Statement of Work _Residence Remodel Chesapeake.docx
DOCX document 54 KB Posted
- Attached to
- Residence Remodel Federal contract opportunity
- Solicitation number
- 31040PRQ240000126_1
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to renovate the kitchen and living spaces of a Coast Guard property located at 213 Tree Fern Dr., Chesapeake, VA 23322.
The SOW requires the contractor to provide all labor, supervision, materials, and permits necessary to modify the existing cabinetry, install new natural gas piping and power for appliances, replace the kitchen backsplash, and install new recessed lighting in the dining and living rooms. The Coast Guard will procure and install the new appliances. The period of performance is 21 calendar days, and the work must be performed Monday through Friday between 0730 and 1600 EST, except for federal holidays. The contractor must provide a project plan, conduct daily progress meetings with the Contracting Officer's Representative (COR), and comply with all applicable local, state, and federal regulations. The government will not provide any resources, and the contractor must furnish all necessary facilities, equipment, and services. The COR will review and accept deliverables within 2 business days.
The related federal contract opportunity, Solicitation #31040PRQ240000126_1, is for the residence remodel project described in the SOW. The estimated price range is $25,000 to $100,000, and the anticipated award will be made within one week of the solicitation closing on April 12, 2024, at 1700 EST. A site visit is mandatory on April 9, 2024, from 0900 to 1400 EST, unless a site visit was conducted for the previous solicitation between March 15 and March 29. Award will be based on best value, considering price, ability to meet requirements, and past performance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Chesapeake Residence Compliance.docx | DOCX document | |
| GE Appliance list for refrence.png | PNG image | |
| Electric oven-microwave combo to go next to fridge.jpg | JPG image | |
| Crawlspace 2.jpg | JPG image | |
| Remove ceiling fan add 6 can recessed lights.jpg | JPG image | |
| Wall oven microwave combo 1.jpg | JPG image | |
| SF-18 RFQ.pdf | ||
| WDOL Residence Remodel.pdf | ||
| Construction Clauses and Provisions FAC 2023 01.doc | DOC document | |
| CONSTRUCTION DAVIS-BACON SERVICE CONTRACT ACT.pdf | ||
| Kitchen backsplash 2.jpg | JPG image | |
| Kitchen backsplash 3.jpg | JPG image | |
| Nat gas meter.jpg | JPG image | |
| Crawlspace 1.jpg | JPG image | |
| Kitchen backsplash 1.jpg | JPG image | |
| Wall oven microwave combo 2.jpg | JPG image | |
| Remove overhead light and install 4 can recessed lights.jpg | JPG image | |
| Electrical panel.jpg | JPG image |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #:31040PRQ240000126_1
STATEMENT OF WORK
STATEMENT OF WORK (SOW)
FOR
Residence Remodel Solicitation Released: 4/3/2024
1.0 GENERAL
1.1 BACKGROUND
The purpose of this project is to renovate the kitchen and living spaces within the Coast Guard property at 213 Tree Fern Dr. Chesapeake, VA 23322 to facilitate a functional environment that meets the properties intended purposes.
1.2 SCOPE
Contractor shall provide all labor, supervision, tools, equipment, material, transportation, incidentals, fees, permits, licenses, and insurance necessary to renovate the kitchen and living spaces at 213 Tree Fern Dr. Chesapeake, VA 23322 in accordance with all local, state and federal regulations. This work includes but is not limited to: Modifying the existing cabinetry to facilitate new appliances, providing all necessary new natural gas piping to appliances, providing all necessary power to new appliances, replacing the existing kitchen tile backsplash, replacing existing light fixtures with recessed lights and providing all necessary power. Performing all finish work (painting/trim/finish) to match existing. The Coast Guard is responsible for procurement and installation of the new appliances.
1.3 OBJECTIVE
The objective of this project is to modify the residences existing kitchen and living spaces to meet the needs and requirements of the Coast Guard.
1.4 APPLICABLE DOCUMENTS
1.4.1 Compliance Documents
The following documents provide specifications, standards, or guidelines that must be complied with in order to meet the requirements of this contract:
1. Contractor is to provide submittals on all cabinetry modifications regarding materials and finishes, light fixture cutsheets, details on mechanical work to include gas valve locations and tie-in details, exhaust hood ductwork details, ceramic tile specs, paint specs, etc.…
2. Documents to support all permits required by the City of Chesapeake, this should include a copy of the permit and all correspondence regarding inspections to final approval.
3. All work is to be completed in accordance with all applicable local, state, and federal regulations (safety, environmental, permits, inspections, etc).
1.4.2 Reference Documents
The following documents may be helpful to the Contractor in performing the work described in this document:
Attached Photos 1 through 12
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 Range Space Modification
2.1.1 Modify existing range space cabinetry and countertop to facilitate new natural gas range install. Paint, trim and finish to match existing. (GE model# PGS930YPFS)
2.1.2 Install all necessary natural gas piping and valves to existing range location to facilitate upgrade from electric to natural gas range install.
2.1.3 Install all necessary power required for new natural gas range operation. Residence already has natural gas capabilties.
2.2. Exhaust Hood Space Modification
2.2.1 Modify existing cabinetry above range space to accommodate the installation of new exhaust hood. This will require extensive modifications to existing cabinetry to accomidate new appliance install. Paint, trim and finish to match existing. (GE model# UVW9301SLSS)
2.2.2 Install all necessary hood exhaust ducting and exterior vent cover required to vent system to the rear exterior of the resisdence. Paint, trim and finish to match existing.
2.2.3 Install all necessary power required for new exhaust hood operation.
2.3 Microwave/Convection Wall Oven Space Modification
2.3.1 Modify existing cabinetry (left of refrigerator space) to accommodate the install of new microwave/convection wall oven (GE model# PT7800SHSS). This will require extensive modifications to existing cabinetry to accomidate new appliance install. Paint, trim and finish to match existing.
2.3.2 Install all necessary power required for new microwave/convection wall oven proper operation.
2.4 Kitchen Tile Backsplash Replacment
2.4.1 Demo existing tile backsplash.
2.4.2 Replace/install backer board as necessary.
2.4.3 Install new tile backsplash and grout. (3x6 subway tiles, color of tile and grout TBD from submittal but look to match existing kitchen colors)
2.4.4 Repair drywall, finish and paint to match existing.
2.5 Dining Room Lights Installation
2.5.1 Remove existing chandelier
2.5.2 Install (4) new dimmable recessed can lights and provide all necessary power and switchlegs to support proper operation.
2.5.3 Repair drywall, finish and paint to match existing.
2.6 Living Room Lights Installation
2.6.1 Remove existing ceiling fan with light.
2.6.2 Install (6) new dimmable recessed can lights and provide all necessary power and switchlegs to support proper operation.
2.6.3 Repair drywall, finish and paint to match existing.
3.0 CONTRACTOR PERSONNEL
3.1 QUALIFIED PERSONNEL
The Contractor must provide qualified personnel to perform all requirements specified in this SOW.
3.2 CONTINUITY OF SUPPORT
The Contractor must ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor must ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor must provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence. Otherwise, the Contractor must provide a fully qualified replacement.
3.3 KEY PERSONNEL
Before replacing any individual designated as Key by the Government, the Contractor must notify the Contracting Officer no less than 15 business days in advance, submit written justification for replacement, and provide the name and qualifications of any proposed substitute(s). All proposed substitutes must possess qualifications equal to or superior to those of the Key person being replaced, unless otherwise approved by the Contracting Officer. The Contractor must not replace Key Contractor personnel without approval from the Contracting Officer. The following Contractor personnel are designated as Key for this requirement. Note: The Government may designate additional Contractor personnel as Key at the time of award.
Project Manager/Superintendent
3.3.1 Contractor Key personnel must not be assigned by the Contractor to more than one key position for this requirement.
3.4 PROJECT MANAGER
The Contractor must provide a Project Manager who must be responsible for all Contractor work performed under this SOW. The Project Manager must be a single point of contact for the Contracting Officer and the COR. The name of the Project Manager, and the name(s) of any alternate(s) who must act for the Contractor in the absence of the Project Manager, must be provided to the Government as part of the Contractor's proposal. The Project Manager is further designated as Key by the Government. During any absence of the Project Manager, only one alternate must have full authority to act for the Contractor on all matters relating to work performed under this contract. The Project Manager and all designated alternates must be able to read, write, speak and understand English. Additionally, the Contractor must not replace the Project Manager without prior approval from the Contracting Officer.
3.4.1 The Project Manager must be available to the COR via telephone between the hours of 0730 and 1600 EST, Monday through Friday, and must respond to a request for discussion or resolution of technical problems within 2 hours of notification.
3.4.2 The Project Manager shall be an employee of the prime contractor not the subcontractor if used. All correspondence shall only be relayed between them and the government.
3.5 EMPLOYEE IDENTIFICATION
3.5.1 Contractor employees visiting Government facilities must wear an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees must comply with all Government escort rules and requirements. All Contractor employees must identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times.
3.5.2 Contractor employees working on-site at Government facilities must wear a Government issued identification badge. All Contractor employees must identify themselves as Contractors when their status is not readily apparent (in meetings, when answering Government telephones, in e-mail messages, etc.) and display the Government issued badge in plain view above the waist at all times.
3.6 EMPLOYEE CONDUCT
Contractor’s employees must comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.7 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer*), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
4.2 PERIOD OF PERFORMANCE
The period of performance for this contract must not exceed 21 calendar days from the date of award.
4.3 PLACE OF PERFORMANCE
The primary place of performance will be a combination of the Contractor’s facilities and the United States Coast Guard at 213 Tree Fern Dr. Chesapeake, VA 23322.
4.4 HOURS OF OPERATION
Contractor employees must generally perform all work between the hours of 0730 and 1600 EST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
4.5 TRAVEL
Contractor travel must not be required for this requirement.
4.7 PROJECT PLAN
The Contractor must provide a draft Project Plan at the Post Award Conference for Government review and comment. The plan, at a minimum, must include: (a) list of work to be performed;(b) project schedule; (c) description of intended results; (d) list and role of key personnel, if applicable and (e) how quality of service (project) will be maintained throughout life of contract. The Contractor must provide a final Project Plan to the COR not later than 2 business days after the award.
4.10 PROGRESS MEETINGS
The Project Manager must meet with the COR on a daily basis to discuss progress, exchange information and resolve emergent technical problems and issues. These meetings must take place either at 213 Tree Fern Dr. Chesapeake, VA 23322, via phone or teleconference.
4.11 GENERAL REPORT REQUIREMENTS
The Contractor must provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).
5.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
6.0 CONTRACTOR FURNISHED PROPERTY
The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0 and SOW 5.0.
7.0 GOVERNMENT ACCEPTANCE PERIOD
The COR will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
7.1 The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
7.2 The COR will have 2 business days to review deliverables and make comments. The Contractor must have 2 business days to make corrections and redeliver.
7.3 All other review times and schedules for deliverables must be agreed upon by the parties based on the final approved Project Plan. The Contractor must be responsible for timely delivery to Government personnel in the agreed upon review chain, at each stage of the review. The Contractor must work with personnel reviewing the deliverables to assure that the established schedule is maintained.
8.0 DELIVERABLES
The Contractor must consider items in BOLD as having mandatory due dates. Items in italics are deliverables or events that must be reviewed and/or approved by the COR prior to proceeding to next deliverable or event in this SOW.
| ITEM |
| SOW REFERENCE |
| DELIVERABLE / EVENT |
| DUE BY |
DISTRIBUTION
| 1 |
| 4.7 |
| Contractor Project Plan |
| 2 days after the award |
COR, Contracting Officer
| 2 |
| 1.4 |
| Compliance Documents |
| 1 day before Notice to proceed |
COR, Contracting Officer
| 3 |
| 4.2 |
| Commence Physical Work |
| 1 day after Notice to Proceed |
| COR, Contracting Officer |
| 4 |
| 7.0 |
| Pre Acceptance Walk through |
| 02 days before end of period of performance |
| COR, Contracting Officer |
LAST UPDATED: 04/03/2024 PAGE 8/17