Storage Building RFP _ 2026.pdf

PDF 1 MB Posted

Attached to
CONSTRUCTION OF STORAGE BUILDING RFP
Solicitation number
PE-77037-NONST-2026-000000026
Issued by
Wilcox County, Georgia

About this file

This is a Request for Proposal (RFP) issued by the White County Board of Commissioners in Cleveland, Georgia for the construction of a storage building. The project involves the purchase, site preparation, and construction of a 35-foot wide by 100-foot long by 16-foot tall steel frame storage building with metal siding and roofing, including six bays with roll-up doors, electrical service, insulation, plumbing, and a restroom facility. The building will be located at 1235 Helen Highway behind the White County Board of Commissioners Building Complex. A mandatory pre-proposal meeting is scheduled for May 8, 2026 at 10:00 AM at the project site. Written questions must be submitted by 12:00 PM on May 12, 2026, with responses posted by 5:00 PM on May 15, 2026. Proposals are due by 3:00 PM on May 28, 2026. The selected contractor will be responsible for all design, engineering, surveying, permitting, and complete turnkey construction. Project duration should be completed in a timely manner as weather conditions allow, with the contractor required to submit a detailed schedule and timeline with milestones in the proposal.

Pricing proposals must be submitted separately and sealed, including all direct and indirect costs with an all-inclusive maximum price. The contractor shall provide a detailed cost estimate broken down by work areas. White County will evaluate proposals based on company background (15 points), personnel qualifications (20 points), relevant work performed (25 points), project approach (25 points), and pricing (15 points). The county reserves the right to negotiate with the apparent winner and reserves the right to reject any or all proposals. Performance and payment bonds equal to 100 percent of the awarded amount are required. Insurance requirements include statutory worker's compensation, comprehensive general liability of at least $1,000,000 per occurrence, and automobile liability of at least $500,000 per occurrence. Payment terms are negotiated, with the county typically paying invoices on a net 30 basis using a draw method with 5-10 percent retainage until punch list completion. The contractor must comply with Georgia's E-Verify requirements and Drug Free Workplace Act provisions.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL

CONSTRUCTION OF

STORAGE BUILDING

ISSUING AGENCY WHITE CO BOARD OF COMMISSIONERS

1235 HELEN HIGHWAY

CLEVELAND GA 30528

PHONE: 706-865-2235

FAX: 706-865-1324

ISSUE DATE APRIL 30, 2026

PROPOSAL CLOSING DATE THURSDAY, MAY 28, 2026

PROPOSAL CLOSING TIME 3:00PM

PROJECT NUMBER 2026-RFP-BOC04302026

1.0 INTRODUCTION

1.1 Purpose of Procurement

The White County Board of Commissioners are requesting proposals for the purchase, site prep, and construction of a 35’ W x 100’ L x 16’ steel frame storage building with metal siding at 1235 Helen Highway, Cleveland, Georgia 30528 behind the White County Board of Commissioner’s Building Complex.

The Contractor shall furnish all labor, supervision, materials, chemicals, equipment, tools and transportation necessary to perform all related services to the construction of the requested structure.

1.2 Proposal Certification

Pursuant to the provisions of the Official Code of Georgia Annotated § 50-5- 67(a), White County certifies that the use of competitive sealed proposals will be practical or advantageous to the County in completing the acquisition described in this document.

The owner shall have the right to waive any informality, irregularity, or insufficiency in the proposal procedure and in any proposal or proposals received, and to accept the proposal which, in the Owner’s sole judgment, is in the Owner’s own best interest. The Owner shall have the right to accept any proposal.

1.3 Schedule of Events

The Request for Proposals shall be governed by the following schedule:

DATE ACTIVITY

April 30, 2026 Release of RFP

May 8, 2026, 10:00am EST Mandatory Pre-Proposal Meeting

May 12, 2026, 12:00pm EST Deadline for written questions to Purchasing Assistant

May 15, 2026, 5:00pm EST Answers to written questions and addenda posted to website

May 28, 2026 3:00pm EST Proposals Due

1.4 Restrictions on Communications

From the issue date of this RFP until a vendor is selected and the award is announced, contractors are not allowed to communicate about this project with any County staff or elected officials except: 1) through the Purchasing Assistant named herein, 2) at Pre-Proposal meeting (if applicable to RFP) or 3) as provided by existing work agreement(s). The County reserves the right to reject the submittal of any vendor violating this provision.

1.5 Pre-Proposal Meeting & Site Visit

A mandatory pre-proposal meeting will be held May 8, 2026 at 10:00am at the White County Board of Commissioners Office, located at 1235 Helen Hwy, Cleveland, Georgia 30528.

1.6 Questions & Addenda

All questions concerning this RFP MUST BE SUBMITTED IN WRITING, (email is preferred but fax and mail may also be used) to the Purchasing Assistant no later than 12:00PM, May 12, 2026.

Misti Lane, Purchasing Assistant White County Board of Commissioners 1235 Helen Highway Cleveland, GA 30528 mlane@whitecountyga.gov Fax: 706-865-1324

No response to inquiries, other than written, will be binding upon the County. White County reserves the right to issue written addenda to any inquiries that alter the scope of the RFP. Addenda shall be posted to the county website, www.whitecountyga.gov under the Bids/RPFs page no later than 5:00 PM, May 15, 2026. A signed copy of any addenda shall accompany submitted proposals. Vendors are advised to check the website for addenda before submitting their proposals.

1.7 Contract Term

The contract between the County and the vendor shall become effective up signing and shall remain in force until completion of the project or until notice of termination, in writing, is given by the other party as provided herein.

White County reserves the right to terminate contract, with 30 days written notice, for any violations in the terms of this agreement, rules, laws or unreconciled issues arising as a result of this agreement. Vendor agrees to provide 30 days written notice and complete any ongoing activity period if Vendor chooses to opt out of an agreement with the County.

1.8 Bonds

Proposal Bonds Not Required Payment Bonds Not Required Performance Bonds Not Required mailto:mlane@whitecountyga.gov http://www.whitecountyga.gov/

Information regarding bonds to be furnished (if required) is stated in the 6.0 Terms and Conditions section of this proposal document, 6.28 “Proposal Bonds, Performance and Payment Bonds.”

1.9 Exception to RFP

Each contractor shall be deemed to agree to comply with all terms, conditions, specifications, and requirements of this RFP. An “exception” is defined as the Proposer’s inability or unwillingness to meet a term, condition, specification, or requirement in the manner specified in the proposal. All exceptions taken must be identified and explained in writing in your RFP and must specifically reference the relevant section(s) of this RFP. If the Proposer provides an alternate solution when taking an exception to the requirement, the benefits of this alternative solution and impact, if any, on any part of the remainder of the Proposer’s solution must be explained in detail.

The County welcomes innovative suggestions and recommendations from Proposers that will ensure a 100% successful service approach.

2.0 SCOPE OF WORK

The White County Board of Commissioners is requesting sealed proposals from qualified contractors for construction of a storage building located at 1235 Helen Hwy, Cleveland, Georgia. All work involved in this project is required to be completed in a professional workmanship like manner according to standard practices. Any alterations or deviation from specifications involving extra cost will be executed upon written orders. The selected company/contractor shall be required to carry necessary insurances until the completion of the project. In addition, the selected company shall obtain any necessary building permits, required inspections, supplies, deliveries, and a complete turnkey installation of the structure at the proposed site. This project is intended to be a design build project. Selected contractor will be responsible for all required plans, engineering, surveying, design, and complete construction.

2.1 PROJECT DURATION AND WORK SCHEDULE

Project duration and work schedule: In the submitted proposal, please describe/summarize a schedule and a tentative timeline of all the phases of the project in which the proposed work will be completed, such as specific milestones and work phase completion dates. We request that the project be completed in a timely manner and as weather conditions allow.

2.2 PROOF OF INSURANCE

Proof of Insurance: The successful contractor shall agree to have all of the required insurances in place and current at all times during the entire term of this agreement. White County has no responsibility to obtain insurance to cover injuries of the successful contractor or subcontractors sustained in connection with providing services under this contract. The selected contractor will be required to provide performance and payment bonds, each totaling 100% of the awarded amount of the work.

2.3 DETAILED COST ESTIMATE

Detailed cost estimate. The contractor shall include a cost estimate with the RFP submittal. The cost estimate should be detailed to capture each area of work and produce a total project cost. Each area of work shall include any incidental costs or work associated with each area. It should be clear what factors make up the total project cost. The contractor may submit more than one cost estimate, or proposal, based on meeting minimum requirements or acceptable alternatives.

2.4 PROJECT DETAILS

• Complete site prep to include grading, drainage, forming, and pouring the concrete pad with an 18” larger footprint slab around the entire building to accommodate a 35’ W x 100’ L x 16’ storage building with 6 bays, (16 gauge steel frame and 26-gauge metal siding, and 24-gauge metal roof storage building.

• Concrete will be a minimum of 4” 3,000 PSI in bays 1 – 5. Bay 6 will be 6” thick. All of slab under building will include a minimum of 4” gravel base, standard reinforcement, and a 10 mil poly vapor barrier

• Form and pour an 8’ x 110’ concrete slab for the front of the building as an apron. Slope the full length of the slab for positive drainage away from building. Use 4” gravel base and the required reinforcement. Add a 5’ x 5’ concrete slab at the end of Bay 1 and Bay 6 for a side entry walk-through door.

• Any import or export dirt will be the responsibility of the contractor

• All concrete will have a smooth finish and treated with a waterproof sealant. Trowel finish any outside concrete and smooth finish on the inside of the building.

2.5 BUILDING STRUCTURE

• Size: 35’ width x 100’ length x 16’ height with a 2:12 roof pitch

• (6 bays) each with roll-up doors (12’ x 12’) with chain reels

• 5’ column spacing or to standard specs on the size of the building

• (x2) 3’0” RH exterior door. One at Bay 1 and one at Bay 2

• (x2) Windows in Bay 1. One on south wall and one on west wall

• See Appendix D for aerial view of site location

2.6 ELECTRICAL/INSULATION/PLUMBING

• Complete hook up to power and water/sewer is required. The contractor will need to provide any design or civil engineering required as well as means and methods.

• Install a 200-amp single phase electrical service panel in Bay 1 and wired with six 20-amp electrical outlets and two LED bay lights on a wired switch

• Insulate Bay 1 walls with 4” batted insulation and insulate ceiling with 6” insulation. Bays 2 – 6 will only have 6” roof insulation (No wall insulation on Bays 2 – 6)

• Bay 1 will need to be plumbed for sewer and water to accommodate a restroom with a floor drain. Restroom will need to be 6’ width x 6’ length x 8’ height walls. Frame restroom using 2” x 6” x 8’ lumber walls and ceiling with ¾” plywood and the top decked with ¾” plywood for storage. It also needs to have a 3’0 interior LH outswing door and will need to have a toilet and deep sink with a small electric water heater in one corner of the restroom. The restroom will also need a 4’ LED light fixture on a wired switch and one GFI outlet.

• Install a frost proof hose bib on the exterior of Bay 1.

3.0 MANDATORY REQUIREMENTS

This section identifies all mandatory requirements which must be present in the proposal before further consideration will be given.

3.1 Proposal Requirements

a. A transmittal letter that states the Proposal is submitted in response to Construction of Storage Building RFP Project# 2026-RFP-BOC04302026.

Letter must be signed by a person authorized to enter into a contractual agreement on behalf of the submitting firm. Name, title, email address and phone number shall be included for a contact person.

b. Completed Pricing Proposal that addresses all elements of the Scope of Work referenced in Section 2 of this RFP, sealed in a separate envelope/package.

c. Qualifications Information requested in Section 4 of this RFP.

d. Evidence of Insurance.

e. Bidder’s Certification (Appendix A)

f. E-Verify Affidavit (Appendix B)

g. Signed Contract (Appendix C)

h. Signed Addendum (if any)

i. Brochures and warranty information

3.2 Pricing Proposal

The Pricing Proposal must be signed by an authorized individual/officer of the firm along with company name and address and printed name of authorized individual/officer. The pricing proposal should include an all-inclusive maximum price and is to contain all direct and indirect costs including out of pocket expenses such as travel, lodging, etc.

The Pricing Proposal must be submitted as a separate, sealed envelope/package.

4.0 QUALIFICATIONS INFORMATION

Qualifications information together shall not exceed 20 pages. Provide the following qualifications information:

a. Business location and officers of the firm (company background)

b. Provide financial information that would allow proposal evaluators to ascertain the financial stability of the Proposer.

i. If a public company, include a recap of the most recent audited financial report.

ii. If a private company, provide a recap of the most recent internal financial statement; and a letter, on the financial institution’s letterhead, stating financial stability.

c. Business Litigation

i. Disclose any involvement by the organization or any officer or principal in any material business litigation within the last five (5) years. The disclosure will include an explanation, as well as the current status and/or disposition.

d. Resumes of key personnel proposed to participate in the project including education background and employment history.

e. A list of relevant work performed for public entities within the last five (5) years, including contact names and telephone numbers (maximum 5).

f. Copies of manufacturer installer certificates (if applicable to RFP). Contractors must be certified resellers of the products they provide and install.

g. Logistics Plan. Proposers shall submit a brief description of proposed site management logistics including the following items:

i. Approach, planning and implementation of project

ii. Contractor's on site staffing, number of personnel and their primary duties.

iii. Space requirements for on-site materials storage.

iv. List of proposed subcontractors.

h. As the above items are to be considered in selection of the Contractor, submission of this information shall be binding on the Contractor and shall not be changed without agreement in writing from the Owner.

5.0 PROPOSAL SUBMISSION AND EVALUATION

5.1 Process for Submitting Proposals

5.1.1 Preparation of Proposal

Each proposal should be prepared simply and economically, avoiding the use of elaborate promotional materials beyond those sufficient to provide a complete presentation. If supplemental materials are a necessary part of the technical proposal, the Contractor should reference these materials in the technical proposal, identifying the document(s) and citing the appropriate section and page(s) to be reviewed.

5.1.2 Packaging of Proposal

Mark the outside of the shipping package as follows:

Construction of Storage Building RFP

Project# 2026-RFP-BOC04302026

FAILURE TO PROPERLY LABEL THE OUTSIDE OF THE SHIPPING

CONTAINER MAY RESULT IN DISQUALIFICATION.

Inside the shipping container, the proposal in response to this RFP must be divided into two separate and appropriately labeled and sealed packages - a Qualifications Proposal and a Pricing Proposal. The inner packages shall be labeled with the submitting firm’s name.

1. The contents of the sealed, inner package labeled “Qualifications Proposal” will include an original and two (2) copies of each of the following:

• Transmittal letter referenced under Section 3.1 of this RFP

• Bidder’s Certification (Appendix A)

• E-Verify Affidavit (Appendix B)

• Signed Contract (Appendix C)

• All qualifications information referenced under Section 4 of this RFP

• Proof of Insurance

• Signed Addendum (if any)

• Required information referenced in Section 2 of this RFP

2. The contents of the sealed, inner package labeled “Pricing Proposal” will Include an original and two (2) copies of each of the following:

• Completed Pricing Proposal

Do not include price information of any kind in the Qualifications Proposal

5.1.3 Submission of Proposals

Proposals will be received by the White County Board of Commissioners Purchasing Assistant until 3:00 PM on May 28, 2026. The original and two (2) copies must be mailed, hand-delivered, or express mailed to:

Misti Lane, Purchasing Assistant White County Board of Commissioners 1235 Helen Highway Cleveland GA 30528

Any submission received after the due date and time will not be evaluated.

NOTE: Many express mail services do not guarantee overnight delivery times to White County. Any proposal received after 3:00 PM on May 28, 2026, will not be opened.

5.2 Evaluation Process

The evaluation of proposals received on or before the due date and time will be conducted as follows:

5.2.1 Administrative Review

The proposals will be reviewed by the Purchasing Assistant for the following administrative requirements:

1. Submitted by deadline

2. Separately sealed Qualifications Proposal and Pricing Proposal

3. All required documents have been submitted

4. Qualifications Proposal does not include any pricing information

5. All documents requiring an original signature have been signed and are included

5.2.2 Mandatory Requirements Review

Proposals which pass the administrative review will be reviewed to ensure all Mandatory Requirements identified in Section 3.0 are addressed satisfactorily.

5.2.3 Qualifications Proposal Evaluation

Proposals which pass the Mandatory Requirements Review will then be evaluated, by a review committee, based on the qualification factors. Qualifications information will be scored as follows and may receive a maximum of one hundred

(100) points.

Company Background 15

Personnel Qualifications 20 Relevant Work 25 Project Approach 25 Pricing 15 Total Points 100

5.2.4 Pricing Proposal Evaluation

The Pricing Proposals from bidders not eliminated during the qualification proposal evaluation will then be reviewed by a committee to determine which proposal results are most beneficial to the County.

5.2.5 Oral Presentations

The County reserves the right to invite Proposers to present their qualifications.

5.2.6 Selection of Proposal

Upon completion of the evaluation process, White County will select the proposal that is in the best interest of White County.

5.3 Rejection of Proposals/Cancellation of RFP

White County reserves the right to reject any or all submissions, to waive any irregularity or informality in a submission, and to accept or reject any item or combination of items, when to do so would be to the advantage of the County. It is also within the right of the County to reject submissions that do not contain all elements and information requested in this document. The County reserves the right to cancel this RFP at any time. The County will not be liable for any cost/losses incurred by the Contractors throughout this process.

6.0 TERMS AND CONDITIONS

See Section 1.0 Introduction and Section 2.0 Scope of Work for submission requirements specific to this Request for Proposal.

6.1 RFP Amendments

The County reserves the right to amend the RFP prior to the proposal due date. All addenda and additional information will be posted to the County’s website, www.whitecountyga.gov, under the Bids/RFPs page no later than 5:00 pm, EST on May 15, 2026. It is the Proposer’s responsibility to check the website for addenda before submitting a proposal. All signed addenda shall be included with the proposal.

6.2 Agreement and Project Forms

The agreement form shall be the Owner’s agreement form. The Owner’s payment, waiver of lien, and change order form(s) shall be used.

6.3 RFP Withdrawal

http://www.whitecountyga.gov/

A submitted RFP may be withdrawn prior to the due date by a signed written request to the Purchasing Assistant.

6.4 Costs for Preparing RFP

The cost for developing the RFP is the sole responsibility of the contractor. The County will not provide reimbursement for such cost.

6.5 Conflict of Interest

If a Proposer has any existing client relationship that involves White County, the Proposer must disclose each relationship.

6.6 Contractor Selection

White County reserves the exclusive right to determine which Proposer should be awarded the contract. The County also reserves the right to reject any and all RFPs at its discretion, with or without cause.

6.7 Negotiations and Apparent Winner

Prior to award, the apparent winning proposer will be required to enter into discussions with the County to resolve any contractual differences.

These discussions are to be finalized within two (2) weeks of notification unless extending the time period is advantageous to the County. Failure to resolve differences will lead to rejection of the contractor’s RFP.

The County reserves the right to negotiate modifications and costs with the successful Proposer, provided that no such modifications affect the specifications set forth herein. The contractor shall commence work only after the transmittal of a fully executed contract and a Notice to Proceed document is received from the County.

6.8 Taxes

White County is exempt from sales taxes; however, the contractor shall pay all taxes required as stated by law. White County cannot exempt others from tax.

6.9 Compliance with Laws

The contractor will comply with all State and Federal laws, rules, and regulations.

6.10 Non-Collusive Bidding

Contractor shall not prevent or attempt to prevent competition in bidding or proposals by any means whatsoever. Contractor shall not prevent or endeavor to prevent anyone from making a bid or proposal by any means whatsoever, nor shall Contractor cause or induce another to withdraw a bid or proposal for the work. § 36-91-21.

If the contractor is a partnership, all of the partners and any officer, agent, or other person who may have represented or acted for them in bidding for or procuring the contract shall also make the oath. If the contractor is a corporation, all officers, agents, or other persons who may have acted for or represented the corporation in bidding for or procuring the contract shall make the oath. If such oath is false, the contract shall be void, and all sums paid by the governmental entity on the contract may be recovered by appropriate action.

6.11 Cancellation

If either party shall refuse, fail, or be unable to perform or observe any of the terms or conditions of the contract for any reason, then the party claiming such failure shall give the other party a written notice of such breach. If within thirty (30) days from such notice, the failure has not been corrected, the injured party may cancel the contract effective thirty (30) days after notice of cancellation.

White County reserves the right to terminate the contract immediately in the event that the contractor discontinues or abandons operations, is adjudged bankrupt or is reorganized under any bankruptcy law or fails to keep in force any required insurance policies or bonds.

Failure of the successful Proposer to comply with any section or part of the contract will be considered grounds for immediate termination of the contract by the County without penalty to White County. White County shall pay for services rendered up to the point of termination.

Notwithstanding anything to the contrary contained in the contract between the County and the successful contractor, the County may, without prejudice to any other rights it may have, terminate the contract for convenience and without cause, by giving thirty

(30) days written notice to the successful Proposer.

If the termination clause is used by the County, the successful contractor will be paid by the County for all scheduled work completed satisfactorily by the successful contractor up to the termination date set forth in the written termination notice.

6.12 Conditions of Materials

It is understood and agreed that materials delivered shall be new, of latest design, and in first quality condition.

6.13 Rejection of Submissions/Cancellation of Request for Proposal

White County reserves the right to reject any or all RFPs, to waive any irregularity or informality in an RFP, and to accept or reject any item or combination of items, when to do so would be to the advantage of White County. It is also within the rights of White County to reject RFPs that do not contain all elements and information requested in this document. White County reserves the right to cancel this Request for Proposal at any time. White County will not be liable for any cost/losses incurred by the contractors throughout this process.

6.14 Non-discrimination

White County does not discriminate on the basis of race, religion, color, sex, national origin, age, or disability.

6.15 Payment

Payment terms and invoicing requirements shall be negotiated and defined by the final contract. White County typically pays invoices on a net 30 basis. Invoices for construction related projects are paid on a draw method as negotiated and with a retainage of 5-10% held until all punch list items are completed.

6.16 Insurance

The contractor shall be responsible for his/her work and every part thereof and for all materials, tools, equipment, appliances, and properties of any and all description used in connection with this project. The contractor assumes all risks of direct and indirect damage or injury to the property of persons used or employed on or in connection with the work contracted for and of all damage or injury to any person or property wherever located, resulting from any action, omission, commission, or operation under the contract, or in connection in any way whatsoever with the contracted work. The contractor shall, during the continuance of all work under the contract, provide the following:

1. Maintain statutory Worker’s Compensation and Employer’s Liability insurance in an amount not less than $1,000,000.00 to protect the contractor from any liability or damages for any injuries (including death and disability) to any of its employees, volunteers, or sub-contractors, including any and all liability or damage which may arise by virtue or any statute or law in force within the State of Georgia, or which may be herein after enacted.

2. The Proposer agrees to maintain Comprehensive General Liability Insurance in an amount of not less than $1,000,000.00 per occurrence to protect the contractor, it’s subcontractors, and the interest of the County against any and all injuries to third parties, including bodily injury and personal injury, wherever located, resulting from any action or operation under the contract or in connection with the contracted work.

The General Liability Insurance shall also include the Broad Form Property Damage Liability endorsement, in addition to coverage for explosion, collapse, and underground hazards where required.

3. The contractor agrees to maintain Automobile Liability Insurance in an amount of not less than $500,000 per occurrence. Such insurance shall include coverage for owned, hired, and non-owned automobiles.

4. The contractor further agrees to protect, defend, indemnify, and hold harmless White County, its commissioners, officers, agents, and employees from and against any and all liability incurred whatsoever as a result of the work performed pursuant to the terms of this proposal.

5. The contractor shall notify the County in writing sixty (60) days prior to change in insurance or cancellation date. The failure of the contractor to deliver a new certificate shall result in suspension of all payments until the new certificate is furnished. Additionally, contract work may be suspended until the new certificate is furnished to the County.

6. Insurance coverage required in these specifications shall be in force throughout the contract term. Should the contractor fail to provide acceptable evidence of current insurance within five (5) days of written notice at any time during the contract term, the owner shall have the absolute right to terminate the contract without any further obligation to the contractor. Furthermore, the contractor shall be responsible for the cost of procuring the uncompleted portion of the contract at the time of termination.

7. Contractual and other liability insurance provided under the contract shall not contain a supervision, inspection, or engineering services exclusion that would preclude the County from supervising and/or inspecting the project as to the end result. The contractor shall assume all on the job responsibilities as to the control of persons under its direct employment and of the sub-contractors and any persons employed by the sub-contractors.

8. The contractor and all sub-contractors shall comply with the Occupational Safety and Health Act of 1970 and amendments as it may apply to this contract.

9. If the contractor does not meet the insurance requirements of the specifications, alternate insurance coverage satisfactory to the County may be considered. The contractor shall be responsible for the costs of any and all alternate insurance coverage so obtained.

6.17 Project Coordination

The contractor shall employ and assign only qualified and competent personnel to perform any service or task involved in this project. The contractor shall designate one such person as a Project Manager, and the Project Manager shall be deemed to be the contractor’s authorized representative, who shall be authorized to receive and accept any and all communication from the County.

The contractor hereby agrees to replace any personnel of sub-contractor, at no cost or penalty to the County, if the County reasonably determines that the performance or any sub-contractor or personnel is unsatisfactory.

6.18 Accuracy of Work

The contractor shall be responsible for the accuracy of work performed and shall promptly correct its errors and omissions without additional compensation. Acceptance of the work by the County will not relieve the contractor of the responsibility for subsequent correction of errors, the clarification of any ambiguities, or the costs associated with any additional work caused by negligent acts, errors, or omissions by the contractor or latent defects in the products sold by the contractor.

At any time during the execution of this project or during any phase of work performed by others based on data secured by the contractor under this agreement, the contractor shall confer with the County for the purpose of interpreting the information supplied by the contractor and to correct any errors or omissions. The above consultations, clarifications, and/or corrections shall be made without added compensation to the contractor.

The contractor shall give immediate attention to these changes so there will be minimum delay to others, the contractor shall be responsible for errors and omissions and hold harmless the County and its agents as provided in the agreement.

6.19 Ownership

Reports, plans, data, statistics, specifications, and other supporting records compiled or prepared in the performance of the services required by this proposal, shall be the absolute property of the County and shall not be used by the contractor for purposes unrelated to this proposal without the prior written approval of the County. Such original documents shall be turned over to the County upon completion of the proposal/contract term except that contractor shall have the right to retain copies of the same.

6.20 News Release by Contractor

As a matter of policy, the County does not endorse the products or services of a contractor.

News releases concerning any resultant contract from this solicitation shall not be made by a contractor without the proper written approval of the County. All proposed news releases shall be routed to the White County Clerk for review and approval.

6.21 Severability

It is understood and agreed by the parties hereto that if any part, term, or provision of this contract is held illegal or in conflict with any law of the State where made or having jurisdiction over any of the parties hereto, the validity of the remaining portions or provisions shall not be affected, and the rights and obligations of the parties shall be construed and enforced as if the contract did not contain the particular part term or provisions held to be invalid.

The County and the contractor agree to resolve through negotiation or mediation prior to filing any cause of action. The venue for any litigation arising from this contract shall be White County, Georgia.

The County reserves the right to cancel the contract and discontinue the services with a thirty (30) day written notice as a result of the failure of the contractor to provide acceptable work and services as delineated in the response to this document or if determined that services can be better provided by in-house or other sources.

6.22 Drug Free Workplace

By submission of a proposal, the contractor certifies that the provisions of Code Sections 50-24- 1 through 50-24-6 of the Official Code of Georgia Annotated, relating to the “Drug Free Workplace Act,” have been complied with in full. The Proposer further certifies that:

1. A drug free workplace will be provided for the contractor’s employees during performance of the contract; and

2. Each contractor who hires a sub-contractor to work in a drug free work place shall secure from that sub-contractor the following written certification: as part of the sub-contracting agreement, Sub-Contractor certifies to the contractor that a drug free workplace will be provided for the sub0contractor’s employees during the performance of this contract pursuant to paragraph (7) of sub-section (b) of Code Section 50-24-3.

3. The contractor further certifies that he will not engage in the unlawful manufacture, sale distribution, dispensation, possession, or use of a controlled substance or marijuana during the performance of this contract.

6.23 Assignment of Contractual Rights

It is agreed that the contractor will not assign, transfer, convey, or otherwise dispose of a contract that may result from this proposal or his right, title, or interest in or to the same, or any part thereof without written consent of the County.

6.24 Indemnity

To the fullest extent permitted by law, the contractor will indemnify, defend, and hold White County harmless from and against any and all claims, damages, losses, and expenses, including but not limited to, fees and charges of attorneys and court and arbitration costs, arising out of or resulting from negligent acts, negligent omissions, willful misconduct, or reckless misconduct of the Proposer or anyone for whom the contractor is responsible.

6.25 Appropriation of Funds

The initial contract and any continuation contract(s) shall terminate immediately and absolutely at any such time as there are no appropriated and otherwise unencumbered funds available to satisfy the County’s obligation under said contract(s).

6.26 Documents Deemed Part of Contract

All contract documents issued by the owner and executed by both parties through the completion of the project shall be deemed part of the contract. No documentation or information provided by the contractor, as part of this proposal or otherwise, shall be deemed part of the contract unless and until incorporated into the contract documents issued by the owner.

6.27 Open Records

All materials submitted in connection with this Request for Proposal will be public documents and subject to the Open Records Act and all other laws of the State of Georgia, the United States of America, and the open records policies of the White County Board of Commissioners. All such materials shall remain the property of White County and will not be returned to the respondent.

6.28 Proposal Bonds, Performance Bonds, and Payment Bonds

A five percent (5%) proposal bond, a one hundred percent (100%) performance bond and/or a one hundred percent (100%) payment bond shall be furnished to White County if stated as a requirement in paragraph 1.8 in the “Introduction” section of this proposal.

Bonding company must be authorized to do business in Georgia by the Georgia Insurance Commission, listed in the Department of Treasury’s publication companies holding certificates of authority as acceptable surety on Federal bonds and as acceptable reinsuring companies and have an A.M. Best rating.

6.29 Georgia Security and Immigration Compliance Act

Proposers submitting a response to this Request for Proposal must provide the following information in the package to indicate compliance with the Georgia Security and Immigration Compliance Act. The forms are provided for completion, Appendix B.

6.30 RFP Opening

Only the names of the companies and individuals responding to the RFP will be read aloud publicly due to the fact that the proposals will be subject to an evaluation review for accurate submissions and qualifications. A list of names responding to the RFP may be obtained from Misti Lane, Purchasing Assistant, mlane@whitecountyga.gov, after the RFP due date and time stated herein.

mailto:mlane@whitecountyga.gov

Appendix A

BIDDER’S CERTIFICATION

Construction of Storage Building RFP Project# 2026-RFP-PR03052026

Date of Proposal

I certify that this Proposal is submitted without prior understanding, agreement or connection with any corporation, firm or person submitting a Proposal for the same goods/services and is in all respects fair and without collusion or fraud. I understand that collusive bidding is a violation of state and Federal law and can result in fines, prison sentences and civil damages awards. I agree to abide by all conditions of this bid and certify that I am authorized to sign this bid for the bidder.

Bidder Information Name and Mailing Address (Type or Print) (Where to Send Payment)

Name of Company Name of Company

Address Address

City, State, & Zip Code City, State, & Zip Code

Phone Number Phone Number

Fax # Email Address

OR

Tax ID Number Social Security Number

Name & Title of Person Authorized to Sign

Name SIGNATURE

Title

Proposals or Bids not signed shall be declared as “Non-Responsive” and may not be considered for award.

Appendix B

E-Verify Affidavit

Georgia Security & Immigration Compliance (GSIC) Act

(CONTRACTOR) E-VERIFY AFFIDAVIT AND AGREEMENT

White County Commissioner and Contractor agree that compliance with the requirements of O.C.G.A. § 13-10-91 and Rule 300- 10-1-.02 of the Rules of the Georgia Department of Labor are conditions of this Agreement for the physical performance of services.

By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm, or corporation which is contracting with the White County Commissioner has registered with and is participating in the federal work authorization program known as “E-Verify”, web address https://e-verify.uscis.gov/enroll/ operated by the United States Citizenship and Immigration Services Bureau of the United States Department of Homeland Security to verify information of newly hired employees, pursuant to the Immigration Reform and Control Act of 1986 [(IRCA), P.L. 99- 603], in accordance with the applicability provisions and deadlines established in O.C.G.A. § 13-10-91. The undersigned Contractor also verifies that he/she/it is using and will continue to use the federal work authorization program throughout the contract period.

The undersigned Contractor agrees that, should it employ or contract with any subcontractor(s) in connection with the physical performance of services pursuant to the contract with the White County Commissioner, Contractor will secure from such subcontractor(s) similar verification of compliance with O.C.G.A. § 13-10-91 on the Subcontractor Affidavit provided in Rule 300- 10-01-.08 or a substantially similar form. Contractor further agrees the Contractor will advise the White County Commissioner of the hiring of a new subcontractor and will provide White County Commissioner with a Subcontractor Affidavit attesting to the Subcontractor’s name, address, user identification number, and date of authorization to use the Federal Work Authorization Program within five (5) days of the hiring before the Subcontractor begins working on the Project. Contractor also agrees to maintain all records of such compliance for inspection by White County Commissioner at any time and to provide a copy of each such verification to the White County Commissioner at the time the subcontractor(s) is retained to perform such services.

E-Verify Employment Eligibility Verification User identification Number

Date of Authorization to Use Federal Work Authorization Program

NAME OF CONTRACTOR

Title of Authorized Officer or Agent of Contractor

Signature and Printed Name of Authorized Officer or Agent

SUBSCRIBED AND SWORN BEFORE ME ON THIS THE DAY OF , 20 .

Notary Public

My Commission Expires:

* As of the effective date of O.C.G.A. § 13-10-91, the applicable federal work authorization program is the “EEV / Basic Pilot Program” operated by the U.S. Citizenship and Immigration Services Bureau of the U.S. Department of Homeland Security, in conjunction with the Social Security Administration (SSA). Authority O.C.G.A. § 13-10-91. History: Original Rule entitled “Contractor Affidavit and Agreement” adopted F. May 25, 2007; eff. June https://e-verify.uscis.gov/enroll/

APPENDIX D

Misti Byrd Highlight

CONTRACT FOR Construction of Storage Building RFP

STATE OF GEORGIA

WHITE COUNTY

THIS AGREEMENT, made and entered into this day of , 2026, by and between WHITE COUNTY, GEORGIA, a political subdivision of the State of Georgia, acting by and through its governing authority, the White County Board of Commissioners (hereinafter referred to as the "COUNTY") and (hereinafter referred to as the

"CONTRACTOR").

WITNESSETH:

WHEREAS, the CONTRACTOR has submitted to the COUNTY a description of the services it is willing to undertake in the performance of certain professional services; and

WHEREAS, the proposal submitted (as attached) by the CONTRACTOR has been approved and accepted by the COUNTY; and

WHEREAS, the parties hereto desire to reduce the terms of this AGREEMENT to writing;

NOW THEREFORE, in consideration of the mutual promises and obligations set forth herein, the sufficiency of which is hereby acknowledged, the parties hereto mutually agree to the following:

1. Character of the Work:

The CONTRACTOR agrees to perform _ Construction of Storage Building RFP , in a manner satisfactory to the COUNTY, set forth in Exhibit “A,” which is attached hereto and incorporated herein by reference.

2. Compensation:

The CONTRACTOR agrees to pay the COUNTY for services rendered under this agreement in accordance with the bid price set forth in Exhibit "A". CONTRACTOR shall submit monthly statements of gross sales. CONTRACTOR shall make weekly payments to COUNTY. All payments shall be mailed to the COUNTY, unless prior arrangements to pick up the payment have been made.

3. Term of Agreement:

The term of this Agreement shall be for a period commencing on and ending on .

4. Termination:

If, through any cause, the CONTRACTOR shall fail to fulfill in a timely and proper manner its obligations under this Agreement, the COUNTY shall thereupon have the right to terminate this Agreement by giving written notice to the CONTRACTOR of such termination and specifying the effective date thereof, which effective date shall be no earlier than fourteen (14) calendar days after receipt of the written notice by the CONTRACTOR. Notwithstanding, the CONTRACTOR shall not be relieved of liability to the COUNTY for damages sustained by the COUNTY by the virtue of any breach of this Agreement, and the COUNTY may withhold payment to the CONTRACTOR for the purpose of setoff until such time as the exact amount of damages sustained by the COUNTY from such breach can be determined.

5. Indemnification:

The CONTRACTOR shall hold harmless and indemnify the COUNTY and its officials, employees, and agents from and against any and all claims, damages, liabilities, suits, actions, judgments, and expenses of litigation (including, without limitation, reasonable attorney’s fees) arising from or in any way related to the CONTRACTOR’S performance of this Agreement.

6. Proof of Insurance:

The CONTRACTOR shall maintain insurance in the types and amounts stated below during the term of this Agreement and any renewals or extensions thereof, and shall provide adequate proof of same to the COUNTY prior to commencing performance under this Agreement.

Insurance- Contractor shall maintain at a minimum the following types and amounts of insurance: (i) statutorily required workmen’s compensation insurance; (ii) comprehensive general liability insurance with limits of not less than $1,000,000 per occurrence and $2,000,000 aggregate, and with an endorsement naming White County as an additional insured; and (iii) automobile liability insurance with limits of not less than $1,000,000 per occurrence and $2,000,000 aggregate. Workman’s Compensation and Employer’s Liability in limits of liability as provided by statutes of the State of Georgia.

7. Assignability/Transferability:

The CONTRACTOR shall not assign or transfer any interest in this AGREEMENT without the written consent of the COUNTY.

8. Entire Agreement; Amendments:

This Agreement represents the entire agreement between the parties with respect to the subject matter hereof, and all prior agreements relating to the subject matter hereof, whether written or oral, are nullified and superseded hereby, and neither party shall have any further rights or obligations under such superseded agreements. This Agreement may be amended or supplemented only by a written amendment duly executed and signed by all parties to this Agreement.

9. Notices Any notices permitted or required to be given pursuant to this Agreement shall be in writing and shall be deemed sufficient if sent via U.S. mail to the respective parties at the following addresses:

If to the COUNTY:

White County Board of Commissioners Attn: White County Manager 1235 Helen Hwy Cleveland, GA 30528

If to the CONTRACTOR:

Attn:

If sent via regular U.S. mail, such written notice shall be deemed to have been “received” three business days after it is deposited in the mail with a proper address and with adequate postage affixed.

10. No Waiver:

No failure on the part of either party to this Agreement at any time to require performance by the other party of any term or condition of this Agreement shall be taken or held to be a waiver of such term or condition or in any way affect such party’s right to enforce such term or condition, and no waiver on the part of either party of any term or condition of this Agreement shall be taken or held to be a waiver of any other term or condition hereof.

11. Immunity:

Nothing contained in this Agreement shall be construed or deemed to be a waiver of any immunity to which the parties or their officials, employees, or agents are legally entitled.

12. Legal Construction; Severability:

This Agreement shall be governed by and construed in accordance with the laws of the State of Georgia. In case any one or more of the provisions contained in this Agreement shall for any reason be held to be invalid, illegal, or unenforceable in any respect, such invalidity, illegality, or unenforceability shall not affect any other provision of this Agreement and this Agreement shall be construed as if the invalid, illegal, or unenforceable provision had never been contained in it.

IN WITNESS WHEREOF, the COUNTY and the CONTRACTOR have executed this agreement as of the first date above written.

COUNTY: CONTRACTOR:

BY: BY:

TITLE: TITLE:

ATTEST: ATTEST:

DATE: DATE:

1.0 INTRODUCTION
1.2 Proposal Certification
1.3 Schedule of Events
1.4 Restrictions on Communications
1.5 Pre-Proposal Meeting & Site Visit
1.6 Questions & Addenda
1.7 Contract Term
1.8 Bonds
1.9 Exception to RFP
2.0 SCOPE OF WORK
3.0 MANDATORY REQUIREMENTS
3.1 Proposal Requirements
3.2 Pricing Proposal
4.0 QUALIFICATIONS INFORMATION
5.0 PROPOSAL SUBMISSION AND EVALUATION
5.1 Process for Submitting Proposals
Construction of Storage Building RFP
Project# 2026-RFP-BOC04302026
5.2 Evaluation Process
6.0 TERMS AND CONDITIONS
6.1 RFP Amendments
6.2 Agreement and Project Forms
6.3 RFP Withdrawal
6.4 Costs for Preparing RFP
6.5 Conflict of Interest
6.6 Contractor Selection
6.7 Negotiations and Apparent Winner
6.8 Taxes
6.9 Compliance with Laws
6.10 Non-Collusive Bidding
6.11 Cancellation
6.12 Conditions of Materials
6.13 Rejection of Submissions/Cancellation of Request for Proposal
6.14 Non-discrimination
6.15 Payment
6.16 Insurance
6.17 Project Coordination
6.18 Accuracy of Work
6.19 Ownership
6.20 News Release by Contractor
6.21 Severability
6.22 Drug Free Workplace
6.23 Assignment of Contractual Rights
6.24 Indemnity
6.25 Appropriation of Funds
6.26 Documents Deemed Part of Contract
6.27 Open Records
6.28 Proposal Bonds, Performance Bonds, and Payment Bonds
6.29 Georgia Security and Immigration Compliance Act
6.30 RFP Opening
Construction of Storage Building RFP
Project# 2026-RFP-PR03052026
Appendix B

File details come from the government source that posted it. Updated .