Statement of Work- Roof Maintenance.pdf

PDF 266 KB Posted

Attached to
Roof Inspection and Maintenance Services BACH Alaska
Solicitation number
W912D026RA004
Issued by

About this file

This is a Statement of Work (SOW) for semi-annual roof inspection and maintenance services at Bassett Army Community Hospital (BACH) and associated Medical Department Activity Alaska (MEDDAC-AK) facilities.

The contractor shall provide comprehensive roof inspection and maintenance services twice annually—once in spring (by May 15th) and once in late summer (August 30th through September 30th)—for multiple buildings across four locations: Fort Wainwright (6 buildings), Fort Greely (1 building), and Joint Base Elmendorf/Fort Richardson (4 buildings). The primary facility is the 313,202 square-foot BACH, which underwent reroofing with a Carlisle Syntec System in August 2019 carrying a 20-year full system warranty requiring semi-annual inspections and maintenance. The contractor must supply all labor, supervision, materials, equipment (ladders, scaffolds, manlifts, fall protection), and transportation. Inspections shall be performed by personnel with minimum three years' experience in respective roof types, and the contractor must be manufacturer-certified for warranted roofs using only manufacturer-approved materials for repairs. Work shall occur during weekdays 06:30-16:30 without interference to facility operations or patient care, with detailed separate reports provided for each building including digital photographs of defects and minimum one photo per deck area. All contractor and subcontractor employees require Anti-Terrorism Level I training, Operations Security (OPSEC) training, and iWATCH training with certificates submitted. Additional requirements include pre-construction meeting attendance, daily trash removal, site cleanup upon completion, and manpower reporting to the Army contractor manpower database with reporting due by October 31st annually covering the 12-month period ending September 30th.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SERVICES

SCOPE of WORK

SEMI-ANNUAL ROOF INSPECTION

Basset Army Community Hospital

Fort Wainwright, ALASKA

26 March 2026

1.1. Project Summary: Provide Semi-Annual Roof Inspection, Maintenance Services and Reporting on various buildings under the responsibility of MEDDAC-AK as required in accordance with this SOW, and the attachments.

1.2. Facility: Bassett Army Community Hospital (BACH) is a 313,202 square foot combined, Patient Care and VA Clinic facility. The “Essential Facility” designation requires the hospital to withstand a 1000 year event (10.5 earth quake) and be capable of operating without any commercial utility support for 96 hours. Bach Facility

Management Headquartered at Ft Wainwright (Ft WW) is also responsible for (5) other

Facilities on the Ft WW Post; (1) Facility at Ft Greely Post and (4) Facilities at the Joint

Base Elmendorf / Ft Richardson (JBER)

1.3. Purpose: Reroof of the BACH Facility Bldg 4076 was Completed AUG 2019. The new Carlisle Syntec Roof System carries a 20 Year Full System Warranty. The Terms of the Warranty Require a Semi-Annual Roof Inspection and Maintenance (2

Inspections per year) including Documentation of the Inspection and any Maintenance.

In addition the following list of roofs under the MEDDAC-AK Facilities are in various stages of warranty with equally important Inspection and maintenance requirements to insure the integrity and longevity of the facility roof systems.

1.3.1. Ft. WW: Bldgs. 4076, 4077, 3406, 3567, 3597, 4066

Ft Greely: Bldg. 655

JBER Bldgs. 634, 786, (47815 & 47810)

2.0 Execution: The Contractor shall provide all supervision, labor, materials, transportation, equipment ( Ladder’s, Scaffold, Manlift’s, Fall Protection) and storage as required to perform the service in accordance with the attached specifications, sound commercial practices, industry and facility standards, and applicable Manufacturers’ requirements. All work shall be accomplished in accordance with applicable federal, state, and local regulations and safety requirements.

2.1. The Contractor shall Inspect each building roof and provide detailed separate reports for each building on the form provided. Digital photos of any defects, and a minimum of 1 photo per deck area shall be provided with the report.

2.2. Inspections shall occur twice annually: One as early as practical in the spring, once roof surfaces are free of all ice and snow, and not later than May 15th; and a second at the end of summer not sooner than August 30th or later than September 30th.

2.3. Contractor shall use qualified, experienced personnel to perform the inspections and maintenance. Minimum 3 Years experience in each type of Roof Installation.

2.4. Contractor shall be certified by the manufacturer of any warranted roofs, and utilize only Manufacturers approved materials for repairs.

2.5. The Contractor shall perform all service activities so as to avoid interference with the operation of the facility and the work of others. Work shall take place during regular business hours during weekdays Monday – Friday 06:30-16:30. Hours outside those parameters may be granted on prior notification and approval. Under no circumstances shall the work interfere with or delay patient care. Any work affecting Life Safety Code requirements and NFPA will require ILSMs to be implemented to mitigate these deviations during any maintenance operations.

2.6. Upon award of the contract, Contractor shall meet with the Facility Management staff for a Pre-Con meeting, before beginning work. Work will only commence after the issuance of a Notice to Proceed (NTP).

2.7. All trash will be removed from the site on a daily basis. Upon completion of the project, all equipment, materials and any other items associated with the project will be removed from the project site. The site will be left clean.

2.8. Anything mentioned in the Scope of Work and not shown on the drawings, or shown on the drawings and not mentioned in the Scope of Work, shall be of like effect as if shown or mentioned in both.

2.9. The Contractor shall be responsible to verify all measurements and dimensions.

Contractor shall clarify with the Project Manager any discrepancies in measurements shown on the drawings. Conflict and/or clarity issues in reference to items, descriptions or drawings within and of this scope of work will be resolved with the writer of this scope.

2.10. Contractor will be required to provide documentation of Inspection and maintenance to Facilities Management (example included in attachments)

3.0 Site Security: The Contractor’s employees are required by the Anti-Terrorism –

Operational Security form to receive access and general protection policy and procedures which will be provided when obtaining a permit to access post through the front gate. The Contractor’s employees and subcontractor employees requiring access to Army installations, facilities, and controlled access areas shall complete Anti-

Terrorism Level I awareness training which can be accessed online at the following address: http://jko.jten.mil/courses/atl1/launch.html. The Contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee as a submittal. The Contractor’s employees and subcontractor employees requiring access to Army installations, facilities, and controlled access areas shall http://jko.jten.mil/courses/atl1/launch.html complete initial Operations Security (OPSEC) training which can be accessed online at the following address: https://securityawareness.usalearning.gov/opsec/. The

Contractor shall provide certificates of completion for each affected contractor employee and subcontractor employee as a submittal. The Contractor’s personnel are also required to complete the iWATCH training which can be accessed online at the following address:

http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.a spx. Have employees sign attendance roster for completing the iWATCH training and provide as a submittal. The Contractor’s employees are not to divulge anything they may see or hear with regards to the activities and operations of units within the workplace or anywhere else on and off the installation. Employees are not to discuss anything they are doing on the installation to anyone that does not need to know.

4.0 Payments: Contractor shall use WAWF and Input Invoices as a 2 in1 Invoice.

5.0 Contractor Manpower Reporting: The Office of the Assistant Secretary of the

Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor will report ALL contractor manpower (including subcontractor manpower) required for performance of this contract. The contractor is required to completely fill in all the information in the format using the following web address https://contractormanpower.army.pentagon.mil

6.0 The required information includes:

(1) Contracting Office, Contracting Officer, Contracting Officer’s Technical

Representative;

(2) Contract number, including task and delivery order number;

(3) Beginning and ending dates covered by reporting period;

(4) Contractor name, address, phone number, e-mail address, identity of contractor employee entering data;

(5) Estimated direct labor hours (including sub-contractor);

(6) Estimated direct labor dollars paid this reporting period (including sub-contractor);

(7) Total payments (including subcontractor);

(8) Predominant Federal Service Code (FSC) reflecting services provided by contractor

(and separate predominant FSC for each sub-contractor if different);

(9) Organizational title associated with the Unit Identification Code (UIC) for the Army

Requiring Activity (the Army Requiring Activity is responsible for providing the contractor with its UIC for the purposes of reporting this information);

(10) Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and nearest City, Country, when in an overseas location, using standardized nomenclature provided on website);

(11) Presence of deployment or contingency contract language, and, https://securityawareness.usalearning.gov/opsec/ http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx

(12) Number of contractor and sub-contractor employees deployed in theater this reporting period (by country). As part of its submission, the contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement.

Reporting period will be the period of performance not to exceed 12 months ending

September 30 of each government fiscal year and must be reported by 31 October of each calendar year.

END SCOPE