United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Replace Interior Coating System 200k Gallon Elevated Water Tank Asset ID: 640200S177

USDA - ARS

Stoneville, Mississippi

Prepared by:

J. Kevin Magee, P.E.

March 2023

STATEMENT OF WORK

Construction

PART 1 - GENERAL

1.1 CONTRACT PROJECT:

0. Project Title:

Replace Interior Coating System, 200K Gallon Elevated Water Tank

0. Project Location:

USDA ARS JWDSRC

141 Experiment Station Road Stoneville, MS 38776

1.2 PROJECT CONTACT PERSONS:

0. CONTRACTING OFFICER (CO):

Monte Jordan
141 Experiment Station Road
Stoneville, MS 38776
Phone: (662)686-5361
Monte.jordan@usda.gov

0. LOCATION COORDINATOR (LC):

Dr. Brian Scheffler 141 Experiment Station Road Stoneville, MS 38776 Phone: (662) 686-5454 (Office) Brian.Scheffler@USDA.gov

0. LOCATION ADMINISTRATIVE OFFICER (AO):

Dr. Phelesia Foster, Administrative Officer
141 Experiment Station Road

Stoneville, MS 38776

Phone: (662) 686-5424
Phelesia.Foster@usda.gov

0. LOCATION POINT OF CONTACT: (LPOC)

Scott Feutz, Location Support Services 141 Experiment Station Road Stoneville, MS 38776 Phone: (662) 820-5454 Scott.Feutz@usda.gov

0. ENGINEERING PROJECT MANAGER (EPM)

Kevin Magee, P.E., Engineering Project Manager USDA, ARS SEA Facilities Engineering P.O. Box 38, 141 Experiment Station Road Stoneville, MS 38776 Cell: (662) 336-0712 Kevin.Magee@usda.gov

1.3 SCOPE OF SERVICES:

The Contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein. Contractor shall furnish all labor, materials, and equipment required to perform interior surface preparation and apply a high-performance coating to the interior of a 200,000 gallon steel water storage tank located at 141 Experiment Station Road, Stoneville MS 38776. All previous coatings used on this storage tank are lead free. This tank was last inspected in July 2020. A project to correct OSHA issues was performed in the Fall of 2020. A copy of the report is available for inspection by prospective bidders.

1.4 APPLICABLE PUBLICATIONS AND REFERENCES:

The publications listed below form a part of this specification to the extent referenced. The publications referred to in text by the basic designation only.

ANSI/NSF 61 Drinking Water System Components – Health Effects NSF/ANSI/CAN 600-2019 Health Effects Solvent Criteria

ASTM D 16 Terminology Relating to Paint, Varnish, Lacquer, and related Products
AWWA D102-06 Coating Steel Water-Storage Tanks
NACE RPO188-99 Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates
SSPC-PA-2 Measurement of Dry Coating Thickness with Magnetic Gages
SSPC-SP10/NACE 2 Near-White Metal Blast Cleaning
SSCP-SP1 Solvent Cleaning
AWWA C 652-02Disinfection of Water Storage Facilities

1.5 DEFINITIONS:

1. Definition of Painting Terms: ASTM D16, unless otherwise specified

2. Coatings: Paint or heavy duty finishes for use on surfaces subject to interior and exterior exposure, submergence, high moisture, or splash, including primers, intermediate coats, and finish coats.

3. Interior Wet: Interior surfaces subject to immersion or splash, including the interior roof structure.
4. Interior Dry: Interior surfaces subject to normal temperature, humidity and condensation.
5. First Coat: Shop primer or field primer.
6. Second, Third, Intermediate, or Finish Coats: Successive finish coats applied over the first coat.
7. DFT: Dry Film Thickness as measured in Mils (1/1000 of an inch)

1.6 QUALITY CONTROL AND ASSURANCE:

A. Certification Requirements:

1. The work performed under this contract shall be subject to continuous audit by the COR & EPM. Quality control is the exclusive responsibility of the Contractor.

2. All coatings shall conform to OSHA requirements for allowable exposure to lead and other hazardous substances.

3. All coatings in contact with potable water or within potable water reservoirs shall be certified according to NSF Std. 61 and shall be NSF/ANSI/CAN 600 compliant.

B. Product Manufacturer:
1. Manufacturer of coatings shall be Induron or approved equal. An approved equal at a minimum shall be a company that specializes in producing high quality industrial coatingmaterials and have a demonstrable history of 10 years or more in supplying potable water compatible epoxy coating systems for the interior steel water tanks.

C. Qualifications:

1. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this project.

2. Applicator Qualifications - Engage an experienced applicator with 5 years or more experience that has successfully completed coating system applications similar in material and extent to those indicated in this statement of work and provide 5 references for evaluation and verification.

D. Single Source Responsibility:

1. Provide coating material and thinners produced by the same manufacturer for each system on all surfaces of the tank.

1. Field Painting Pre-Application Meeting:

Hold a pre-application meeting before the start of field surface preparation and coating application. Require attendance of parties directly affecting work of this section, including the engineer, applicator, inspector, and coating manufacturer’s representative. Review the specifications to ensure each parties’ responsibilities are understood. Subjects to be discussed are: environmental requirements, protection of surfaces not scheduled to be coated, surface preparation, application, disinfection, repair, field quality control, cleaning, protection of coating systems, annual inspection, coordination with other work and any other areas of concern expressed at the meeting.

F. All work shall be in compliance with the latest version of ANSI/AWWA D100-11 and D102-14.

G. All work shall be in accordance with OSHA Safety and Health Standards.

1.7 SUBMITTALS:

A. Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR & EPM for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. All submittals shall be sent electronically to the EPM, COR, LPOC, and CO for approval. Allow 7 days for review. Contractor is responsible for any costs incurred for materials ordered without prior approval.

1.8 DELIVERY, STORAGE, AND HANDLING :

A. Material shall be delivered to the site in original containers with labels intact and seals unbroken. Labels should provide the following information: material name, coating manufacturer, color name and number, batch or lot number, date of manufacture, mixing and thinning instructions.

B. All coatings shall be stored in an enclosed structure to protect them from weather and excessive heat or cold. Flammable coatings must be stored to conform to City, County, State and Federal safety codes for flammable coatings or paint materials. At all times coatings shall be protected from freezing.

C. All empty containers shall be disposed of in accordance with local, state and federal regulations.

1.9 PROJECT/SITE CONDITIONS

A. Climate:

No paint shall be applied when the air or surface temperature, as measured in the shade, is below that which is recommended by the manufacturer. Paint shall not be applied to wet or damp surfaces, and shall not be applied in rain, snow, fog, mist, or when the surface temperature will be less than 5 F above the dew point. No paint shall be applied when it is expected that the surface temperature will drop below the manufacturer's recommendation within 2 - 4 hours after the application of the paint. Dew or moisture condensation should be anticipated, and if such conditions are prevalent, painting shall be delayed until it is certain that the surfaces are dry. In addition, the days painting shall be completed well in advance of the probable time of day when moisture condensation will occur in order to permit the film the required drying time as specified by the manufacturer prior to the formation of moisture.

B. Ventilation:

Provide ventilation during coating curing stage in confined or enclosed areas in accordance with AWWA D102-06, Section A.7.5. Forced air ventilation shall be maintained for a minimum of four (4) days following interior coating application to assist in curing process.

C. Dust and Contaminants:

Schedule coating work to avoid excessive dust and airborne contaminants. Protect work areas from excessive dust and airborne contaminants during coating application and curing.

A. Containment:

During surface preparation, airborne particulates and debris from the removal of coatings should be effectively contained to prevent contamination of surrounding air, soil and/or water. Minimizing or eliminating the airborne particulate by containing and collecting debris generated should reduce these environmental hazards. The control of these airborne particulates should comply with SSPC Guide 6 Guide for Containing Debris Generated During Paint Removal Operations as well as all local, state and federal regulations.

B. Disposal:

Due to the date of the original installation of this tank (2001) and the nature of all subsequent coatings applied, it can be safely assumed that all existing interior and exterior coatings on this tank are lead-free, therefore normal blasting and disposal procedures can be used. If the contractor has any concerns regarding hazardous existing materials , it shall be brought to the attention of the CO and EPM immediately for further discussion and planning.

PART 2 – PRODUCTS

2.1 GENERAL

A. Approved Manufacturers:
Induron Coatings
P.O. Box 2371
Birmingham, AL 35201-2371
Customer Service: 800-324-9584
Website: Induron.com

B. Materials:

Coating products of Induron Coatings, Inc. are listed as a standard of quality and performance. Only coatings that meet or exceed the performance of these specified coatings may be submitted for use. No substitutions will be considered unless the CO and EPM has received a written request for approval at least 10 days prior to the bid date for receipt of bids and only if it is deemed an approved equal. Each request shall include the name of the specified material; and a complete description of the proposed substitute including performance and test data, cure times, recoat windows, and generic composition. No request for substitution shall be considered that would decrease film thickness, offer a change in the generic type of coating specified or the number of coats specified. The decision of the CO and EPM regarding approval or disapproval of the proposed substitution shall be final.

C. Colors: Colors shall be as selected by the EPM.

D. Thinning, Mixing and Tinting:

1. Where thinning is necessary, only the products of the manufacturer furnishing the coating will be allowed. All thinning shall be done in strict accordance with the coating manufacturer’s recommendations.

2. Mix in accordance to the manufacturer’s recommendations.

3. Each coat shall be slightly different in shade than the preceding coat, unless otherwise noted.

PART 3 – EXECUTION

3.1 GENERAL BID SCHEDULE

A. Examination:
Examine areas and conditions under which coating systems are to be applied. Notify CO, COR and EPM of areas or conditions that are not acceptable. Do not begin surface preparation or application until unacceptable areas or conditions have been corrected.

B. Protection of Surfaces Not Scheduled to be Coated:

Where applicable, protect areas and surfaces not scheduled to be coated from damage during surface preparation and application of coatings. Immediately remove coatings that fall on surrounding areas and surfaces not scheduled to be coated.

C. Coating Systems:

Steel Interior Wet:
1. System: Ceramic Epoxy Primer/ 70% Solids Ceramic Epoxy/ 70% Ceramic Epoxy
2. AWWA D102-06: Inside Coating System 3
3. ANSI/NSF 61 Certified

4. Surface Preparation: SSPC-SP10 Near White Blast Cleaning. No steel shot or steel grit blast media to be used as final surface preparation for surfaces to be placed in immersion service.

5. Surface Profile: 1.5-2.5 mils
6. Primer: Ceramaprime applied to achieve 2.5-3.5 dry mils. Color: Tan.
7. Stripe Coat: Ceramapure TL70 applied by brush to achieve 3.0-5.0 dry mils. Color: Pool Blue.
8. 1st Coat: Ceramapure TL70 applied to achieve 10-15 dry mils. Color: Pool Blue.
9. 2nd Coat Ceramapure Tl 70 applied to achieve 10-15 dry Mils Color Pool Blue
9. Total System Minimum DFT: 22.5 mils.

D. Application

1. Prepare steel substrate in accordance with Coating Manufacturer’s instructions.
2. Ensure surfaces are dry.

3. Prior to field touch up of shop primed steel, all surfaces shall be cleaned to remove all surface contamination including oil, grease, dust, dirt and foreign matter. All rusted, abraded, and unpainted areas shall be prepared to specified surface preparation before primer is applied.

4. Abrasive blast cleaned surfaces shall be coated the same day as the cleaning is performed. If rust or contamination appears as a result of delay in primer application, the surface shall be cleaned to specified surface preparation before primer is applied.

5. Apply coatings in accordance with coating manufacturer’s instructions.

6. Mix and thin coatings, including multi-component materials, in accordance with manufacturer’s instructions.

7. Keep containers closed when not in use to avoid contamination.

8. Do not use mixed coatings beyond pot life limits.

9. Use application equipment, tools, pressure settings, and techniques in accordance with manufacturer’s instructions.

10. After sufficient cure of the field prime coat, apply a stripe coat to the interior wet areas with a brush to critical locations on steel such as welds, corners, and edges using specified intermediate coat.

11. Uniformly apply coatings at spreading rate required to achieve specified DFT.

12. Apply coatings to be free of film defects that would adversely affect performance of the coating system. Apply exterior coatings to be free of characteristics or defect that adversely affect appearance.

13. Interior: Caulk all unwelded roof seams, connections, and crevices to prevent corrosion and staining.

E. Repair

1. Damaged Materials: repair or replace damaged materials and surfaces not scheduled to be coated.

2. Damaged Coatings: Touch-up or repair damaged coatings. Touch-up of minor damage shall be acceptable where the result is not visibly different from adjacent surfaces.

3. Coating Defects: Repair in accordance with coating manufacturer’s instructions coatings that exhibit film characteristics or defects that would adversely affect performance or appearance of coating systems.

4. Drill additional weep holes in balcony flooring in areas that show signs of having ponding water.

3.2 TESTING EQUIPMENT AND PROCEDURES

A. General:

The Contractor shall have on the project site the following testing equipment. Equipment shall be in calibration and proper working order. Equipment shall be used in accordance with the manufacturers' instructions or as directed by the EPM or EPM representative. The EPM & COR shall be notified of time of testing so that he might be present to witness testing. The Contractor shall keep a daily log of environmental conditions, work schedule, and any other pertinent information. The log shall be turned over to the Owner at the end of the project to be included in the permanent record.

1. Sling Psychrometer: Relative humidity and dew point readings shall be taken at intervals throughout the days work. Readings shall be taken at the start of the mornings work, mid day and afternoon. Should environmental conditions change, additional reading shall be taken to assure that coatings are being applied under the conditions as outlined by the coatings manufacturer.

2. Surface Temperature Thermometer: Surface temperatures shall be taken in areas where work is being performed. Surface temperature shall be that as specified by the coatings manufacturer.

3. Replica Tape & Micrometer: Testex X-Course Replica Tape shall be employed to determine the surface profile of blasted surfaces. Surface profile shall be as specified.

4. Dry Film Thickness Measurements: Dry film thickness reading shall be taken with a properly calibrated (per the manufacturer's instructions) Type 1 (magnetic) or Type 2 (electromagnetic) instrument. Dry film thickness reading will be taken and recorded in accordance with guidelines set forth in SSPC-PA2 Measurement of Dry Coating Thickness with Magnetic Gages. The Contractor shall provide ladders, rigging, etc. as necessary to allow the Engineer to spot check paint thickness of each coat.

5. Holiday Detection: After completion of the interior coating system, interior surfaces shall be holiday detected in accordance with NACE RPO188-99 Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates. Holiday detector shall be a Tinker & Rasor Model M-1 or equal. Areas found to have holidays shall be marked and repaired in accordance with the paint manufacturer's instructions. The Engineer shall be notified of time of testing so that he might be present to witness testing.

3.3 DISINFECTION

A. Disinfection of Water Contact Surfaces and Filling of Water Storage Tanks:
a.The interior of the tank and the wet riser shall be thoroughly washed and disinfected in accordance with AWWA C652 Method 2 or 3. The EPM shall approve the method of disinfection.
b.Do not disinfect water contact surfaces or fill water storage tanks until application of coating systems is complete, coatings have fully cured, and field quality control inspection is complete.
c.Allow number of days in accordance with manufacturer’s instructions and as directed by engineer for full cure of coating systems on water contact before flushing, disinfecting, or filling with water.
d.The tank shall be filled with clean water furnished by the owner.

B. Bacteriological Testing: Upon completion of the disinfection process the owner or his representative shall arrange for bacteriological testing of water samples. The tank shall not be put into service until safe results are obtained.

3.4 FIRST ANNIVERSARY INSPECTION

A. Owner shall establish and notify contractor giving at least 30 days notice as to the date and method of inspection.

B. If an inspection date has not been established within 13 months after the coating work was completed, the first anniversary inspection shall be considered to be waived.

C. First anniversary inspection shall follow the guidelines set forth in AWWA D102-06 Section 5.2.

3.5 REQUISITE REPAIR WORK

General – Complete all repair work before intermediate coat of paint is applied unless indicated otherwise. Base Bid Items.

1. Interior Coating System per specifications.

2. Inspect and Adjust Windage rods and riser stay rods as needed, to withstand 100 mph winds blowing from any direction as required by AWWA D100-05.

3. Clean and lubricate all moving parts of the liquid level indicator.

4. Drill additional weep holes in balcony flooring in areas that show signs of having ponding water.

4.0 ADDITIONAL PROJECT REQUIREMENTS:

1. This Project is to replace the interior lining of the 200K gallon elevated potable water tank at the USDA ARS Research Facility at Stoneville, MS. The contractor is to provide all materials, equipment, labor, supervision and expertise to prepare the surface with a #10 blast and apply all coatings per the manufacturers recommendations. The contractor shall provide a 7 day notice before mobilizing on site to allow USDA to drain the tank and make preparations to switch to backup water supply.

2. In addition to any warranty that may be provided by material suppliers or subcontractors, USDA will be provided an additional Warranty from the Contractor to cover labor and materials for a period of one year to be verified and in place before project closeout.

The contractor will provide a turn-key product to include, but not limited to, all materials as specified, the proper demolition as specified, and the installation of all material as specified. This Project is located at the USDA ARS Campus at 141 Experiment Station Road, Stoneville, MS 38776.

a. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.

b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, and health and safety codes, in effect at the time of contract award.

c. This project falls under the DAVIS BACON Wage Act.

d. Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be obtained through: https://www.sam.gov/

e. Utilization of Bio-Based Products: To the extent possible, the contractor shall make every effort to utilize products and material based from bio-based materials, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: https://www.biopreferred.gov

4.1 Description of Work:

1. The Contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.

1. The Contractor will provide all work per Section 4.1 and properly dispose of all waste material.

1. Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during installation. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.

1. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. A site visit is not required. However, no compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.

1. All installation to be per Manufacturer’s recommendation.

1. Contractor will verify all dimensions and existing site conditions prior to beginning work.

1. Contractor shall keep work area clean on a daily basis and take measures to control debris while work is being performed.

1. Contractor is required to manage the project and consult with the Government prior to beginning all work phases. And, to work in a manner that minimizes the impact of the work on Government operations, research, and functions.

1. Contractor shall organize and schedule the work such that the water tank will be out of operation the least amount possible. Contractor shall coordinate with local point of contact to choose the window of work.

1. Contractor will provide weekly reports of work performed to the COR or location monitor.

1. Contractor shall remove and dispose of all construction related materials from all work areas on a daily basis, and remove these waste materials from the site on a weekly basis.

1. All work must be performed in such a manner as to not adversely affect daily operations of the facility, its workers, and the onsite facility operations.

1. Contractor shall have a designated superintendent on the job at all times when working on this project.

5.0 ADDITIONAL GENERAL REQUIREMENTS:

5.1 Permits

Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Installation

It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.3 Protection of Work and Property/Safety Requirements

1. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) 10 days after contract award. SSSP / APP shall be approved by the Government before construction work commences. Government will supply samples if requested.

1. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.

1. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. If necessary, the Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

1. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.

5.4 Temporary Facilities

1. Temporary utilities of electricity and water will be furnished to the Contractor by the Government.

1. Contractor is responsible for providing portable toilet facilities for contractors use. Location to place facilities will be provided during pre-construction meeting.

5.5 Materials and Equipment

1. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.

1. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.6 Cleanup

The construction site shall be kept clean and free of debris at all times. Disposal of the old equipment and /or material is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

5.7 Warranty

1. Submit data concerning the standard one-year warranty for workmanship and materials as well as any warranty that may be provided by material suppliers, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

5.8 Final Payment/Contract Closeout

The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):

1. General contractor’s minimum one (1) year warranty on work.

1. Release of liens.

1. Final Invoice

6.0 PROJECT SCHEDULE

The Contract time for this project is 90 calendar days from Notice to Proceed. The notice to proceed will be issued at the preconstruction conference. Any requests for additional time must be submitted by the Contractor and received by the Contracting Officer well before the expiration of the period of performance.