Q A.docx
DOCX document 13 KB Posted
- Attached to
- Residential Security Upgrade
- Solicitation number
- SUG50015R0010
- Issued by
-
Department of State US Embassy Kampala
About this file
Response to questions rasied during the site visit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Residential_Security_Upgrade.doc | DOC document | |
| Residential_Security_Upgrade__Final.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A FROM SITE VISIT
Question: Window film was not discussed during the walk through of the sample house.
Answer: Go ahead and quote for installation as requested in the solicitation document
Question: Is the window film provided by the US government.
Answer: Yes. Window film is government furnished property (refer to exhibit 5 in the solicitation document)
Question: Is the kick activator for the escape egress government furnished property?
Answer: The kick activators are government furnished property.
Question: The solicitation document says the vendor shall provide other supplies. What are these supplies?
Answer: Any supplies not on the government furnished property that are necessary to complete the works are responsibility of the vendor e.g. Brushes, welding rods, etc.
| Question: | Is there a completion period? |
| Answer: | The completion document is stated in the solicitation document. The Contractor shall complete all services on individual housing units within ten (10) calendar days of receipt of a task order. Any deviation will be in writing from the Contacting Officer. |
File details come from the government source that posted it. Updated .