This is a Statement of Work (SOW) for underground fiber optic cable installation services at Seney National Wildlife Refuge in Seney, Michigan. The contractor shall provide and install armored, direct-burial rated singlemode fiber optic cable (Corning glass) with LC UPC connectors to connect Highline Internet's distribution line at Highway M-77 to the new Headquarters and Visitor Center, and an additional run from the Headquarters building to the existing Maintenance Shop. The cable must be capable of supporting 2 GB service and all parts, protective conduit, and installation labor are contractor-supplied. Highline Internet is identified as the preferred contractor, though alternative state-licensed general contractors with demonstrated fiber optic installation experience and industry-standard termination practices are eligible.

Work shall commence when ground conditions permit trenching, estimated May 1, 2026, with all work completed by June 12, 2026. Normal duty hours are Monday through Friday, 8:00 a.m. to 4:30 p.m. The contractor must coordinate with the Fish and Wildlife Service (FWS) Infrastructure Management Division and Refuge, perform utility locates before excavation, obtain FWS approval for the proposed fiber route, use existing empty conduit beneath the Headquarters and Visitor Center parking lot where possible, and provide an as-built map showing exact fiber routing and burial depth. Deliverables include a fully installed and tested fiber optic system, restoration of disturbed grounds, material submittals for government review, and fiber testing results demonstrating signal performance and continuity. The technical coordinator is Sara Siekierski, Refuge Manager, with Timothy Fuller, Architect, as secondary contact. Quality control measures include proper installation depth and routing, clean terminations with verified optical performance, and accurate final documentation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Type of Service or Construction (NAICS)

Fiber Optic Cable Installation

PR Number:

Instructions: Complete all Bold Elements below and mark N/A for elements that are not applicable and delete sub elements. This will ensure that each element is considered.

1. General:

1.1 Describes the project in general terms:

The Contractor shall provide and install underground fiber optic cabling to supply high-speed internet connectivity to the Seney NWR new Headquarters and Visitor Center and existing Maintenance Shop.

1.2 Purpose/End Application:

Highline Internet has agreed to provide monthly service to Seney NWR. To enable this service, the Refuge requires new direct-burial fiber optic cable connecting the Highline-owned distribution line at highway M-77 to the new Headquarters and Visitor Center, and an additional run from the Headquarters building to the existing Maintenance Shop.

1.3 Product reviewed and selected:

The Contractor shall provide all parts and pieces necessary for a fully functioning fiber optic line including but not limited to:

• Armored, direct-burial rated, singlemode custom fiber optic cable (Corning glass).

• LC UPC connectors on both lead and termination ends.

• Any protective conduit required to meet safety and regional construction standards.

1.4 Contractor Qualifications:

Highline is the preferred contractor due to unique service capability. Alternative contractors must be state-licensed general contractors with demonstrated experience installing underground fiber optic cable and industry-standard termination practices.

1.5 Other:

No additional items noted.

2. Place of Performance and Period of Performance (Where and When)

2.1 Location:

Seney National Wildlife Refuge 1674 Refuge Entrance Road Seney, MI 49883

2.2 Performance start and end date:

Work may begin when ground conditions allow trenching (estimated May 1, 2026).

All work must be completed by June 12, 2026.

2.3 Normal duty hours:

Monday–Friday, 8:00 a.m. – 4:30 p.m.

Contractor must provide emergency contact information.

2.4 Non-duty hours:

Evenings, weekends, and all Federal holidays.

3. Scope

3.1 The Contractor shall:

• Coordinate all work with the FWS Infrastructure Management Division (IMD) and Refuge.

• Install fiber optic cable capable of supporting 2 GB service.

• Avoid disturbance of existing utilities; perform utility locates before excavation.

• Obtain FWS approval for the proposed fiber route (expected along refuge entrance road or service road). See attachment.

• Use the existing empty conduit beneath the new Headquarters and Visitor Center parking lot to avoid trenching through paved areas.

• Install fiber from the Highline-owned highway M-77 line to the new Headquarters and Visitor Center Technology/Security Room.

• Install secondary fiber from HQ to the Maintenance Shop Office.

• Ensure all connections meet Highline service requirements and are compatible with Seney NWR owned equipment.

• Submit all materials for FWS approval prior to installation.

• Provide a final as-built map showing exact fiber routing and burial depth.

4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line item detail on the PR is recommended)

4.1 Clearly state the deliverables required, the schedule for delivery, the quantities, schedule (for multiple items):

Fully installed fiber optic system:

– Highway M-77 to New Headquarters and Visitor Center

– New Headquarters and Visitor Center to Maintenance Shop

• All connectors properly terminated and tested.

• Restoration of disturbed grounds.

• Delivery schedule consistent with Section 2.

4.2 Identify the type of documentation (printed and electronic-such as manuals) to be provided , as well as those quality indicators desired by the Government:

• As-built fiber route map in digital .pdf format.

• Material submittals for Government review and approval.

• Fiber testing results demonstrating signal performance and continuity

5. Data Management Plan (DMP) for Science Data Agency Reference:

Not applicable. No new scientific data is being created.

6. Government-Furnished Equipment (GFE) / Government-Furnished Information

(GFI):

None.

7. Evaluation and Acceptance

7.1 The contractor will be evaluated as detailed herein. Government acceptance is contingent upon: [Either state generally or reference the table in 8.2 if used:

Preferred vendor is Highline. See sole source justification. If this isn’t approved the Government will evaluate the Contractor’s proposal based on:

• Technical capability and experience,

• Qualification of personnel,

• Cost reasonableness and justification,

• Compliance with SOW requirements.

8. Quality Control/Quality Assurance:

8.1 For commercial supplies reference clauses for inspection and acceptance:

Contractor shall implement QC procedures according to industry standards for fiber optic installation.

8.2 Identify and detail measures for assessing quality control and acceptance; each requirement is unique and a table format is visually friendly and may be desirable:

Proper installation depth and routing,

• Clean terminations with verified optical performance,

• Accurate final documentation and mapping,

• Compliance with conduit-use requirements at the new Headquarters and Visitor Center.

9. Technical Coordinator:

9.1 Identify the primary individual responsible for the final product or service:

Sara Siekierski Refuge Manager 1674 Refuge Entrance Road Seney, MI 49883 Email: sara_siekierski@fws.gov Phone: (906) 630-2015

9.2 Identify the secondary or co-individual responsible with same pertinent information:

Timothy Fuller Architect 5600 American Boulevard West Suite 990 Bloomington, MN 55437 Email: timothy_fuller@fws.gov Phone: (612) 713-5186

Existing Maintenance Shop, terminate fiber optic in IT room (maintenance office).

New Headquarters and Visitor Center, install fiber optic to IT room.

Proposed Fiber Route #1:

Refuge Entrance Road

Proposed Fiber Route #2:

Service Road

Approximate beginning of empty buried conduit to New Headquarters and Visitor Center. Proposed fiber route between New

Headquarters and Visitor Center and Maintenance Shop

Highway M-77