STATEMENT OF WORK Used Oil.docx

DOCX document 18 KB Posted

Attached to
Extraction of Used Oil
Solicitation number
W911KF-25-S-0010
Issued by

About this file

This Statement of Work outlines requirements for extracting used oil from holding tanks at the Anniston Army Depot's (ANAD) Hazardous Waste Storage Facility. The contractor must extract approximately 16,000 gallons per occurrence from one or two 20,000-gallon holding tanks, using their own equipment, pumps, and adapters for 2-inch piping connections. The contractor is responsible for spill prevention and cleanup, must obtain necessary depot access credentials, and provide 48-hour advance notice before arriving on site.

Key operational requirements include weighing vehicles before and after loading (using 7 pounds per gallon conversion factor), separating water from the extracted oil, and providing documentation of the separation process and water content percentages. The contractor must be self-sufficient, providing all materials, transportation, labor, equipment, and tools. No specific quantity is guaranteed, and the contractor's facility and processes must be available for government audit. The associated Request for Information (RFI) from the Department of the Army Materiel Command has a response deadline of February 17, 2025, at 10 AM CST, under NAICS code 211120 with a size standard of 1,250 employees.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

USED OIL

ANAD has a requirement for the extraction of used oil from holding tanks located on the Anniston Army Depot (ANAD) specifically at the Hazardous Waste Storage Facility (HWSF).

Extraction The oil shall be extracted from one and/or two of two 20,000 gallon holding tanks. The Depot Point of Contact (POC) will advise the contractor which tank(s) oil will be removed from upon the contractor arriving on site. Most piping and connections are two (2) inches, but adapters may be required and shall be provided by the contractor. The used oil shall be pulled from the holding tank into the contractor’s conveyance. The contractor’s equipment shall be equipped with pumps to draw the used oil from the holding tank. These valves have potential for failure. The contractor shall be prepared and able to remedy any situation that may occur from valve failure. When complete each line, valve, and equipment shall be leak free with valves and access points properly closed, sealed, and secured. The contractor shall comply with specific onsite extraction methods as determined by Depot personnel in advance of work starting and agreed upon by the contractor. The Government will not provide any equipment, supplies, or tools. The contractor shall be prepared to be self-sufficient and provide all material, transportation, labor, equipment, tools, coordination, planning and necessary supervision to complete this requirement.

Spills Due to the nature of this scope, spills are possible. The contractor shall take all precautions to prevent a spill from occurring. Should a spill occur, the contractor shall be responsible for cleaning up the spill to the satisfaction of the Depot POC. Should the Depot be involved in any cleanup effort, the cost incurred by the Government shall be paid by the contractor. The contractor shall have in their possession the appropriate quantity of spill clean-up materials and tools to remediate any situation. Should a spill occur, the contractor shall notify their Depot POC immediately. Contractor equipment shall be free of any petroleum, oil, or lubricant drips or leaks.

Quantity It is estimated the quantity of oil to be extracted is approximately 16,000 gallons per occurrence. Actual amounts will vary as well as the frequency between oil removal episodes. There is no quantity specified and that fact shall not constitute the basis for an equitable price adjustment. All oil shall be removed from each tank designated as part of this scope.

Depot Access The contractor shall obtain the necessary credentials to gain access to Anniston Army Depot without the need for an escort. The contractor shall notify the Depot POC, contracting specialist, and Recycling Program Manager a minimum of 48 hours prior to arriving to remove used oil. This is imperative so that Depot personnel have time to make necessary arrangements or adjustments to accommodate the oil removal process. Should notification not be made to the Government and upon arrival the contractor is delayed or prohibited from extracting oil, no equitable adjustments will be given. Should the contractor fail to perform on the specified date the contractor may be subject to financial penalties imposed by the Government for cost and inconveniences incurred by the Government. Information provided in the notification by the contractor shall include the number of trucks that will be used on that day and identification information for each truck. Other information may be required at the discretion of any POC and/or the contracting officer (KO). Methods of communication shall be email and any other method requested by Depot POCs.

Weight The contractor shall weigh each vehicle used to transport the used oil upon entry, prior to loading, and then again after loading prior to departure from the Depot. The factor of Seven (7) pounds per gallon will used to convert weight to gallons for payment purposes. This will be done on Depot scales as designated by the POC. The contractor will be provided a POC that will meet each vehicle at the scales to perform this requirement.

Percentage Volume It is know the extracted used oil will be contaminated with water. The water shall be separated from the used oil and payment submitted only for the quantity of oil resulting from this process. The contractor shall provide formal documentation of processes used to separate water from the oil. The contractor shall document the gallons and percentage of water separated from the used oil extracted from ANAD. The contractor shall be responsible for reliable and accurate data identifying the water content of each load. These totals in gallons and percentages shall be clearly stated in the documentation returned to ANAD with payment. The contractors facility, processes, and data regarding used oil obtained from ANAD shall be made accessible upon request by the POC for the purpose of audit and observation.