Statement of Work (SOW) Paint Float.doc
DOC document 89 KB Posted
- Attached to
- Floating Scaffold/Work Platforms
- Solicitation number
- 14501FY25MAINTDOCK
About this file
This Statement of Work (SOW) details a requirement for the US Coast Guard to procure a custom floating scaffold dock for maintenance of the USCGC POLAR STAR. The solicitation (Number 14501FY25MAINTDOCK) seeks a one-tier aluminum scaffolding paint float system designed to OSHA standards, capable of supporting 5 personnel, with specific technical specifications including a 10'x16' floating dock with PVC decking, built-in ladders, aluminum frames and railings, safety harness slide rail, and corner cleats for mooring. The procurement is a total small business set-aside with a firm-fixed-price contract, targeting contractors who can deliver the specialized marine maintenance platform to the ship's location in Seattle, WA. Interested vendors must be registered in SAM.gov and submit quotes directly to specified Coast Guard contacts, with shipping fees included in the total cost proposal.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
USCGC POLAR STAR FLOATING MAINTENACE DOCK
A. GENERAL INFORMATION
1. Title of Project: USCGC POLAR STAR FLOATING MAINTENCE DOCK
2. Scope of Work: The contractor shall provide all resources necessary to accomplish the tasks and deliverables described in this Statement of Work (SOW). The contractor shall provide a one-tier floating scaffold dock as outlined in Contractor Requirements.
3. Background: Contractor is to manufacture and deliver a floating scaffold dock that will be used for maintenance of ships.
4. Type of Contract Contemplated: This will be a firm-fixed priced purchase order.
B. CONTRACTOR REQUIREMENTS
Contractor is to provide the below product:
This will be a one tier aluminum scaffolding paint float system with a back side railing constructed in accordance with OSHA 29CFR1915 and OSHA 29CFR1926.452 standards.71, capable of supporting 5 personnel.
Scaffolding system will have built in ladders for access.
Frames and railings will be made of aluminum.
Railings will have aluminum toe guards.
The Platform will be approximately 5-7’ tall.
Platform will stagger inward by approximately 2’.
Platform will have a safety harness slide rail.
Each deck will have PVC decking.
The scaffolding will be secured on a floating dock (also PVC decking) that will be approximately 10’x16’ and have proper number of floats to keep it buoyant.
Each corner of the dock will have 1 cleat (4 in total). The cleats must be strong enough to moor the paint float to a pier. Also the floating dock will have lifting eyes in each corner that are strong enough to lift the paint float with a sling.
Every deck level and dock will have rub rails around the decks.
Weight of the paint float will coincide with the building materials and stability of the paint float.
*These dimensions are approximate and may be adjusted for stability and buoyancy purposes by a professional engineer and meet the OSHA standards listed above.
C. DELIVERY OR DELIVERABLES
Furnished product will be delivered to the below address. Freight charges to be listed on quotations.
USCGC Polar Star (WAGB 10) 1519 Alaskan Way S
Seattle WA 98134
File details come from the government source that posted it. Updated .