/publicLanding.aspx?QS=cb6a98e01dff4fd094c7e29e5c4c05c0 mailto:jkonrad@tectest.com
Abatement for Summer 2025 Bond Program Page 5
HSPS intends to formally award the project at: Harbor Springs Public School’s Board of Education Meeting – TBD At: HSPS Administration Building
800 S. State St.
Harbor Springs, Michigan 49740
Note: TEC will issue a letter of recommendation and/or formal letter of intent to the lowest, qualified Bidder(s) no later than Thursday, May 30, 2025 to allow the recommended contractor the opportunity to prepare for the project, submit the project notification and accurately consider other bids.
Questions Regarding Project Specifications:
The only questions/clarifications that will be formally recognized will need to be submitted in writing, with a formal written response from HSPS. Questions are due by February 18, 2025.
Official questions, and need for clarification regarding, scheduling, bonding, contract language, legal questions, and the Project Specification should be addressed to:
Mr. Brad Plackemeier, HSPS Office: 231-526-4545 Email: bplackemeier@harborps.org
Scheduling and non-legal questions, clarifications regarding the Project Specifications should be addressed to:
Joseph T. Konrad, TEC Office: (248) 588-6200 Mobile: (734) 707-6571 Email: jkonrad@tectest.com
All official changes and interpretations to the Project Specifications will be made via addenda only. Bidders are encouraged to fax [(248) 588-6232] or email (to the email address(es) listed above) all questions regarding the specifications, bidding procedures, etc. to TEC
Project Specification Documents:
Project Specification Documents will be available on e-builder at:
Bonding Requirements:
HSPS requires that all bidders submit a Bid Bond in accordance with the requirements summarized below and that all selected Contractors submit Performance and Labor and Materials Bonds in accordance with the requirements summarized below:
Bid Bond
Amount: 5% Requirements: The Bidder shall submit the required Bid Security in the form of a Bid Bond by a Treasury approved surety licensed to do business in the State of Michigan, a Cashier's Check, or a Certified Check in the amount of 5% of the bid price. The Bid Security shall be submitted with the understanding that if the bid is accepted, the Bidder will enter into a formal contract with the Owner and that the required Performance and Labor and Material Payment Bonds (as listed below and fully detailed in the General Conditions section) will be provided by the Contractor. The Bid Security oblige is HSPS. Bidders shall agree not to withdraw proposals for a period of thirty (30) days after the bid due date.
Performance Bond & Labor and Material Payment Bonds Amount: 100% mailto:bplackemeier@harborps.org mailto:jkonrad@tectest.com
Abatement for Summer 2025 Bond Program Page 6
Requirements: The accepted Contractor will be required to furnish, in the amount of 100% of the Contract Price, satisfactory Performance Bond and Labor and Material Payment Bond by a Treasury approved surety, as listed on the U.S. Department of Treasury Circular 570, licensed to do business in the State of Michigan. The U.S. Department of Treasury Circular 570 can be viewed at the following web site: https://www.fiscal.treasury.gov/fsreports/ref/suretyBnd/c570_a-z.htm. The accepted Contractor will be required to furnish the bonds prior to the start of the project. Mobilization to the project site will not begin until acceptable bonds are furnished by the accepted Contractor.
Additional Information for Bidders:
All applicable insurance policies (including asbestos specific) will be required of each accepted Bidder. Bidders must submit copies of the Contractor’s current State of Michigan Asbestos Abatement License. This project is not tax exempt from State Sales Tax and/or Use Tax. All materials and supplies incorporated and used in construction and becoming a permanent part of this project will not be exempt from State Sales Tax and/or Use Tax. Prevailing wages are not required for this project.
Confidentiality The proposals and supporting materials become the property of the HSPS and are subject to public access according to the Freedom of Information Act, MCL 15.231 et. Seq.
Request for Quotation Packet - Submittal Requirements:
The BID Packet (Pages 12-21) shall be submitted on the forms furnished in this specification. The BID Packet must be submitted in duplicate. The BID Packet and all additional information requested must be submitted as follows:
Item Item Description Page No.
1. BID Submittal Packet Cover Sheet 8
2. Bidder’s Agreement and Certification and Bidder Acknowledgment 9-10
3. Bid No. 19.01 – High School 11
Bid No. 19.02 – Unit Prices 12-15
4.
Familial Relationship Disclosure Statement [STATE REQUIREMENT - BID WILL NOT BE ACCEPTED WITHOUT THIS SIGNED AND NOTARIZED STATEMENT]
5. Affidavit of Compliance – Iran Economics Sanctions Act 17 [STATE REQUIREMENT - BID WILL NOT BE ACCEPTED WITHOUT THIS SIGNED AND NOTARIZED STATEMENT]
6. Bidder’s Statement of Qualifications and Statement of Bid Preparation 18-20
7. Bidder’s Response to Statement of Qualifications and Statement of Bid Preparation Submit
8. Bid Security Submit
9. Contractor’s Current State of Michigan Asbestos Abatement License Submit
10. Proof of Insurance Submit
11. Additional Information Submitted by Bidder Submit
TEC and HSPS request that the Bidder enter “NO BID” on the bid forms in lieu of omitting the page.
https://www.fiscal.treasury.gov/fsreports/ref/suretyBnd/c570_a-z.htm.
Abatement for Summer 2025 Bond Program Page 7
- Bid No. 19.01 High School Project Summary for Bid Advertisement
This project summary provides a summary of the asbestos-containing materials and non-asbestos-containing materials which will be removed as part of the bid. The scope of work, project requirements and project schedule are provided in the specification documents. The Contractor is encouraged to review all aspects of the scope-of-work when preparing the bid and is instructed not to use this summary when preparing this bid.
[ABATEMENT]
19.01 High School, ACM Abatement
The abatement at the High School includes the removal of asbestos containing floor tile/mastic, carpet over suspected asbestos containing floor tile and/or mastic, stair tread, and fire doors, from various locations. The abatement at High School will require negative pressure enclosure(s), as delineated in the bidders required workplan. The accessible work hours allow for a M-F, 7AM to 5PM schedule to complete the project. Double shifts, extended hours, and/or weekend/holiday hours must be included in the proposed work plan and approved by the Owner.
Abatement for Summer 2025 Bond Program
SPECIFICATIONS
Bond Work for Summer 2025 Pre-Demolition Abatement @ The High School
Representative:
E-Mail:
P: F: Phone/Fax:
Address:
Contractor Name:
BIDDER INFORMATION
BIDDER’S AGREEMENT AND CERTIFICATION
The undersigned Bidder, having fully examined the Project Specification Documents [including, but not limited to, Section I (the Bid Advertisement, the Project Summary and the BID packet), Section II (the Project Scope of Work and Requirements) and Section III (the General Conditions and the General Procedures for Asbestos Abatement)], as well as all other associated information (including the addenda listed and acknowledged on the following page), and having familiarized himself with the conditions to be encountered affecting the cost of the work, does hereby propose to satisfactorily complete all activities required to be performed and to furnish all of the labor, materials, tools, equipment and all other necessary additional services needed to complete the Asbestos Abatement Activities required in connection with this project. Addenda issued by HSPS or TEC and acknowledged by the Bidder, are made part of the Project Specification Documents and are listed on the following page.
All Bidders were provided the opportunity to attend the Pre-Bid Examination on 11:00 A.M., Tuesday, February 11, 2025, and provided the opportunity for an accompanied tour of the building(s), and all Bidders have been encouraged, and provided the opportunity, to examine the project site/building and familiarize themselves with the work described in the Project Specification Documents. The submission of a bid for the projects described in the Project Specification Documents shall be deemed conclusive evidence that the Bidder has thoroughly examined all documents constituting this specification (including, but not limited to, those items and sections listed above), has familiarized himself with the work and requirements described and shall constitute a waiver by each of all claims of error in bid, withdrawal of bid, or payment of extras, or combination thereof, under the executed Contract, or any revision thereof. All figures set forth in the Project Specification Documents referencing sizes, amounts, or materials are estimates only and are provided for the convenience of the Bidder. The Bidder is solely and completely responsible for his own measurements and for his own determination regarding the scope of the project(s).
These specifications including, but not limited to, the Bid Advertisement, the Project Scope of Work and Requirements, the General Conditions and the General Procedures for Asbestos Abatement, have attempted to detail and address all aspects of the projects being performed for HSPS. Nonetheless, the successful completion of the projects in a safe manner and in compliance with all applicable regulations remains as the foremost concern of HSPS. To insure that this goal is met, it is expressly agreed by and between the parties to the contract, hereinafter to be signed between Harbor Springs Schools and the Contractor, that HSPS and/or TEC, as the Owner’s Representative, have complete control over the manner in which the projects shall proceed and may, in their sole discretion, waive provisions of these Project Specifications or require and enforce more stringent or different provisions should they, in their discretion, determine that such changes will or may more fully protect HSPS, the Contractor, their subcontractors, agents, servants or others under their control or direction or the general public from any risks and/or situations associated with the said projects.
This provision in no way constitutes a waiver by the Contractor of his/her responsibilities to conduct said projects in accordance with all applicable regulations and in accordance with these specifications. This provision is set forth and is intended to provide HSPS and/or TEC with the power to require additional steps to be taken to ensure that the projects proceeds in a manner to fully, to the utmost extent possible, protect HSPS and/or TEC, as well as the general public, from risks and liability associated with such projects.
After the bids are received, tabulated and evaluated by TEC, and the apparent lowest qualified Bidder(s) for each Bid item has been determined, the Bidder(s) agrees to meet with TEC, if so requested. For purposes of these meetings, the Bidder agrees to provide any post bid information as listed in the General Conditions. The Bidder, if awarded a contract, agrees to commence all pre-project planning and preparation activities upon receipt of a written “Notice to Proceed/Letter of Intent” and to fully complete their work in accordance with and to conform to the milestone activity dates and durations set forth in the Project Specification Documents.
The signature of a representative for the Bidder on each applicable project constitutes a full and complete agreement with the Project Specifications and the Bidder’s Agreement and Certification. All Bid Forms must be completed. Bids which are not submitted should be marked “N/A”, or have similar notations.
Type of Bid Security Please indicate type of bid security provided: [ ] 5% Bid Bond [ ] Certified Check
Acknowledgment of Addenda:
The Bidder has received and reviewed the following addenda:
Addendum No. Addendum No. Addendum No.
Dated Dated Dated
Type of Business:
The Bidder is a (check one): Partnership Corporation
The Bidder is (check all that apply): Minority Woman Owned Small Business Enterprise
Identification of Potential Conflict of Interest The Bidder hereby discloses and describes any business, financial, or pecuniary relationship existing between the Bidder (or any officer, agent, or employee of the Bidder) and any officer, employee, agent, board member, or owner of HSPS, TEC, the Construction Manager/General Contractor, or Architect. If no such relationship exists, so state in the space provided.
Attach additional pages if necessary
Signature of Chief Executive Office (or equivalent)
BIDDER ACKNOWLEDGMENTS
Acknowledgment of Specification Details/Bid Preparation:
The Bidder acknowledges that the Bidder has reviewed each section of the bid documents relating to each of the Bids and understands that the Bidder will not be released from the Bid(s) due to missed abatement related activities or other similar oversights. The Bidders also acknowledges that he has checked each bid and that all figures are correctly listed on the bid forms.
Signature of Chief Executive Office (or equivalent)
The Bidder hereby agrees and certifies to comply with all requirements described within this Project Specification and the listed and acknowledged Addenda and agrees to accept a payment of for all work regarding this bid as described in the “Project Scope of Work and Requirements”, including the Project Summary, Abatement Activities, Abatement Requirements, Additional Requirements and Information, Project Diagrams and the Time Schedule.
The Bidder agrees and certifies that the above stated cost includes all charges for all wages, overtime, taxes, materials, supplies, equipment, disposal costs, general conditions, supervision, insurance, overhead, profit and incidental expenses and fees. The Bidder hereby agrees and certifies that if the projects are not completed by the final due date the Bidder will accept a penalty as described in the project specifications.
The Undersigned, a Representative of the Bidder, hereby authorizes and requests any person, firm, or corporation to furnish any information requested by HSPS and/or their Representatives in verification of the recitals comprising the Bidder’s Statement of Qualifications. When requested, a breakdown of the bid by building will be submitted following award of a contract.
COMPANY NAME
PRINT NAME
TITLE
SIGNATURE
Alternate Bids Provided:
[ ] None [ ] Attached - List Below:
Bidder Noted Conditions/Restrictions on Bid:
[ ] None [ ] Listed Below:
Bid No. 19.01 - High School - Abatement for Summer 2025 Bond Program (Base Bid)
Base Bid dollars ($ )
Bid No. 19.02 (All Bidders) - Abatement for Summer 2025 Bond Program (Unit Price Schedule)
UNIT PRICE SCHEDULE:
Furnish all labor, materials, equipment and services necessary for and incidental to the above-named project as directed in the Contract Documents. All applicable taxes and bond costs are to be included in the Unit Prices. Unit prices shall be utilized in the event additional removal work and/or deletions of work are included at the Owner's/Environmental Consultant's discretion.
ASBESTOS/ASBESTOS Contamination Removal Unit Prices:
12”x12” Floor Tile/Mastic Removal, Per Square Foot: $ (includes materials, labor and disposal)
9”x9” Floor Tile/Mastic Removal, Per Square Foot: $ (includes materials, labor and disposal)
Straight Pipe Insulation Removal Per Linear Foot:
(includes materials, labor, and disposal)
Pipe Diameter of < 6" $
Pipe Diameter of 6" to 12" $
Pipe Diameter of > 12" $
Pipe Fitting Insulation Removal Per Each Fitting:
(includes materials, labor, and disposal of elbows, valves, T's, etc.)
Pipe Diameter of < 6" $
Pipe Diameter of 6" to 12" $
Pipe Diameter of > 12" $
Cementitious Panel Removal, per square foot: $ (includes materials, labor and disposal)
Fire Door Removal, per door: $ (includes materials, labor and disposal)
Vapor Barrier, per square foot: $ (includes materials, labor and disposal) $
Duct Insulation Removal, per square foot: $ (includes materials, labor and disposal) $
HVAC Fabric (vibration dampener cloth) Removal, per square foot: $ (includes materials, labor and disposal)
Mixer Box Insulation, per square foot: $ (includes materials, labor and disposal)
Spray Applied Insulation Removal, per square foot: $ (includes materials, labor and disposal)
Decorative Surfacing Material, per square foot: $ (includes materials, labor and disposal)
Tank Insulation Removal, per square foot: $ (includes materials, labor and disposal)
Sink Undercoating Insulation, Removal, per sink: $ (includes materials, labor and disposal)
Paper Baffle Insulation Removal, per square foot: $ (includes materials, labor and disposal)
2' X 4' Suspended Grid System demolition, per square foot: $ (includes materials, labor and disposal)
Ceiling Demolition including suspended/systems, per square foot: $ (including materials, labor and disposal)
- 1'X 1Glue-on (including substrate) $
- 1'X 1'Suspended spline $
- 2'X 4'Suspended lay-in $
- 2'X 4'Suspended lay-in $
- 2'X 2'Suspended lay-in $
- Plaster Walls/Ceilings $
Exterior Perimeter Panel Removal, per square foot $ (includes materials, labor and disposal)
Carpet Removal, per square foot $ (including materials, labor and disposal)
Floor Tile/Linoleum, per square foot $ (including materials, labor and disposal)
Remobilize to continue ACM abatement work on additional items, in the event that the scheduled work is interrupted: $
Hourly Rate for Asbestos Abatement Worker (per person), Fully loaded to include materials, equipment, removal and disposal: $
Hourly Rate for Asbestos Abatement Supervisor (per person), Fully loaded to include materials, equipment, removal and disposal: $
Non-ACM Demolition, Unit Prices
Concrete wall Demolition per square foot: $ (includes materials, labor and disposal)
CMU Block wall Demolition, per square foot: $ (includes materials, labor and disposal)
Ceramic/Quarry Tile wall Demolition, per square foot: $ (includes materials, labor and disposal)
2' X 4' Suspended Grid System demolition, per square foot: $ (includes materials, labor and disposal)
Plaster Ceiling Demolition including suspended/systems, per square foot:$ (including materials, labor and disposal)
- 1'X 1Glue-on (including substrate) $
- 1'X 1'Suspended spline $
- 2'X 4'Suspended lay-in $
- 2'X 2'Suspended lay-in $
- Plaster Walls/Ceilings $
Carpet Removal, per square foot $ (including materials, labor and disposal)
Floor Tile/Linoleum, per square foot $ (including materials, labor and disposal)
Mastic removal, per square foot for ginding removal $ (including materials, labor, equipment and disposal)
Hourly Rate for Demolition Worker, Fully loaded to include materials, equipment, removal and disposal: $
Hourly Rate for Demolition Supervisor, Fully loaded to include materials, equipment, removal and disposal: $
Remobilize to continue demolition work on additional items, in the event that the scheduled work is interrupted: $
Hazardous Material Removal Unit Prices:
Fluorescent Light Ballast, Removal, Per Ballast: $ (includes materials, labor and disposal)
Fluorescent Light Removal, Per (four) 4-foot Bulb: $ (includes materials, labor and disposal)
Mercury Thermostat Switch Removal, Per Switch: $ (includes materials, labor and disposal)
Lead Sheeting Removal, Per Square Foot: $ (includes materials, labor and disposal)
Lead Based/Containing Paint Removal, Per Square Foot: $ (includes materials, labor and disposal)
Remobilize to continue work on additional items, in the event that the scheduled work is interrupted: $
FAMILIAL RELATIONSHIP DISCLOSURE STATEMENT
Important: This disclosure statement must be included with your bid as required by state law (Public Act 232 of 2005).
As required by Public Act 232 of 2005, all bids shall be accompanied by a sworn and notarized statement disclosing any familial relationship that exists between the owner or any employee of the bidder and any member of the HSPS’s Board of Education or the Superintendent of Schools. The Board of Education shall not accept a bid that does not include this sworn and notarized disclosure statement.
The undersigned, the owner or authorized officer of (the “Bidder”), pursuant to the familial disclosure requirement provided in the HSPS advertisement for construction bids, hereby represent and warrant, except as provided below, that no familial relationships exist between the owner(s) or any employee of the company and any member of the HSPS’s Board of Education or the Superintendent of Schools. If such a relationship exists, please explain:
Attach additional pages if necessary
By: (bidder signature)
Title: (type or print)
Date:
Subscribed and Sworn to Before Me:
This day of , 20 A.D., in and for the County of , Michigan.
My commission expires:
Acting in the County of:
AFFIDAVIT OF COMPLIANCE - IRAN ECONOMIC SANCTIONS ACT
Important: This disclosure statement must be included with your bid as required by state law (Public Act 517 of 2012).
The undersigned, the owner or authorized officer of
(the “Contractor”), hereby certifies, represents and warrants that the Contractor (including its officers, directors and employees) is not an “Iran linked business” within the meaning of the Iran Economic
Sanctions Act, Michigan Public Act No. 517 of 2012 (the “Act”), and that, in the event Contractor is awarded a contract as a result of the aforementioned Request For Proposal, the Contractor will not become an “Iran linked business” at any time during the course of performing the Work or any services under the contract.
The Contractor understands and agrees that, if HSPS receives credible information that this Affidavit includes false information, HSPS will conduct an investigation that may lead to the termination of this contract as provided in the Act. The Contractor agrees to indemnify HSPS (including its agents, employees and representatives), and hold them harmless, for all actual attorneys’ fees and costs, settlements, awards, judgments, interest and bonds arising from or relating to any such investigation.
The Contractor further acknowledges that any person who is found to have submitted a false certification may be responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the HSPS’s investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years from the date the it is determined that the person has submitted the false certification.
By: (bidder signature)
Title: (type or print)
Date:
Subscribed and Sworn to Before Me:
This day of , 20 A.D., in and for the County of , Michigan.
My commission expires:
Acting in the County of:
BIDDER’S STATEMENT OF QUALIFICATIONS and
STATEMENT OF BID PREPARATION
All questions must be answered clearly and in a comprehensive manner on Bidder supplied answer sheets. Do not submit answers on this sheet. Any Bidder failing to answer all questions may be rejected on these grounds. It is understood that the by submitting a signed bid, the Bidder is certifying the correctness of all statements and is hereby under oath. All answer sheets that are used must have a reference to this Statement of Qualifications and/or a reference to the project or HSPS. The Bidder may submit any additional information which may be of assistance in evaluating the qualification of the Bidder. Information will only be released by HSPS following a written request.
Corporate Information
1. Name of Bidder
2a. Permanent Main Office Address, Phone Number and Fax Number 2b. Additional Offices - Number, Locations, Addresses, Phone Numbers and Fax Numbers
Corporate History
3. When was (Name of Bidder) Organized?
4. If a Corporation, where is (Name of Bidder) Incorporated?
5. How many years has (Name of Bidder) been operating under the (Name of Bidder) name?
6. How many years has (Name of Bidder) been licensed in the State of Michigan for Asbestos Abatement?
7a. What other names are the principals of (Name of Bidder) operating under that are associated with the asbestos abatement industry?
7b. What other names have the principals of (Name of Bidder) operated under that have been associated with the asbestos abatement industry?
8. Have the principals of (Name of Bidder) filed for Chapter 11 or Chapter 13 for protection of (Name of Bidder) or for any other asbestos abatement related firm, company or organization, in the last five years? Describe.
Corporate Experience and References
9. Please list contracts currently on hand, including those projects which are in progress. Please provide a schedule (with actual or anticipated commencement and completion dates) and approximate gross dollar amount of each contract. Specifically highlight non-HSPS projects which will be conducted at the same time as this project.
10. Please list all specifications (Name of Bidder) is currently submitting bids for which have overlapping project dates. Please provide a schedule with anticipated commencement and completion dates.
11. Have you (Name of Bidder and other entities identified in Questions 7a and 7b answers) ever failed to complete any work awarded to you?
12. Have you (Name of Bidder and other entities identified in Questions 7a and 7b answers) ever been disqualified from bidding in HSPS?
13. Have you (Name of Bidder and other entities identified in Questions 7a and 7b answers) ever not been recommended for bid contracts when you were the low bidder in HSPS?
14. Have you (Name of Bidder and other entities identified in Question 7a and 7b answers) ever not been recommended for bid contracts when you were the low bidder on a project designed by TEC
15. Please list all projects (Name of Bidder) completed in HSPS in the last three (3) years.
16. Please list all projects over $15,000 completed by (Name of Bidder) in the last twelve (12) months (projects with HSPS do not need to be listed in response to this question), stating approximate gross dollar amount, and the month and year completed.
17. Please list the experience of (Name of Bidder) in work similar to this project. Project references must include: names, addresses, and phone numbers of Building Owner's for whom projects were performed (minimum of four). This list should include only AHERA projects, which include the removal of surfacing materials as a portion of the scope-of-work.
Corporate Compliance History
18. Please list any and all citations with or without monetary penalty received, pending, paid or disputed by
(Name of Bidder and other entities identified in Question 7a and 7b answers) during the past 3 years for failure to comply with applicable federal, state or local regulations. Describe in detail the type of citation, the reason for the citation and the ultimate disposition of same. Provide copies of all citations received in the last three (3) years and all correspondence associated with the citations.
19. Please provide the dates and results of the last on-site inspection by the Michigan Department of Labor and Economic Opportunity ((LEO), formerly Department of Licensing and Regulatory Affairs) and the Michigan Department of Environment, Great Lakes and Energy ((EGLE) formerly Michigan Department of Environmental Quality).
20. Please list all penalties incurred through non-compliance with asbestos abatement project specifications, including projects designed by firms other than TEC, including liquidated damages/penalties, overruns in scheduled time limitations and any subsequent resolutions for (Name of Bidder) in the last three (3) years.
Corporate Resources
21. Please list (Name of Bidder)’s staff size, including number of foreman (accredited competent persons), number of workers and common sources for additional manpower. Estimated number of new hires for “peak” season may be listed with this response.
22. Please list (Name of Bidder)’s staff size, including number of foreman (accredited competent persons), number of workers and common sources for additional manpower that will be used for this project. List information for all buildings.
23. Please list of (Name of Bidder)’s major equipment (as of the submitting of this bid) which will be available specifically for this contract. Do not provide an inventory list. The response to this question must specifically reference the equipment which will be available for this project. Please indicate the number of equipment, such as AFDs, showers, scaffolds, etc. which will be on-site for the duration of the project.
24. Please provide (Name of Bidder)’s bank references.
25. Please provide the name of the Bonding Company and the name and address of agent used for this bid.
Bidder’s Bid Preparation Information and Miscellaneous Acknowledgments
26. Did a representative of the Bidder attend the Pre-Bid Examination on 11:30 A.M., Tuesday, February 11, 2025
27. Did a representative of the Bidder conduct a field review to review the project scope of work? If yes, list the dates and times of each visit.
28. After a thorough review of the “Project Scope of Work and Requirements”, including the Project Summary, Abatement Activities, Abatement Requirements, Additional Requirements and Information and the Time Schedule, did the Bidder note any project scope of work discrepancies or omissions?
29. Did the Bidder review and understand the “General Procedures for Asbestos Abatement”, specifically the procedures outlined for asbestos pipe insultation, flooring removal including mastic removal by mechanical means, glovebag removal activities, full-containment removal activities, decontamination, and exterior spot removal activities?
30. Did a representative of the Bidder review the Project Notifications section? Will the Contractor be able to submit the notification prior to the start of the project? Please provide any conditions relevant to the project notification.
31. Did a representative of the Bidder review the information regarding insurance and bonding? Does the
Bidder understand that the project cannot begin until the requested Certificate of Insurance and the Performance/Payment Bonds have been submitted and approved?
32. Does the bid provided by the Bidder contain any work scope adjustments or qualifications, such as locations of material/quantity inconsistencies or locations of omitted materials?
33. Does the bidder offer any discounts for multiple school awards? If yes please specify please provide a detailed breakdown of the proposed alternate bid.
34. Are there any submittals that the Contractor will not be able to submit prior to the start of the project?
35. Please list all work hour restrictions that the Bidder proposes, such as days the Contractor will not work in the event of meeting the project schedule.
36. Please provide a summary of all bid limitations.
Additional Information
37. Please provide a Bidder’s Statement of Qualifications for all sub-contractors who will be used on this project. (A subcontractor does not include suppliers). Subcontractors not listed in this response will not be allowed for use on the project without the expressed written permission of TEC and the Owner.
38. Please feel free to provide any additional information which may assist the Owner and TEC with a complete and thorough evaluation of the bids including proposed alternates.
SECTION II
PROJECT SCOPE of WORK and REQUIREMENTS
HSPS as part of a Three (3) year Bond Project will be conducting asbestos/hazardous material abatement prior to planned demolition/renovations for the Summer of 2025. The following bid items identify the work at one of the four schools scheduled for work as part of the bond program. The schedule to accomplish abatement and required access demolition activities totals 25 work days. It is the intent of the HSPS to expedite contracts to accommodate the compressed schedule.
A work plan must be submitted as an element of the bid. Bids not accompanied by a workplan will be considered incomplete. At minimum the work plan shall include the following:
• type of enclosure system;
• negative pressure design including NAM placement and containment exhausting locations configuration of containment system;
• non-permit entry confined space attainment/maintenance
• removal techniques;
• waste handling procedures;
• decontamination procedures;
• proposed landfill including type, name, and address;
• schedule including man-power loading;
• Emergency Planning Procedures (see Section 8.0 of these specifications):
• and personal air monitoring practices.
The work plan submitted with the bid will be utilized to qualify the bid. Awards will be made to the lowest, qualified bidder for each element of work. The Contractor must qualify their cost estimate by providing the elements of the work plan above. A bid not supported by a work plan addressing the elements above will not be evaluated.
- Bid No. 19.01 - The High School Project Scope of Work
This project summary provides a summary of the asbestos-containing materials and non-asbestos-containing materials which will be removed as part of the bid. The scope of work, project requirements and project schedule are provided in the specification documents. The Contractor is encouraged to review all aspects of the scope-of- work when preparing the bid and is instructed not to use this summary when preparing this bid.
[ABATEMENT]
19.01 High School, ACM Abatement
The abatement at the High School includes the removal of asbestos containing floor tile/mastic, carpet over suspected asbestos containing floor tile and/or mastic, stair tread, and fire doors, from various locations. The abatement at High School will require negative pressure enclosure(s), as delineated in the bidders required workplan. The accessible work hours allow for a M-F, 7AM to 5PM schedule to complete the project. Double shifts, extended hours, and/or weekend/holiday hours must be included in the proposed work plan and approved by the Owner.
• 12”x 12” Floor Tile/Mastic in the Wood Shop building – 4,400 Square Feet (SF)
• One tagged fire door – Men’s Gymnasium Locker Room
• Carpet/12” / 12” Floor Tile and Stair Tread over suspected asbestos containing floor tile/mastic in the Academic Wing- 60,000 SF; Carpet and Floor Tile has been installed over known/verified asbestos containing floor tile and/or mastic.
All 60,000 SF of the carpet, floor tile and stair tread are to be removed within a regulated area. In the event that the carpet, floor tile and/or stair tread results in the incidental removal of asbestos containing floor tile beneath it, then the containment requirements will need to be re-evaluated based on the quantity, location and type(s) of asbestos containing materials found. Extensive investigation of the conditions regarding this issue have been undertaken by TEC. It is TECs opinion that there is no tile beneath the carpet, floor tile and/or stair tread. However, TEC can not rule out the possibility of some floor tile and it more likely that some of the areas will have asbestos containing mastic.
As indicated above the initial containment shall consist of barrier tape, signage, critical path barriers, and approximately 3 negative air machines venting outside per floor. In the event that asbestos containing floor tile and/or mastic is encountered the containment requirements will be adjusted and unit price compensation will apply to additional removal of asbestos containing materials beneath the 60,000 SF of non-asbestos containing carpet, floor tile and stair tread. Where asbestos containing mastic is encountered the removal process will involve grinding to clean concrete and TEM clearances. It is not expected that asbestos containing floor tile with no asbestos containing mastic will be encountered.
Abatement Requirements:
The Contractor will be allowed to construct multiple negative pressure enclosures for the complete removal of all of the materials detailed in the “Abatement Activities” for subject schools.
1. The Contractor is responsible for all of the materials listed in the scope of work, as well as depicted on the attached drawings. When present in, connected to or adjacent to the room, materials located in bathrooms, closets, storage rooms, below fixtures (such as radiators, cabinets and bookcases), behind furniture and inside sink cabinets, flooring materials are included. for certain areas are listed below:
• Mastic beneath structures: The Contractor will remove all asbestos containing mastic beneath structures including but not limited to, closets, cabinets, equipment, etc.
2. The regulated areas will be emptied of all furniture, furnishings and moveable objects prior to the start of the project.
The Owner will complete this activity. The Contractor will be responsible for any materials below fixed cabinets, shelving units, counters, etc. left in place prior to the start of the project.
3. The exact routing of projects and configuration of the number of regulated areas/combination of functional spaces will be coordinated on-site. When possible, adjoining functional spaces will be combined into a single regulated area. Each negative pressure enclosure constructed to address asbestos abatement in this project group will be set-up in accordance with the following minimum guidelines prior to the start of any abatement activities:
• Critical barriers, constructed of a minimum of one (1) layer of six-mil polyethylene sheeting, will be set-up over all access points to non-project areas, such as doors to adjoining rooms/hallways and exterior doors/windows. Asbestos warning signs will be placed on the non-project side of the critical barrier when necessary to prohibit entrance. No access will be made from these locations into the project area at any time (except through the decontamination chamber).
• Critical barriers, constructed of a minimum of one (1) layer of six-mil polyethylene sheeting, will be placed over all ceiling return vents, bookcases, lockers and all items which cannot be decontaminated in each of the project area spaces. Critical barriers, constructed of a minimum of two (2) layers of six-mil polyethylene sheeting, will be placed over all in ceiling vents.
• A semi-permanent barrier consisting of 2”x 4” studs, plywood walls and lockable entry door will be erected within the High School hall at the entrance to Unit A. Specifically, the barrier will be erected by the awarded contractor at the only interior entrance to Unit A. This barrier is to remain upon completion of abatement activities. The barrier should include one lockable door. On the Unit A side of the barrier the critical barrier requirements above will apply.
• A minimum of one (1) air filtration device (AFDs) will be required in each functional space in excess of 400 square feet. This minimum number of machines is desired to create a minimum negative pressure of 0.02 inches of water equivalent, sufficient air changes and appropriate air flow through the enclosure. The Contractor will be responsible for properly securing the exhaust tubes in any exterior windows and/or doors used for exhaust locations.
• A three-stage decontamination chamber will be required for this project. The decontamination chamber will be connected at a location convenient to building access and waste out activities and will be coordinated on-site. A black polyethylene barrier will be placed in front of the decontamination chamber to provide an additional visual barrier to the work area.
• The construction of a bag-out chamber will be permitted. The exact location, set-up, position and construction of the bag-out chamber must be reviewed with Testing Engineers and Consultant’s Project Coordinator. Bag out chambers set-up without the review and approval of Testing Engineers and Consultants will be sealed and/or torn down at the discretion of Testing Engineers and Consultants.
• Visual barriers, constructed of a minimum of one (1) layer of black polyethylene sheeting, will be set-up at various locations to provide an additional visual barrier to the work area. The exact number and locations will be determined on site, based on building occupancy and usage patterns.
4. All asbestos containing mastic abatement activities will be completed in accordance with all applicable provisions of the
OSHA Asbestos Standard (1926.1101(g) - “Methods of Compliance”).
5. All asbestos-containing materials must be removed using wet methods and then bagged and sealed immediately. Bags will be randomly checked as they are transported from the enclosure and double bagged. All bags determined to not be adequately wet will be sent back into the enclosure. No bags may remain open inside the enclosure. The Contractor will be permitted to leave sealed bags inside the enclosure overnight. All bags must be removed from the enclosure prior to the start of the visual inspection.
6. All surfaces inside the enclosure will be fully washed with a combination of wire brushing, rinsing, wet- wiping and HEPA vacuuming during the final cleaning portion of the project. During final cleaning activities, the ceiling will be rinsed and then encapsulated during the lock down portion of the project.
7. At the conclusion of the final cleaning activities in the enclosure, a visual inspection will be completed in accordance with the listed “Visual Inspection Procedures” (Item #4, “General Requirements and Information”).
Final Clearance Sample Requirements:
TEM Clearance Air Samples Each of the regulated areas established for the removal of the materials described in subject schools will be cleared using Transmission Electron Microscopy (TEM). Pursuant to the requirements of AHERA, five (5) TEM samples will be collected from each regulated area. All five samples must be analyzed below and average of 70 structures to allow for tear down of the enclosure. All TEM air samples will be collected in accordance with the AHERA regulation and all EPA recommended guidelines.
Project Schedule:
The Contractor may begin mobilization and setup activities on Monday, June 16, 2025, and will be complete with all abatement activities, including tear down activities, by the end of the day on Friday, July 18, 2025. The project schedule allows for a total of five (25) work days (Monday-Friday) to complete the project. Additional project dates include:
School Location ACM Removal Start Ready for Clearance End # of Work Days
High School
Phase I – Unit A 1st Floor and West half of 2nd Floor
6.16.25, 7 AM 6.25.25, 10 AM 6.27.25 5 PM 10
High School
Phase II – Unit A 2nd Floor, West Half and 3rd Floor
6.25.25, 7 AM 7.9.25, 10 AM 7.11.25 5 PM 10
High School
Wood Shop 7.9.25, 7 AM 7.16.25, 10 AM 7.18.25 5 PM 5
High School
1 Fire Door and Frame- Unit C, East Entrance To Boys Locker Room
TBD TBD TBD
½ day during above
25 day schedule
Schedule Restrictions - Set-up:
The Contractor will not be allowed to mobilize to the project site for summer work until 7:00 a.m. on Monday, June 16, 2025.
Project Diagrams:
The project diagrams identifying location of asbestos containing material removal have been included in Appendix B.
General Requirements and Information