Station_Fire_Island_Exhaust_Fan_SOW.pdf
PDF 815 KB Posted
- Attached to
- USCG Station Fire Island Attic Vents
- Solicitation number
- 30199PR270000005
- Issued by
- Suffolk County, New York
About this file
Summary
This Scope of Work document outlines the removal and replacement of four attic exhaust fans and associated controls at USCG Station Fire Island, a Multi Mission Building located in Sector Long Island Sound in New York. The contractor shall provide all labor, materials, equipment, supervision, and testing necessary to replace the existing fans with four new Loren Cook Gemini GN-500 inline centrifugal cabinet exhaust fans (or equal) rated at 500 CFM minimum at 0.10 inch water gauge external static pressure, operating on 115 volts single-phase 60 Hz power with adjustable EC motors and integral backdraft dampers. The work includes installation of four adjustable thermostats with manual continuous-operation controls, removal of obsolete equipment, minor duct transitions, and all necessary wiring and connections using existing branch circuits and infrastructure. Site visits are encouraged and must be coordinated with the USCG Engineering Petty Officer Kyle Turcott at the provided contact information during standard work hours (Monday-Friday, 0800-1500, excluding federal holidays). The building will remain occupied during work, requiring contractors to maintain safe access and minimize disruption. All work must be completed within 30 calendar days after contract award, with final acceptance and testing to be demonstrated to the COR and EPO.
The contractor must submit product data for Government review and acceptance before procurement and shall provide documentation of compliance with domestic-preference provisions, airflow verification, test results, and operating instructions. A one-year warranty on workmanship and installed equipment is required beginning at Government acceptance, in addition to any manufacturer warranties. Work is limited to equipment replacement and minor associated connections; structural changes, major duct rerouting, new circuits, panel upgrades, roof work beyond preservation of existing conditions, and hazardous-material abatement are excluded and require written Contracting Officer authorization if encountered. The Contracting Officer Representative is DCC Kyle Swann at (562) 277-0240, who coordinates technical matters and inspections, while only the Contracting Officer may authorize changes to scope, price, or schedule.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Station Fire Island Attic Exhaust Fan Replacement
SCOPE OF WORK
Multi Mission Building | USCG Sector Long Island Sound
1 General
The Contractor shall provide all labor, materials, equipment, supervision, transportation, removal, installation, and testing necessary to replace four attic exhaust fans and associated controls at Station Fire Island. Restore the existing attic ventilation function using standard equipment installation methods, existing louvered penthouses, existing openings, and existing branch circuits. Building footprint, use, and ventilation arrangement shall remain unchanged.
2 Site Visit and Coordination
A site visit is highly encouraged before submitting an offer. Verify equipment locations, access, duct connections, available power, mounting conditions, and removal requirements. Coordinate all visits, outages, and work with the
COR and unit Engineering Petty Officer (EPO): Kyle Turcott, MKC
1 Rescue Rd
Babylon, NY 11702
1 (510) 437-3288
Kyle.N.Turcott@uscg.mil
Work hours are Monday through Friday, 0800–1500, excluding federal holidays, unless otherwise authorized.
The building will remain occupied; maintain safe access and minimize disruption.
3 Removal and Equipment Installation
Remove the four existing fans, motor-operated dampers, and obsolete controls and accessories at the replacement locations, to the extent present. Remove only wiring and conduit no longer required. Dispose of removed materials off Government property in accordance with applicable requirements.
Provide four new inline centrifugal cabinet exhaust fans, identified as AEF-1 through AEF-4, Loren Cook Gemini
GN-500 with Vari-Flow EC motor or equal. Each fan shall provide at least 500 CFM at 0.10 inch water gauge external static pressure, operate on 115 volts, single phase, 60 Hz, and include an adjustable EC motor with thermal overload protection, galvanized steel cabinet with 1/2-inch acoustic lining, dynamically balanced forward-curved wheel, and integral outlet backdraft damper. Provide UL 705 listing and AMCA-certified air and sound performance under Standards 211 and 311.
Reference dimensions are approximately 17 inches wide by 12 inches long by 8 inches high, with nominal 8-by-6-inch duct connections; reference input is approximately 180 watts and 2.1 amps. Verify actual manufacturer dimensions, electrical load, and fit before procurement. Maintain accessible clearances for maintenance through existing attic access.
Suspend fans from suitable existing framing using threaded rods, manufacturer-approved attachments, and vibration isolators. Provide minor duct transitions, sealed connections, hangers, and fasteners necessary to connect to the existing louvered penthouses. Preserve existing roof openings, curbs, flashing, and penthouses.
Repair incidental damage caused by the work and maintain weather-tight conditions.
Reuse the existing branch circuit serving each corresponding fan location. Provide necessary local wiring, conduit, junction boxes, disconnects, and control connections. Permanently label each fan and its serving circuit at the associated junction box. Confirm existing circuit capacity and equipment compatibility before installation; no new circuits, panel upgrades, structural reinforcement, or major duct rerouting are included.
4 Controls
Provide one adjustable thermostat and manual continuous-operation control for each fan. Mount thermostats near the center of the attic joist run, approximately 60 inches above the top chord and approximately 15 feet from the associated fan, subject to accessible field conditions coordinated with the EPO. Set automatic operation to start on a temperature rise above 90°F, adjustable, and stop when the thermostat is satisfied. Provide all local control wiring and mounting accessories.
mailto:Kyle.N.Turcott@uscg.mil
5 Installation Limits and Drawing Reference
Attachment 1 is Drawing SK-1, dated March 21, 2024, Project 26062571, provided for existing locations and applicable connection details. This scope supersedes drawing notes requiring removal of mushroom vents, installation of new louvered penthouses or curbs, new roof openings or framing, and salvage or reinstallation of propeller fans. Those activities are excluded. Connect new inline fans to the existing penthouses and openings.
Work is limited to equipment replacement and minor associated connections. If existing conditions require engineering design, structural changes, major electrical or ventilation reconfiguration, extensive roof work, or hazardous-material abatement, stop the affected work and notify the COR for referral to the Contracting Officer.
Do not proceed with additional work without written Contracting Officer authorization. Final acceptance of the requirement as non-complex remains with LOG-9.
6 Safety and Environmental Requirements
Perform work in accordance with applicable electrical, mechanical, building, and safety requirements and manufacturer instructions. Use qualified trades, electrical lockout/tagout, required fall protection, and safe attic access practices. Protect personnel, occupied spaces, and existing equipment. Obtain unit authorization before hot work. Do not disturb suspect asbestos-containing materials or lead-based coatings; stop affected work and notify the COR. Any required pre-disturbance testing shall be coordinated through the Government before disturbance; abatement is excluded.
7 Submittals and Completion
Before procurement, submit product data for the four fans and controls showing airflow, electrical characteristics, dimensions, mounting, listings, certifications, and compliance with domestic-preference provisions included in the contract. Obtain Government review and acceptance before installation. Submit any proposed equal for review.
Report conflicts among field conditions, this scope, the drawing, and manufacturer instructions before proceeding.
Test all four fans and demonstrate proper rotation, discharge through the existing penthouses, backdraft damper operation, thermostat start and stop, and manual continuous operation. Verify and document airflow of at least
500 CFM per fan under installed conditions and correct excessive vibration, leaks, and other deficiencies.
Demonstrate operation to the COR and EPO.
Remove debris and clean affected areas. Provide operating and maintenance instructions, product data, test results, warranties, and a record of fan locations and serving circuits. Provide a one-year warranty on workmanship and installed equipment beginning at Government acceptance, in addition to any longer manufacturer warranty. Complete all work within 30 calendar days after contract award.
8 Contracting Officer Representative
DCC Kyle Swann
Telephone: (562) 277-0240
The COR coordinates technical matters and inspections. Only the Contracting Officer may authorize changes to contract scope, price, or schedule.
Attachment 1 Vent Drawing SK 1
| 1 General |
| 2 Site Visit and Coordination |
| 3 Removal and Equipment Installation |
| 4 Controls |
| 5 Installation Limits and Drawing Reference |
| 6 Safety and Environmental Requirements |
| 7 Submittals and Completion |
| 8 Contracting Officer Representative |
| Attachment 1 Vent Drawing SK 1 |
File details come from the government source that posted it. Updated .