STIP 21737 SnapShot.pdf

PDF 410 KB Posted

Attached to
Compensation, Classification and Pay Equity Study
Solicitation number
S-KA0010-00009525
Issued by
Jackson County, Amity City, Oregon

About this file

STIP 21737 Project Summary

This document is a Statewide Transportation Improvement Program (STIP) project snapshot issued by the Oregon Department of Transportation (ODOT) for the 2024-2027 STIP cycle. The project involves painting the Devils Lake Fork Wilson River Bridge (OR-6) located on Highway 037 near Tillamook, Tillamook County, Oregon to preserve the structure. The bridge is a rural minor arterial classified as a structure work class project. The project is divided into three phases: Professional Engineering (PE) at $218,900, Right of Way (RW) at $5,600, and Construction (CN) at $6,935,100, for a total current estimate of $7,159,600. The bid let date is October 10, 2024. The project has undergone multiple phase slips, most recently with the Right of Way phase slipped to federal fiscal year 2024 (effective July 31, 2023) and the Construction phase slipped to federal fiscal year 2024 (effective October 24, 2022).

Funding for the project derives from HB2017 Bridge Seismic funds and Surface Transportation Block Grants (STBG) Flexible funds, with an 89.73% federal match and 10.27% state match across all phases, resulting in approximately $6,424,309 in federal funding and $735,291 in state funding. The Construction phase is funded 60.80% through Advance Construction Program funds ($4,216,600) and 39.20% through STBG-Flex funds ($2,718,500). The project is administered by ODOT with Region 2 as the responsible region and PSEDOC as the certified agency monitor. The project was created on October 16, 2019, by Rachelle Nelson and last updated on October 1, 2023, by Amanda Sandvig. The project maintains an "Active STIP" status and is approved by the Federal Highway Administration (FHWA).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statewide Transportation Improvement Program Generated on: 2/6/2024 9:26:03 AM Project Summary Page 1 of 4

Key Number: 21737 2024-2027 STIP Project Name: OR6: Devils Lake Fork Wilson River Bridge (Active STIP)

Project Overview Total Current Estimate $7,159,600.00 Description Paint the bridge to help preserve the structure.

Responsible Region 2 Related Programs HB2017

Project Status Date 10/20/2022 STIP Name 2024-2027 STIP Project Status APPROVED Administrator ODOT

Certified Agency

Monitor PSEDOC Applicant ODOT Bid Let Date 10/10/2024 MPO Non-MPO Target Date Constructor CONTRACTOR PAYMENTS Award Date Functional Class RURAL MINOR ARTERIAL

Air Quality Approval Req. Work Class STRUCTURES

Regulatory Agency FHWA Budget Authority OTC

Air Quality Approval Date. IGA #

Contract #

Created On 10/16/2019 Created By RACHELLE NELSON Last Updated On 10/1/2023 Last Updated By AMANDA SANDVIG

Locations

Route Highway MP Begin

MP

End Length Street City County ACT Bridge Reg

State Repr Dist

State Sen Dist

US

Cngr Dist

OR-6 037 WILSON RIVER 31.99 32.11 0.12 TILLAMOOK NWACT 02472 2 32 16 5

Phases

Ph Phase Total Est. Cost

Original Auth Amount

Original Auth Date

Current Auth Amount

Current Auth Date

Current STIP Amount

Curr

STIP

Year

Initial STIP Amount

Init

STIP

Year

EA Fed Aid ID Status

PE 218,900.00 218,900.00 1/22/21 218,900.00 1/22/21 218,900.00 2021 218,900.00 2021 PE003270 S037(033) APPROVED

RW 5,600.00 0.00 0.00 5,600.00 2024 5,600.00 2021 APPROVED

Reference Documents PROJECT DOCUMENTS

STIPFP_Project_Summary_Report_2017.06.2.v1.1

Project Summary Page 2 of 4

Key Number: 21737 2024-2027 STIP Project Name: OR6: Devils Lake Fork Wilson River Bridge (Active STIP)

CN 6,935,100.00 0.00 0.00 6,935,100.00 2024 6,935,100.00 2023 APPROVED

Tot 7,159,600.00 218,900.00 218,900.00 7,159,600.00 7,159,600.00

Budget Limitation

Phase Budget Limitation Percent of Phase

Budget Limitation Amount Opt Code Option Desc

PE

BRIDGE 100.00% 218,900.00 S STATE PROJECT

PE Totals 100.00% 218,900.00

RW

BRIDGE 100.00% 5,600.00 S STATE PROJECT

RW Totals 100.00% 5,600.00

CN

BRIDGE 100.00% 6,935,100.00 S STATE PROJECT

CN Totals 100.00% 6,935,100.00 Grand Totals 7,159,600.00

Financial Plan -- Estimate / Actual Amounts

Phase Funding Resp STIP Year Total Est/Act Amt Fed Est/Act Amt

State Est/Act Amt

Local Est/Act Amt Comment

PE

HB2017

BridgeSeismic

2021-2024

STIP 2021 218,900.00 196,418.97 22,481.03 0.00

PE Totals 218,900.00 196,418.97 22,481.03 0.00

RW

HB2017

BridgeSeismic

2021-2024

STIP 2022 0.00 0.00 0.00 0.00

HB2017

BridgeSeismic

2021-2024 STIP 2023 0.00 0.00 0.00 0.00 07/27: Slipped phase from FFY23 to

FFY24

HB2017

BridgeSeismic

2021-2024 STIP 2024 0.00 0.00 0.00 0.00 07/27: Slipped phase from FFY23 to

FFY24

HB2017

BridgeSeismic

2024-2027 STIP 2024 5,600.00 5,024.88 575.12 0.00 07/27: Slipped phase from FFY23 to

FFY24

RW Totals 5,600.00 5,024.88 575.12 0.00

Project Summary Page 3 of 4

Key Number: 21737 2024-2027 STIP Project Name: OR6: Devils Lake Fork Wilson River Bridge (Active STIP)

CN

HB2017

BridgeSeismic

2021-2024

STIP 2023 0.00 0.00 0.00 0.00

9/8/2021: Funding swap // reduce by $2,718,500 and move to SW Local Bridge per H Derrickson email request.

HB2017

BridgeSeismic

2021-2024

STIP 2024 0.00 0.00 0.00 0.00

9/8/2021: Funding swap // reduce by $2,718,500 and move to SW Local Bridge per H Derrickson email request. 10/20/22: slip to 24.

HB2017

BridgeSeismic

2024-2027

STIP 2024 4,216,600.00 3,783,555.18 433,044.82 0.00

9/8/2021: Funding swap // reduce by $2,718,500 and move to SW Local Bridge per H Derrickson email request. 10/20/22: slip to 24.

SW LOCAL

BRIDGE

2021-2024

STIP 2023 0.00 0.00 0.00 0.00

9/8/2021: Funding swap from HB2017 BridgeSeismic per H Derrickson email request.

SW LOCAL

BRIDGE

2021-2024

STIP 2024 0.00 0.00 0.00 0.00

9/8/2021: Funding swap from HB2017 BridgeSeismic per H Derrickson email request. 10/20/22: slip to 24.

SW LOCAL

BRIDGE

2024-2027

STIP 2024 2,718,500.00 2,439,310.05 279,189.95 0.00

9/8/2021: Funding swap from HB2017 BridgeSeismic per H Derrickson email request. 10/20/22: slip to 24.

CN Totals 6,935,100.00 6,222,865.23 712,234.77 0.00

Grand Totals 7,159,600.00 6,424,309.08 735,290.92 0.00

Project Summary Page 4 of 4

Key Number: 21737 2024-2027 STIP Project Name: OR6: Devils Lake Fork Wilson River Bridge (Active STIP)

Fund Codes Phase Fund Code Description Percent of Phase Total Amount Federal Percent Federal Amount State

Percent State Amount Local Percent Local Amount

PE

ACP0 ADVANCE CONSTRUCT

PR 100.00% 218,900.00 89.73% 196,418.97 10.27% 22,481.03 0.00% 0.00

PE Totals 100.00% 218,900.00 196,418.97 22,481.03 0.00

RW

ACP0 ADVANCE CONSTRUCT

PR 100.00% 5,600.00 89.73% 5,024.88 10.27% 575.12 0.00% 0.00

RW Totals 100.00% 5,600.00 5,024.88 575.12 0.00

CN

ACP0 ADVANCE CONSTRUCT

PR 60.80% 4,216,600.00 89.73% 3,783,555.18 10.27% 433,044.82 0.00% 0.00

Z240 SURFACE TRANSP

BLOCK GRTS-FLEX 39.20% 2,718,500.00 89.73% 2,439,310.05 10.27% 279,189.95 0.00% 0.00

CN Totals 100.00% 6,935,100.00 6,222,865.23 712,234.77 0.00 Grand Totals 7,159,600.00 6,424,309.08 735,290.92 0.00

Amendments Status Date Amendment Num. Status Project Change Type S/C Key

Number Change Reason

7/31/23 21-24-3670 APPROVED SLIP 21737 Slip the Right of Way phase to start in federal fiscal year 2024.

10/24/22 21-24-2832 APPROVED SLIP 21737 Slip the Construction phase to start in federal fiscal year 2024.

12/29/21 21-24-1768 APPROVED SLIP 21737 Slip the Right of Way phase to start in federal fiscal year 2023.

Selection Criteria: STIP 2024-2027 STIP Key Number 21737 Project ID 46853