From: Susan Phemister Re: Questions from pre-proposal conference for STZ20016Q0003 held on July 26, 2016 Date: July 27, 2016
The questions below were asked and answered at the pre-proposal conference for STZ20016Q0003, held on July 26, 2016 at the U.S. Embassy Dar es Salaam, and are hereby provided to all bidders.
Q. Is a list of generators provided?
A. Yes, it is provided in the posted RF Q. What is the condition of the generators?
A. All generators on the list are in good, working condition.
Q. Is a sensor system currently installed on the generators?
A. No, no sensor system is currently installed on the generators.
Q. What is the time frame to provide emergency service?
A. As stated in the RFQ, contractor shall provide emergency service within 3 hours of a call.
Q. What do we do if we don’t have a backup generator large enough for your largest generators? It’s very expensive to keep a large generator on standby.
A. Note in your proposal what you are able to provide for your backup generator(s).
END.