Statement of Work SOW Backflow Preventers BFP removal relocation.docx
DOCX document 61 KB Posted
- Attached to
- Relocate 2 Backflow Preventers (BFP) Federal contract opportunity
- Solicitation number
- 12405B23Q0476
About this file
This statement of work outlines requirements for a construction project to relocate and replace backflow preventers at a USDA facility. The selected contractor will remove two existing underground backflow preventers and install new 6-inch backflow preventers in an above-ground enclosure on a concrete pad. The contractor must visit the site, submit safety and installation plans, use approved materials, schedule work to minimize disruptions, complete work within 180 days, and provide a one-year warranty on all workmanship and materials. The related federal contract opportunity is solicitation number 12405B23Q0476 to relocate two backflow preventers for the USDA Agricultural Research Service Field Research Implementation and Information Delivery.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF1442 SOLICITATION 12405B23Q0476.pdf | ||
| Experience Modification Rate EMR Insurance Contractor Certification Solicitation 12405B23Q0476.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
Relocate and Replace Building 1 Backflow Preventers
U.S. National Poultry Research Center 950 College Station Road Athens, Georgia 30605
1. Scope of Work The contractor shall provide all professional services necessary to complete the removal of the existing main water line backflow preventers from underground vault and the installation of new backflow preventers in a new above ground enclosure as described.
The contractor shall include all services and field labor, equipment (including cranes, rigging and material handling equipment), materials, testing and personal protective equipment necessary to perform the work.
Equipment and services provided by the Government for contractor use are listed below:
· None provided.
1.1 Base Bid
The contractor shall provide a detailed proposal and cost breakdown for the entire project including submittals for proposed equipment and materials.
1.2 Site Visit
Contractors are strongly encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.
Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid.
2. Codes and Standards Applicable Codes and Standards apply and are not limited to the following.
| ANSI - | American National Standards Institute. |
| ASME - | American Society of Mechanical Engineers. |
| NEC - | National Electrical Code, NFPA 72. |
| OSHA - | Occupational Safety and Health Administration |
| ADA – | Americans with Disabilities Act |
All work must meet Local, State and Federal codes, and latest IBC codes.
3. Project Summary Removal of 2 existing backflow preventers serving Building 1 from underground vault and installation of two new 6” backflow preventers (BFP) in a new, above ground enclosure on a concrete pad.
1) In order to minimize disruptions to facility operations, outages will be kept to a minimum.
2) Install spool pieces in place of existing BFPs.
3) Install piping to new BFP location.
4) Install new concrete pad and BFP enclosure. Enclosure must be designed for BFP installation, must meet or exceed all BFP manufacturer’s requirements and must include adequate freeze protection.
5) All piping and components including backflow preventers must be approved for use in Athens-Clarke County Public Utilities water system.
6) New backflow preventers will be tested certified before final inspection and acceptance.
The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to traffic, daily operations and research programs.
4. Safety The contractor will submit a Site Safety Specific Plan (SSSP) in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.
Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel.
5. Contractor Requirements The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.
The project work shall be performed per the following guidelines:
1) Contractor will verify all dimensions and site conditions prior to beginning work.
2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.
3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site weekly.
4) Contractor is required to manage the project and consult with the Government prior to beginning all work.
5) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.
6) All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances, and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.
6. Material Submittals Submittals and O&M documentation must be provided for all materials used on this project.
7. Pre-Construction Submittals Contractor’s Site Specific Safety Plan (SSSP) must be provided to and approved by USDA before installation can begin.
8. Damage to Property:
The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the USDA.
9. Inspection and Acceptance A government representative shall inspect and approve the work. The Contractor shall schedule inspection a minimum of 2 days in advance.
10. Period of Performance The completion of this project shall not exceed 180 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
10.1 Work Hours:
Generally, contractor work hours shall be Monday through Friday, 7:00 A.M. to 4:30 P.M. except on Government holidays for most of the installation work. Tie-in or other work requiring outages will be performed after hours (pre-arranged at least 48 hours in advance).
Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to the schedule change.
11. Guaranty The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period of one (1) year from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.