This document is a Statement of Work (SOW) for repairs and modifications to Building 640 at Robins AFB, Georgia. The 581st Software Engineering Squadron (SWES) has a requirement to make changes to the conference room in this building.

The key tasks include removing and repairing a projection screen, painting the entrance doors, foyer, and conference room, and providing all necessary painting materials and equipment. The work is to be coordinated with the SWES team, and the Primary Contracting Officer has overall responsibility and approval authority. The location of the work is 639 Tech Road, Bldg. 640, Robins AFB, GA 31098, and the Point of Contact is Mike West at 478-926-4714.

View the file

Other files for this federal contract opportunity

Other files attached to Bld640 Paint/Repairs for 581st Software Engineering Squadron (SWES), newest first.
File Type Posted
Solicitation - FA857924Q0031.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

For

12418 Bld640 Paint and Repair, BAF 76165

402nd Software Engineering Group (402 SWEG)

280th Software Engineering Squadron (SWES)

15 July 2024

1.0 GENERAL INFORMATION

1.1 Scope

The 581st Software Engineering Squadron (SWES) has a requirement to make modifications and repairs to Building 640 Conference room.

2.0 SPECIAL CONSIDERATIONS

2.1 Program and Engineering Management

All contractor tasks and requirements covered by this document shall be coordinated with the 581st SWES team. Overall responsibility and approval of any changes to the contract or attachments resides with the Primary Contracting Officer (PCO).

2.2 Contract Management

Overall responsibility and approval reside with the PCO. No conversation, recommendation, or direction, whether given directly or implied by Government personnel or representative, that will affect the scope, schedule, or price of the program covered by this SOW, shall be acted upon by the contractor unless specifically directed in writing by the PCO.

3.0 CONTRACTOR TASKING AND REQUIREMENTS

3.1 The contractor shall plan, direct, coordinate, monitor, evaluate, and control contractor tasks specified in this SOW. The contractor shall notify the PCO, by email, of any management problems requiring Government action.

3.2 The contractor shall remove 10’X5’ projection screen from south side of the conference room and repair the opening in the wall.

3.3 The contractor shall paint:

3.3.1 The entrance doors (double doors 36” each) into the foyer.

3.3.2 All four walls in the foyer (11’X9’ walls with a 9’ ceiling).

3.3.3 The entrance doors (double doors 36” each) into Conference Room #1 Rm2204.

3.3.4 All four walls in Conference Room #1 RM# 2204 (30’X18’ with an 8’ ceiling).

3.3.5 The entrance door into Rm# 2400 (single 32” wide door).

3.4 The contractor shall provide all paint/painting materials and equipment required to complete tasks in this SOW.

4.0 LOCATION OF WORK AND POC

4.1 639 Tech Road Bldg. 640 Robins AFB, GA 31098

4.2 Mike West: 478 926 4714

1.1 Scope
2.1 Program and Engineering Management
3.0 CONTRACTOR TASKING AND REQUIREMENTS
4.0 LOCATION OF WORK AND POC

File details come from the government source that posted it. Updated .