Structured Cabling RFP Use this.pdf
PDF 352 KB Posted
- Attached to
- Structured Fiber Cabling
- Solicitation number
- RFP-NCS-260000000125-1
- Issued by
- Berrien County, Michigan
About this file
This is a Request for Proposals (RFP) for Structured Fiber Cabling issued by Novi Community School District in Michigan for the fiscal year 2026/2027. The district is seeking proposals for structured fiber cabling installation across nine school buildings, including Deerfield Elementary, Novi Middle School, Novi Woods Elementary, Orchard Hills Elementary, Parkview Elementary, Village Oaks Elementary, Maintenance and Operation, Novi Community Schools Maintenance, and Transportation Building. The project involves installing a total of 21 fiber cable runs between building IDF locations, with specific requirements for fiber type (12 strand 10GbE Single-Mode Armored/Plenum Fiber), and will also include three new rack installations. The RFP was released on October 15, 2025, with a mandatory walkthrough scheduled for November 5, 2025, and sealed bids due by December 9, 2025. The installation period is set for July 1, 2026 through September 30, 2026.
The project is funded through the Universal Service Fund (USF) E-Rate program, with the district's Form 470 number 260002335. Bidders must comply with E-Rate requirements, including providing the lowest corresponding price and detailing all eligible and ineligible products. The RFP requires a 5% bid bond for bids over $25,000, comprehensive documentation including testing results, and a three-year warranty on the cabling system. Bidders must provide detailed documentation, including as-built diagrams, testing results, and warranty information. The district reserves the right to award different portions of the project to separate vendors and will evaluate bids based on price, product quality, service, delivery, and past performance, with a focus on technical experience and support in educational environments.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Novi Community School
District 25425 Taft Road Novi, MI 48375
Request for Proposals
Structured Fiber
Cabling Request For Proposal Year: 2026/2027
FY2026 E-Rate FORM 470 – 260002335
School District Contact:
Jason Smith, Director of Technology Technology Department Phone: 248.297.1346 E-mail: jason.smith@oakland.k12.mi.us
Prepared by:
Triple R Consultants
P.O. Box 302 South Lyon, MI 48178
Phone: 810.923.9290 E-mail: bob@triple-r.us
Novi Community School District
FY2026 Fiber Structured Cabling RFP-260002335 10/16/2025 ii
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
Contents
REQUEST FOR PROPOSALS – STRUCTURED CABLING
1.0.0 INVITATION TO BID
2.0.0 BIDDER INSTRUCTIONS
3.0.0 GENERAL CONDITIONS
4.0.0 UNIVERSAL SERVICE FUND (USF) CONDITIONS
5.0.0 SCOPE OF WORK
6.0.0 TIMELINE REQUIREMENTS
7.0.0 AWARDED CONTRACT REQUIREMENTS
PRODUCTS AND SERVICES SPECIFICATIONS
8.0.0 STRUCTURED CABLING SPECIFICATIONS
9.0.0 HORIZONTAL DISTRIBUTION SUBSYSTEM
10.0.0 SYSTEM DOCUMENTATION
APPENDIX A – INTENT TO BID FORM
APPENDIX B – BID SIGNATURE PAGE
APPENDIX C – BILL OF MATERIALS TOTALS
APPENDIX D - FAMILIAL DISCLOSURE AFFIDAVIT
APPENDIX E - IRAN LINKED BUSINESS AFFIDAVIT
APPENDIX F – PREVAILING WAGE
FY2026-RFP Fiber Structured Cabling-260002335 10/16/2025 3
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
REQUEST FOR PROPOSALS – STRUCTURED CABLING
1.0.0 INVITATION TO BID
1.1.0 BID ACCEPTANCE
Novi Community School District, hereby known as “District”, will accept sealed responses (“Bids”) to this Request for Proposals (RFP) for Structured Cabling projects which comply with the Invitation to Bid, Bidder Instructions, General Conditions, Universal Service Fund (USF) Conditions, Scope of Work, Timeline Requirements, Awarded Contract Requirements, and Products and Services Specifications set forth below and submitted to the District at the following address:
Novi Community School District
Educational Services Building – Attention: Jason Smith
25425 Taft Road
Novi, MI 48374
1.2.0 INTENT TO BID FORM
All Bidders must complete and submit the Intent to Bid Form, Appendix A, no later than November 05, 2025. The Bidder shall be responsible for the timely delivery of the Intent to Bid Form. The Bidder shall make no additional stipulations on the Intent to Bid Form or qualify their Bid in any other manner.
1.3.0 FACILITIES/BUILDING WALKTHROUGH
All Bidders are encouraged to attend a walkthrough meeting at the facilities and buildings where the structured cabling will be installed. The walkthrough meeting will begin promptly at the time specified whereby any/or all questions regarding the structured cabling project will be answered by the District. The walkthrough meeting is scheduled for 2:00 PM on November 05, 2025 at Educational Services Building, 25425 Taft Road, Novi, MI 48374.
1.4.0 ADDENDUM QUESTIONS
All Bidders must complete and submit all major addendum questions by November 05, 2025.
2.0.0 BIDDER INSTRUCTIONS
2.1.0 BID OPENING
All Bid responses to this RFP must be in duplicate in a sealed opaque envelope labeled as follows:
Structured Cabling - FY2026 USF Bid and “December 09, 2025”. The bidder must also include an electronic copy of all bid materials on a flash drive as well as the paper copies.
2.1.1 No oral, telephonic, telegraphic, e-mail or facsimile Bids will be considered.
2.1.2 No Bids will be considered after 2:00 PM, December 09, 2025.
2.1.3 The Bidder shall be responsible for the timely delivery of the Bid; the District shall not be liable to any Bidder for any delivery or postal delays and postmarking to the bid opening date will not substitute for receipt of the Bid
2.1.4 All timely submitted Bids received by the District will be opened at the Educational Services Building, 25425 Taft Road, Novi, MI 48374 at 2:00 PM, December 09, 2025 for recommendation to the Board of Education at a future regularly scheduled meeting.
2.1.5 If the District is closed due to unforeseen circumstances on the bid opening date, Bids will be due on the next day that the District is open.
2.2.0 BID BONDS
The Bidder shall submit a five percent (5 %) Bid Bond, of the total base Bid price, made payable to Novi Community School District, with the sealed Bid. No Bid Bond is required if the total base Bid price is less than twenty-five thousand dollars ($25,000.00). Any Bids for $25,000.00 or more received without a Bid Bond will be rejected by the District.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 4
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
2.3.0 CLARIFICATIONS AND CORRECTIONS
Direct any and all questions regarding this RFP by email to: Jason Smith, at: jason.smith@oakland.k12.mi.us. The resulting answers, along with the questions shall be posted on USAC website.
2.4.0 GENERAL REQUIREMENTS
2.4.1 The District or its representatives shall not be held responsible for expenses incurred in the preparation or subsequent presentation of the Bid response.
2.4.2 This RFP for Structured Cabling is not an offer to enter into a contract, but rather a solicitation for Bids.
2.4.3 The Bidder shall supply, upon request, samples and/or brochures of the proposed materials and equipment with the Bid.
2.4.4 The District shall provide, upon request and at the Bidders’ expense, blueprints and/or drawings associated with this project.
2.4.5 The District reserves the right to reject Bids submitted without a five percent (5%) Bid Bond, signed Bid Signature Page, Bill of Materials, Familial Disclosure Affidavit, Iran Linked Business Affidavit, and list of four (4) references.
2.5.0 BID IDENTIFICATION REQUIREMENTS
The Bid shall include the full legal name of the Bidder, its business address, telephone number, and a statement identifying the Bidder as a sole proprietorship, partnership, corporation, or other legal entity. A proprietorship shall state the full name of the proprietor, a partnership shall state the full names of the general partners, and a corporation shall identify the state in which it is incorporated. Each copy of the Bid shall be signed by the person or persons legally authorized to bind the Bidder to a contract.
2.5.1 The Bidder shall complete and submit, along with the Bid, a Bid Signature Page, Appendix B, in long hand, in ink, by an authorized representative.
2.5.2 The Bidder shall complete and submit, along with the Bid, a Bill of Materials, Appendix C, summarizing the details of the Bid.
2.5.3 The submitted Bid shall include a Familial Disclosure Affidavit form, Appendix D, which is properly completed, signed by an authorized representative of the Bidder, and notarized with an affixed, raised notary seal.
2.5.4 The submitted Bid shall include a list of at least four (4) references, one (1) of which must be a school or school district, for similar work performed within the past three (3) years.
2.5.5 The Bid shall be accompanied by a sworn and notarized affidavit that represents and warrants that the bidder, including its officers, directors and employees, is not an “Iran Linked Business” within the meaning of the applicable Michigan Public Act No. 517 of 2012, and that in the event bidder is awarded a contract as a result of this RFP, the bidder will not become an “Iran Linked Business” at any time during the course of performing under the contract. The Board of Education will not accept a Bid that does not include the sworn and notarized Iran Linked Affidavit, Appendix E. Bids in non-compliance with this request are subject to rejection.
2.6.0 BLUEPRINTS AND DRAWINGS
Blueprints and/or drawings of the facilities will be made available to the Bidder by the District in the following manner:
2.6.1 The District shall provide drawings per request on the Intent to Bid Form. (Appendix A)
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 5
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
2.7.0 DEFINITIONS
The foregoing definitions are made available for the purpose of this Request for Proposals (RFP) only.
2.7.1 District – Novi Community School District
2.7.2 Bidder(s) – Business Entities and/or Person(s) submitting the Bid.
2.7.3 Bid(s) – A complete and properly executed proposal to perform the Scope of Work, or designated portion thereof, for the sums stated within the Bid.
2.7.4 Base Bid – The sum stated in the Bid for which the Bidder offers to perform the Scope of Work wherein work may be added or subtracted for sums stated in the Alternate Bid, if any.
2.7.5 Alternate Bid – An amount stated in the Bid to be added or subtracted from the amount of the Base Bid, if said change in the Scope of Work, method of construction and/or materials is accepted by the District.
2.7.6 Selected Vendor/Contractor – The Bidder(s) receiving formal notice of acceptance of his/her Bid(s) and has been duly served by an officer or agent of the District duly authorized to give such notice.
3.0.0 GENERAL CONDITIONS
3.1.0 RIGHTS OF ACCEPTANCE OR REJECTION
The District’s Board of Education reserves the right to reject any and all Bids in whole, or in part, and accept any Bid or portion of the Bid that, in their opinion, best serves the interests of the District.
3.2.0 QUALIFICATION OF BIDDERS
For the purpose of assuring the District of the quality of workmanship, materials, products and/or services, the Board of Education will retain the right and has complete discretion to qualify or disqualify any Bidders on the basis of available information concerning the Bidder’s ability to perform as needed and the suitability of the products and/or services included in the Bid as described in sections 3.4.0 and 3.5.0. Each Bidder, by submitting a Bid, represents that:
3.2.1 The Bidder has read and understands all the Bid requirements, conditions and specifications contained herein.
3.2.2 The Bidder has the option to visit the District work site and familiarize themselves with the local conditions under which the work is to be performed.
3.2.3 The Bid is based upon the materials, systems and equipment described, without exception, in all Bid documents supplied by the District.
3.3.0 VARIANCE AND PRICE
Any variance from the specifications in section 8.0.0 of this RFP must be fully explained in writing by the Bidder.
All prices quoted in the Bid must be on a unit price basis and include the total price. The price of an item or unit of a given product as promised in a Bid cannot be changed by the service provider regardless of whether the District changes the quantity of the item or unit needed.
3.4.0 MANUFACTURER(S) BRANDS/MODEL NUMBERS
The naming of a manufacturer(s), brand or model number will not be considered as excluding other brands or model numbers for purposes of later providing the products as promised in the Bid. Specifically, similar products with comparable construction, material and workmanship will be considered as equal. Notwithstanding, the Board of Education of the District has complete discretion to evaluate the merits of all Bids submitted and can take into consideration the brand and/or model numbers set forth in the Bids.
3.5.0 DETAILED BILL OF MATERIALS REQUIREMENT
Vendors are strictly prohibited from including any line item for 'miscellaneous materials,' 'contingency,' 'unspecified parts,' or similar generic categories within their proposed bill of materials. All materials, components, and equipment must be itemized individually, including their specific manufacturer, manufacturer part number (SKU), unit cost, and quantity. Any bid containing a 'miscellaneous materials' line item or lacking the required specificity for all proposed materials may be considered non-responsive and may be grounds for immediate disqualification without further review.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 6
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
3.6.0 MANUFACTURER(S) SUBSTITUTIONS
Any substitution from the specified products and/or services by the manufacturer(s) is acceptable if at no additional cost to the District and approved by an authorized district representative prior to placing the order for said products and/or services. The District reserves the right to refuse any and all manufacturer(s) substituted products and/or services.
3.7.0 MANUFACTURER(S) DISCOUNTS
The District reserves the right to receive any and all manufacturer(s) price reductions, discounts or rebates that are received by the selected vendor/contractor for the specified products and/or services. The selected vendor/contractor agrees to pass any and all cost savings from the manufacturer(s) for the specified products and/or services to the District by way of a setoff of monies owed or refund of monies paid by the District.
3.8.0 CLEAN-UP
The selected vendor/contractor must, at all times, keep the premises free from accumulations of waste materials, caused by the work; and upon completing the work, must remove all work-related rubbish from and about the building(s) and must leave the work area broom clean, or its equivalent. In the case of a dispute, the District may remove the rubbish and charge the cost to the selected vendor/contractor.
3.9.0 ROYALTIES AND PATENTS
The selected vendor/contractor must pay for all royalties, copyright, trademark, and patents and must defend all suits for claims or infringements on copyrights, trademarks and/or patent rights and shall indemnify and hold the District harmless from any and all claims and/or loss related to claims and/or infringements on copyrights, trademarks and/or patent rights, including reasonable attorney fees and costs incurred by the District.
3.10.0 ADDENDA
Any clarifications or modifications to the specifications for the RFP will be issued by the District in the form of an addendum. Any addendum issued during the bidding time will become part of the specifications and a copy will be sent to all Bidders as set forth in section 2.3.0.
3.9.1 No verbal statements by the District will be considered binding or enforceable against the District.
3.9.2 No requests for clarifications or modifications will be processed after the date listed in Section 1.4.0.
3.11.0 FEDERAL, STATE AND LOCAL TAXES
All products and/or services furnished by the selected vendor/contractor must comply with all applicable federal, state and local codes, and regulations. All Bids must include, and the selected vendor/contractor must pay, all taxes levied by the Federal, State, and Local Governments, on both labor and materials. The District reserves the right to require evidence of such tax payments prior to final payment of the contract. The District is exempt from Federal Excise and State Sales Taxes. To comply with these regulations, sales tax is not to be included in the Bid.
3.12.0 PROJECT IMPLEMENTATION
The selected vendor/contractor shall have sufficient resources in order to complete the project within the allotted timeframe and shall, upon request, demonstrate that they have the resources necessary to fulfill the Timeline Requirements in section 6.0.0 of this RFP.
3.13.0 NO DISCRIMINATION
The selected vendor/contractor and their subcontractors are required not to discriminate against any employee or applicant for employment, to be employed in the performance of the Bid, with respect to hire, tenure, terms, conditions, or privileges of employment, because of race, color, religion, national origin, or ancestry or also because of age or sex, except based on a legitimate occupational qualification. Violation of this requirement may be regarded as a material breach of the Michigan Fair Employment Practices Act and may be subject to prosecution.
3.14.0 NO SMOKING POLICY
The District adheres to a mandatory no smoking policy on school premises and/or at school functions. All Bidders shall comply with this no smoking policy.
3.15.0 PRODUCTS AND SERVICES SPECIFICATIONS
It is the intent of the specifications in section 8.0.0 of this RFP to define the minimum acceptable quality of products and/or services. The product line must be of known quality from a nationally recognized manufacturer(s) who regularly advertises, promotes, and distributes products and services to the school market.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 7
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
3.16.0 VARIATIONS FROM SPECIFICATIONS
All variations from the specified products and/or services, section 8.0.0, must be fully explained and included with the Bid. Manufacturer(s) Brands must be used in all cases.
3.15.1 The District reserves the right to increase or decrease quantities or modify the specifications.
3.15.2 The selected vendor/contractor shall agree to a written modification of the terms of its original Bid within five (5) business days of receiving written notification of the increase or decrease in quantities, or modification of the specifications.
3.17.0 PARTIAL BIDS
Partial Bids will be considered, where appropriate.
3.18.0 CANCELLATIONS
The District reserves the right of cancellation for non-performance of the terms specified in the awarded contract.
3.19.0 WITHDRAWAL OF BIDS
Upon presentation of proper identification, any Bidder may withdraw his/her Bid at any time prior to the scheduled Bid Opening date and time, section 2.1.0. No Bid shall be withdrawn for a period of ninety (90) days after the Bid Opening date and time.
3.20.0 BID EVALUATIONS
Considerations for awarding contracts will include price, product quality, service, delivery, and maintenance of products and/or services, adherence to specifications, past performance to the District, vendor/contractor reliability, warranties and familiarity with the projects and the facilities of the District.
3.19.1 It is the intent of the District to award the contract to the Bidder submitting the “best” cost effective Bid for the project; provided the Bid has been properly submitted and delivered, including all required documentation herewith, and considered reasonable in price.
3.19.2 Price being the primary factor, consideration, other than price alone, shall be used in determining the most successful Bid; technical experience, local service and support, and experience in educational environments are used to perform the District’s Bid evaluations.
3.19.3 The Board of Education of the District will evaluate the merits of all Bids submitted and reserves the right to accept or reject any or all Bids.
3.21.0 NOTICE OF AWARD
The Bidder will be deemed as having been awarded when the formal notice of acceptance of his/her Bid has been duly served upon the intended awardees by an officer, or agent, of the District duly authorized to give such notice.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 8
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
4.0.0 UNIVERSAL SERVICE FUND (USF) CONDITIONS
4.1.0 IDENTIFICATION NUMBER
The service provider’s USF Service Provider Identification Number (SPIN) must be included in the Bid. Direct all questions regarding the USF requirements in this RFP to the Universal Service Administrative Company (USAC), Schools and Library Division (SLD) at (888) 203-8100.
4.2.0 FY2026 FUNDING REQUESTS
The specified products and/or services are to be provided for FY2026 (July 1, 2026-June 30, 2027) and must qualify for universal service discounts under the FY2026 universal service support mechanism, E-Rate. The E-Rate
Modernization Order permits applicants to seek support for Category 2 eligible non-recurring services purchased on or after April 1, three months prior to the start of the funding year on July 1. No invoices to USAC/SLD will be DATED or PAID before July 1, 2026.
4.3.0 UNIVERSAL SERVICE DISCOUNTS
The service provider contract is conditional upon the District receiving universal service discounts under the FY2026 universal service support mechanism, E-Rate. The District reserves the unrestricted right to reduce the contract amount by reducing the amount of services and/or products in order to meet budget requirements in the event the level of the universal service discounts is reduced. Any such reductions to the contract amount will be made prior to the start of the specific work being reduced or eliminated on a given building and/or project.
4.4.0 UNIVERSAL SERVICE DISCOUNT IMPLEMENTATION
The District reserves the unrestricted right to specify the filing option for the universal service discounts for each product and/or service offered within a Bid: Billed Entity Applicant Reimbursement (BEAR) or Service Provider Invoice (SPI).
4.5.0 ELIGIBLE PRODUCTS AND SERVICES
The USF eligible products and/or services identified on the USAC FY2026 Eligible Services List, which is incorporated herein by reference, must be identified separately from any and all “ineligible” products and/or services in the Bid.
4.6.0 PROJECT FUNDING REQUIREMENTS
This project is entirely conditional upon receiving written notification in the form of a Funding Commitment Decision Letter from the USAC/SLD that the District has been approved for E-Rate Funding. If the District receives less than the full E-Rate Funding for which it applies, the District has the unrestricted right to reduce the number of units and services in the accepted Bid. In the event that E-Rate Funding is not available for the accepted Bid, District, in its discretion, may cancel and/or modify the Scope of Work (SOW) and subsequent purchases requested in this RFP.
4.7.0 DETAILED BILL OF MATERIALS REQUIREMENT
Vendors are strictly prohibited from including any line item for 'miscellaneous materials,' 'contingency,' 'unspecified parts,' or similar generic categories within their proposed bill of materials. This requirement is mandated directly by the Universal Service Administrative Company (USAC) for all services funded through the Universal Service Fund (USF). USAC requires that all materials, components, and equipment be itemized individually, including their specific manufacturer, manufacturer part number (SKU), unit cost, and quantity, to ensure the verifiability, eligibility, and proper accounting of USF dollars. Any bid containing a 'miscellaneous materials' line item or lacking the required specificity for all proposed materials may be considered non-responsive and may be grounds for immediate disqualification without further review, as it prevents our ability to comply with USAC's auditing and funding requirements.
4.8.0 LOWEST CORRESPONDING PRICE
Lowest Corresponding Price (LCP) is defined as the lowest price that a service provider charges to non-residential customers who are similarly situated to a particular E-Rate applicant for similar services. Service Providers cannot charge E-Rate applicants a price above the Lowest Corresponding Price (LCP) and must actually charge the rate that is the LCP, not just offer the LCP in the Bid. In addition, promotional rates offered by a Service Provider for a period of more than 90 days must be included among the comparable rates upon which the LCP is determined.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 9
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
5.0.0 SCOPE OF WORK
5.1.0 GENERAL DESCRIPTION
The general description of the Scope of Work (SOW) for this project is to provide the District with Structured Cabling at seven (9) nine school buildings. In addition to the forgoing SOW, all Bids must comply with all sections of this RFP and the Products and Services Specifications set forth in sections 8.0.0 through 11.0.0.
5.2.0 FACILITIES/LOCATIONS
Building Name Address City State Zip
Deerfield Elementary 26500 Wixom Road Novi MI 48374
Maintenance and Operation 45495 Eleven Mile Road Novi MI 48374
Novi Community Schools Maintenance 45495 11 Mile Rd Novi MI 48374
Novi Middle School 49000 Eleven Mile Road Novi MI 48374
Novi Woods Elementary School 25195 Taft Road Novi MI 48374
Orchard Hills Elem School 41900 Quince Novi MI 48375
Parkview Elementary School 45825 Eleven Mile Road Novi MI 48374
Transportation Building 45505 West Eleven Mile Road Novi MI 48374
Village Oaks Elementary School 23333 Willowbrook Novi MI 48377
5.3.0 VENDOR/CONTRACTOR RESPONSIBILITY
It shall be the responsibility of the selected vendor/contractor to provide the configuration and system quantities to all locations stated herein. The intentional or accidental omission of necessary component(s) or system(s) shall require the selected vendor/contractor to supply said missing component(s) or system(s) at no cost to the District. The District and any Consultants associated with this RFP are not responsible for any omission, failure to detect any requirement, or any other condition required to complete the Scope of Work. The awarded Bidder shall:
5.3.1. Meet jointly with representatives of the District to exchange information and agree on details of equipment arrangements and installation interfaces for a structured cabling project.
5.3.2. Have sufficient resources in order to complete the SOW within the allotted timeframe and shall, upon request, demonstrate that they have the resources necessary to complete the SOW within the specified timeframe.
5.3.3. Furnish all labor, supervision, tooling, and miscellaneous mounting hardware and consumables for the structured cabling system installed at the District.
5.3.4. Furnish, install, and terminate data jacks at each location according to the Product and Services Specifications and as shown on the supplied existing blueprints/drawings.
5.3.5. Abate any existing cable in each building, where applicable, and will properly dispose of such cable at the Bidder’s expense.
5.3.6. Install all cable in accordance with the Product and Services Specifications and/or manufacturer’s recommendations and best industry practices.
5.3.7. Develop and submit for approval a labeling system for the cable installation. At a minimum, the labeling system shall clearly identify all components of the system; racks, cables, panels, and outlets.
5.3.8. Test (100%) all cables and termination hardware for defects in installation and to verify cable performance under installed conditions.
5.3.9. Install a fire stop system in accordance with the specifications and/or manufacturer’s recommendations which shall be completely installed and available for inspection by the local inspection authorities prior to cabling system acceptance.
5.3.10. Provide installation, administration, testing, and “As-Built” documentation required from and/or maintained by the selected vendor/contractor during the course of the entire cabling installation project.
5.3.11. Provide a written guarantee/warranty covering the installed cabling system against defects in workmanship, components, and performance, and follow-on support after project completion for a period of three (3) years.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 10
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
5.4.0 BILL OF MATERIALS SUBMISSION
Vendors must provide a comprehensive and detailed bill of materials for all proposed structured cabling components and equipment. Each item must be individually listed with its manufacturer, manufacturer part number (SKU), unit cost, and quantity. Bids including generic line items such as 'miscellaneous materials' or 'contingency' will be subject to heightened scrutiny and may be rejected if the specific components cannot be clearly identified and validated for E-Rate eligibility. Vendors are strongly encouraged to ensure all materials are explicitly itemized to avoid delays or disqualification.
5.5.0 FIBER CABLING QUANTITIES
All fiber runs will be placed in a metal raceway or may use existing conduit, where appropriate.
5.5.1 Fiber Cabling
The District is accepting Bids for a total of (21) twenty-one fiber cable runs between the building IDF locations connecting back to the building MDF in the locations listed in the table below. The fiber must be capable of a minimum 10Gbps connection speed. The Bid shall include all necessary patch cables and materials to complete the fiber cabling project. Any and all USF E-Rate “ineligible” products and/or services must be listed separately in the Bid.
Building Name Description Distance
Deerfield Elementary IDF1
12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2)
~225 ft.
Deerfield Elementary IDF2 ~375 ft.
Deerfield Elementary IDF3 ~555 ft.
Novi Middle School IDF1
12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2)
~630 ft.
Novi Middle School IDF2 ~210 ft.
Novi Middle School IDF3 ~575 ft.
Novi Middle School IDF4 ~325 ft.
Novi Middle School IDF5 ~730 ft.
Novi Middle School IDF6 ~540 ft.
Novi Woods Elementary IDF1 12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2) ~220 ft.
Orchard Hills Elementary IDF1
12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2)
~265 ft.
Orchard Hills Elementary IDF2 ~305 ft.
Orchard Hills Elementary IDF3 ~290 ft.
Parkview Elementary IDF1
12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2)
~335 ft.
Parkview Elementary IDF2 ~230 ft.
Parkview Elementary IDF3 ~525 ft.
Parkview Elementary IDF4 ~550 ft.
Village Oaks Elementary IDF1
12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2)
~250 ft.
Village Oaks Elementary IDF1 ~210 ft.
Village Oaks Elementary IDF1 ~280 ft.
Maintenance and Transportation IDF1 12 strand 10GbE Single-Mode Armored/Plenum Fiber (OS2) ~140 ft.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 11
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
5.5.2 Fiber Cabling Notes
The District is accepting Bids for a total of (21) twenty-one fiber cable runs between building IDF locations connecting back to the building’s MDF. Detailed notes about the new and existing fiber runs, as well as the district MDF and IDF closets are outlined below.
Building Name Notes Existing
Enclosure
2M SC-LC
Patch Cables
Needed
Deerfield Elementary MDF Combine WAN into enclosure with IDF's. 4U 8
Deerfield Elementary IDF1 In mech loft on 2nd floor, follow ladder rack and existing pathways.
1U 2
Deerfield Elementary IDF2
This IDF is in the mechanical loft on the 2nd floor.
The pathway is through the hallway to the main office, and then across the drywall and around the circle dome ceiling into the glassed-in display room and then back to the hallway to the MDF.
1U 2
Deerfield Elementary IDF3
Follow the IDF 2 pathway through the hallway to the main office and then across the drywall and around the circle dome ceiling into glassed-in display room and then back to the hallway to the MDF.
1U 2
Novi Middle School MDF Combine WAN into enclosure with IDF's. Note that the Deerfield Elementary run with ST ends passes through Novi Middle School MDF.
6U 14
Novi Middle School IDF1 1U 2
Novi Middle School IDF2 This IDF is in the loft mechanical room. 1U 2
Novi Middle School IDF3 This IDF is in the loft mechanical room. 1U 2
Novi Middle School IDF4 1U 2
Novi Middle School IDF5 If short drywall ceiling space at edge of cafeteria ceiling is inaccessible, use pathway around cafeteria.
1U 2
Novi Middle School IDF6 1U 2
Novi Woods Elementary MDF Combine WAN into enclosure with IDF's. 2U 4
Novi Woods Elementary IDF1 1U 2
Orchard Hills Elementary MDF Combine WAN into enclosure with IDF's. 4U 8
Orchard Hills Elementary IDF1 1U 2
Orchard Hills Elementary IDF2 Single post rack hardware required. 1U 2
Orchard Hills Elementary IDF3 Single post rack hardware required. 1U 2
Parkview Elementary MDF Combine WAN into enclosure with IDF's, move existing single-mode fiber from separate enclosures to IDF 5/6 into new enclosure.
6U 12
Parkview Elementary IDF1 Single post rack hardware required. 1U 2
Parkview Elementary IDF2 Single post rack hardware required. 1U 2
Parkview Elementary IDF3 1U 2
Parkview Elementary IDF4 1U 2
Parkview Elementary IDF5 Remove existing fiber from existing IDF 5 enclosure in lower section of the rack and relocate to new the 6U enclosure.
n/a 1
Parkview Elementary IDF6 IDF 6 passthrough from IDF 5. n/a 1
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 12
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
Village Oaks Elementary MDF Combine WAN into enclosure with IDF's. 4U 8
Village Oaks Elementary IDF1 This room has restricted workspace. 1U 2
Village Oaks Elementary IDF2 1U 2
Village Oaks Elementary IDF3 Demo all old fiber. 1U 2
Maintenance and Transportation MDF Combine WAN into enclosure with IDF's. MDF is inside of the Maintenance Building.
2U 4
Maintenance and Transportation IDF1 This IDF is inside of the Transportation Building. 1U 2
5.5.3 Racks
The District is accepting Bids for a total of (3) three racks for the project in the MDF and IDF locations below. Detailed notes about the new and existing fiber runs, as well as the district MDF and IDF closets are outlined below. The Bid must also include any necessary mounting hardware, labor to move existing wiring in old rack to new rack, and any required hardware to move wiring. This service is for the time period from July 1, 2026 through June 30, 2027. Any and all USF E-Rate “ineligible” products and/or services must be listed separately in the Bid.
Location Manufacturer Part Number Description Qty
Parkview Elementary
IDF3
Tripp-Lite (or equivalent) SRW26USDPG SmartRack 26U UPS-Depth Wall-Mount Half-Height Rack Enclosure, Hinged Back
Parkview Elementary
IDF4
Tripp-Lite (or equivalent) SRW26USDPG SmartRack 26U UPS-Depth Wall-Mount Half-Height Rack Enclosure, Hinged Back
Village Oaks Elementary
IDF2
Tripp-Lite (or equivalent) SRW26USDPG SmartRack 26U UPS-Depth Wall-Mount Half-Height Rack Enclosure, Hinged Back
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 13
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
6.0.0 TIMELINE REQUIREMENTS
6.1.0 PROJECT TIMELINE
The selected vendor/contractor shall have sufficient resources in order to complete the SOW, section 5.0.0, within the allotted timeframe and shall, upon request, demonstrate that they have the resources necessary to fulfill the timeline requirements for completing the entire project. The District is expecting the project to be completed in accordance with the following Project Timeline:
RFP available on-line or for pickup ............................................................................. [October 15, 2025]
Drawings are included as part of this RFP.................................................................. [October 15, 2025]
Walk Thru ....................................... [2:00 PM]. ......................................................... [November 05, 2025]
Sealed Bids Due .............................. [2:00 PM]. ......................................................... [December 09, 2025]
Sealed Bids Opened ........................ [2:00 PM]. ......................................................... [December 09, 2025]
Sign Contracts/approve Implementation Schedule ................................................. [December 19, 2025]
Installation Begins .......................... ..................................................................................... [July 01, 2026]
Installation Complete ..................... .......................................................................... [September 30, 2026]
6.2.0 SCOPE OF WORK SCHEDULES
If and when the school buildings specified in the SOW are occupied with students and school is in session, the selected vendor/contractor is expected to perform the project after school hours and without any additional costs to the District.
Areas of the school buildings that are otherwise unoccupied with students and whereby instruction is not disturbed, the selected vendor/contractor may perform the SOW with prior written authorization from the District.
6.3.0 PROJECT IMPLEMENTATION SCHEDULES
All Bidders shall provide the District with a project implementation schedule that adheres to the timeline requirements stated above, section 6.1.0. Further, the project implementation schedule must demonstrate that the selected vendor/contractor has the means and capability to complete the SOW without disruption to school building instruction, activities, and meetings. This said project implementation schedule must be agreed upon by both the vendor/contractor and the District and shall be incorporated as part of the awarded contract.
7.0.0 AWARDED CONTRACT REQUIREMENTS
7.1.0 CONTRACT EXECUTION
The Bidder shall render, deliver and execute the awarded contract within ten (10) days of being notified that the Bid is accepted and that the selected vendor/contractor is awarded a contract to perform the SOW in accordance with all terms and conditions contained herein. The awarded contract must be SIGNED and DATED by both the District and the awarded vendor/contractor prior to start of any work and in compliance with section 4.6.0.
7.2.0 SEPARATE CONTRACTS
The District reserves the unrestricted right to award different portions of the project, as broken out in the Bill of Materials, Appendix C, to separate vendors/contractors as separate contracts. Said separate contracts shall be based on the District’s evaluation and interpretation of the “most cost effective” means for the District to complete the SOW for this project.
7.3.0 CHANGES TO SCOPE OF WORK
The District, without invalidating the Contract, may order changes within the SOW consisting of additions, deletions, and/or modifications, the Contract Sum and the Contract Time being adjusted accordingly. All said changes in the SOW shall be authorized by written “Change Order(s)”, signed by the District, and will be executed under applicable condition of contract documents.
7.3.1 The Contract Sum and The Contract Time may be changed only in writing.
7.3.2 The cost or credit to the District from all “Change Order(s)” shall be determined by mutual, written, agreement.
7.3.3 The District will not pay invoices for work performed by verbal authorization.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 14
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
7.4.0 PERFORMANCE BOND REQUIREMENTS
The Bidder shall furnish a Performance Bond covering the faithful performance of the awarded contract and a labor and material payment Bond in the TOTAL amount of the Bid in such form and with such sureties as the District shall approve, which such approval will not be unreasonably withheld. If the selected vendor/contractor defaults, neglects or fails to perform any provisions of the awarded contract, the District may, at its discretion, and after seven (7) days written notice to the selected vendor/contractor, notify the bonding company that the selected vendor/contractor is in default.
7.4.1 The selected vendor/contractor shall provide, and maintain in force, a bond with surety, and on forms approved by the District in the amount of one-hundred percent (100%) of the contract amount that the selected vendor/contractor shall promptly and faithfully perform all obligations under the awarded contract.
7.4.2 The selected vendor/contractor shall provide and maintain, in force, a bond with Surety and on forms approved by the District that selected vendor/contractor shall make payment to all claimants for all labor and material used or reasonably required for use in the performance of the awarded contract.
7.4.3 Final Bid price may not exclude costs to secure or hold performance or bid bonds.
7.5.0 TERMINATION OF AWARDED CONTRACTS
If the selected vendor/contractor defaults or neglects to carry out the SOW and sections referenced therein, in accordance with the awarded contract and/or fails to perform any provision of the awarded contract, the District may, after seven (7) days’ written notice to the selected vendor/contractor and without prejudice to any other remedy it may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the selected vendor/contractor or, at its option, may terminate the awarded contract and take possession of the site and of all materials, equipment, tools, and construction equipment and machinery thereon owned by the selected vendor/contractor and may finish the project by whatever method it may deem expedient. If such expense exceeds such awarded contract price, the selected vendor/contractor shall pay the difference to the District.
7.6.0 EMPLOYMENT PRACTICES
The selected vendor/contractor, by signing a contract, agrees to comply with the provision of the State of Michigan policy regarding "Non-Discrimination of Employment", section 3.12.0.
The selected vendor/contractor shall also:
7.6.1 Provide all selected vendor/contractor employees with picture ID.
7.6.2 Upon arrival and departure, have all employees sign in and out at the main office for each school building location.
7.6.3 Supply the District, by email, weekly work schedules no later than the Wednesday of the preceding week.
Failure to do so may result in the schedule being rejected by the District.
7.6.4 The Selected Vendor/Contractor shall ensure that all of its employees, and any subcontractor employees, who will have direct and unsupervised access to students or who will be working on school property when students may be present, have undergone and passed a criminal history record check in compliance with the requirements of Michigan's School Safety Legislation (Public Acts 129, 131, and 138 of 2005).
7.6.5 The Selected Vendor/Contractor shall bear all costs associated with these background checks.
7.6.6 Prior to the commencement of any on-site work, the Selected Vendor/Contractor must provide the District with a written certification that all on-site personnel have successfully passed this screening and are cleared to work in a school environment.
7.6.7 The District reserves the right to deny site access to any individual who has not been cleared or for whom this certification has not been provided. Failure to comply with this requirement may be considered a material breach of the contract.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 15
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
7.7.0 SELECTED VENDOR/CONTRACTOR PERFORMANCE
The selected vendor/contractor will be responsible for construction means, methods, techniques, sequences or procedures, and safety precautions and programs in connection with the SOW, section 5.0.0, and the Timeline Requirements, section 6.0.0. The selected vendor/contractor shall also:
7.7.1 Provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, transportation, and other facilities and services necessary for proper execution and completion of the SOW.
7.7.2 At all times enforce strict discipline and good order among its employees and shall not employ any unfit person or anyone not skilled in the tasks assigned to them.
7.7.3 Give all notices and comply with all laws, ordinances, rules, regulations, and orders of any public authority bearing on the performance of the work performed.
7.7.4 Be responsible for the acts and omissions of all his employees and all Subcontractors, if any, their agents and employees and all other persons performing any of the work under a contract with the selected vendor/contractor.
7.8.0 SUBCONTRACTOR PERFORMANCE
A Subcontractor is a person, firm, company, or corporation who has a contract with the Bidder to perform any work for completing the project. The awarded Bidder shall be responsible for the actions, inactions, and work performed by the subcontractor. Contracts between the Bidder and the subcontractor shall be in accordance with the terms of the awarded contract by the District to complete the SOW, section 5.0.0. The selected Bidder shall furnish to the District, in writing, a list of any/all subcontractors proposed to perform any part or portion of the SOW to complete the project.
The selected Bidder shall not employ any subcontractor to whom the District objects and may withdraw their Bid or submit an acceptable substitute.
7.9.0 SUPPLEMENTAL INFORMATION REQUESTS
The Bidder shall be prepared to provide the District, within ten (10) days of being notified of the awarded contract, the names of the suppliers for the equipment and materials used to complete the work. The District may request any and all Bidders to also submit, within ten (10) days of being notified, the following:
7.9.1 The Bidder’s performance record(s).
7.9.2 An itemized list of the Bidder’s equipment, plant, and personnel.
7.9.3 The Bidder’s financial statement(s).
7.9.4 A description of any project which the Bidder has completed in a satisfactory manner.
7.9.5 Any additional information that will satisfy the District that the Bidder is adequately situated and able to fulfill the terms of the proposed contract.
7.9.6 A description of any other project(s) that will be performed simultaneously with the District’s project(s).
7.9.7 A statement regarding any past, present, or pending litigation for contracted products and services.
7.10.0 INSPECTIONS
The District and its agents have the right to inspect the selected vendor/contractor’s work periodically to determine that proper materials were used and that the progress and quality of work completed is in accordance with the contract.
7.10.1 Prior to the start of the projects, the selected vendor/contractor will have materials on site and available for inspection by the District’s designated authorized representative.
7.10.2 All equipment used for the project must be in compliance with the specified part numbers contained in the successful Bid.
7.10.3 Prior to completion of the work, all ceiling tiles will be left open until the District has inspected the work.
After said inspections, the selected vendor/contractor will replace all ceiling tiles.
FY2026-Fiber Structured Cabling RFP-260002335 10/16/2025 16
©2008 Confidential Proprietary intellectual property; use of this property is limited to RFP responses only.
Any other use of this property requires expressed written permission by Triple R Consultants.
7.11.0 INVOICE/PAYMENT REQUIREMENTS
Invoicing for payment(s) will be made 100% upon completion of the SOW and acceptance by the District. All invoices must be in compliance with the USF E-Rate Conditions, section 4.6.0. No invoices will be DATED or PAID before July 1, 2026. Payments will be paid NET 30 days AFTER:
7.11.1 Acceptance by the District of “AS-BUILT” diagram(s) in both paper and electronic copy, preferably Microsoft Visio.
7.11.2 Mandatory Tier 2 certification testing shall be performed and documented for one hundred percent (100%) of the installed fiber optic strands in accordance with the requirements outlined in Section 9.3.0 of this RFP.
Final test documentation, including all required OLTS results and OTDR traces, must be submitted and formally accepted by the District prior to final payment.
7.11.3 When applying for payments, the selected vendor/contractor shall submit to the District an itemized invoice based upon the installation schedule and supporting documentation required herein.
7.11.4 The project shall be considered complete when the SOW has been completed, accepted by the District and the following items are furnished; a) required guarantees, b) waivers of lien submitted showing all payrolls, material bills and other indebtedness connected with the project have been paid. The selected vendor/contractor must submit both a) and b) before the final payment is requested.
7.11.5 Payment may be withheld by the District for; a) defective work not remedied, b) claims filed and unresolved,
c) failure of the selected vendor/contractor to properly pay for labor, materials or equipment, or proper payment to Subcontractors, and/or d) damages to the District or another Contractor.
7.12.0 GUARANTEES
The selected vendor(s)/contractor(s) must furnish the District a written guarantee of the services and/or products provided to the district for, at least, three (3) years after the final payment covering all workmanship and materials specified in the contract. Any defects in workmanship or materials for which a claim is submitted by the District within the three (3) year period must be corrected or replaced within thirty (30) days.
7.13.0 WARRANTIES
The selected vendor/contractor(s) must furnish the District written warranty documentation. This warranty documentation shall include cable and connectivity components and have one (1) point of contact person for all cabling system issues, where applicable.
7.13.1 The selected vendor/contractor must warrant that all materials and supplies incorporated within the Bid, is new, unless otherwise specified,…
This is the start of the file's text. The full file is on GovTribe.