This is a Statement of Work (SOW) for installing a new epoxy terrazzo floor in the men's locker room at Building 48, Coast Guard Base Alameda, California. The project covers approximately 825 square feet and requires the contractor to provide all labor, materials, and equipment for floor installation, including removal of existing flooring, subfloor preparation, and reinstallation of obstructions. The primary objective is to deliver a low-maintenance, high-durability floor suitable for facility users.
The contractor must complete nine tasks: project management with a designated point of contact and permit acquisition; removal of furniture and interferences; installation of containment and ventilation measures; removal and disposal of existing flooring and vinyl cove base; subfloor preparation with crack filling; installation of high-performance epoxy terrazzo flooring (minimum 3/8-inch nominal thickness, seamless, non-porous, stain and mildew resistant, designed for high-traffic wet areas); reinstallation and anchoring of benches; installation of 4-inch vinyl cove base and transition strips; and daily site cleanup. All submittals, including product details with color samples and a project schedule, must be provided within 10 business days of award. Work shall be completed within 60 calendar days from the start date, performed between 7:00 AM and 5:00 PM Monday through Friday, excluding federal holidays. Contractor personnel require Real ID-compliant identification and must submit names and birthdates at least 72 hours before site access. All work must comply with federal, state, and local codes, OSHA regulations, and the U.S. Coast Guard Safety and Environmental Health Manual (COMDTINST M5100.47). The primary technical point of contact is LCDR Bethany Stafford, with CWO Joshua Alton as secondary contact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Construction Solicitation Replace Mens Locker Room Floor.pdf | ||
| BASE ACCESS LIST.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) for
Install New Floor in Men’s Locker Room at Building 48 Coast Guard Base Alameda
Coast Guard Island, Alameda, CA
1.0 Introduction/Background
This Statement of work (SOW) defines the requirements for a contractor to provide all necessary labor, materials, and equipment to install a new low maintenance/high durability floor in the men’s pool locker room that measures approximately 825 square feet. Work includes removing existing flooring, prepping subfloor, removing and reinstalling obstructions. The contractor shall be responsible for all aspects of the project as detailed in this document and in accordance with all applicable industry standards and USCG regulations.
2.0 Objective
The primary objective is to install a new low maintenance floor in the men’s pool locker room for all facility users.
3.0 Scope of Work
3.1 Tasks
The contractor shall perform the following tasks:
3.1.1 Task 1: Project Management
Designate a single point of contact for all project communications.
Coordinate all work with USCG designated POC.
Obtain all necessary federal, state, and local permits.
3.1.2 Task 2: Clear Interferences
Clear interferences/move furniture as necessary to meet the requirements of this contract. This includes benches.
3.1.3 Task 3: Install containment/ventilation measures to prevent spreading dust throughout the facility.
3.1.4 Task 4: Remove and dispose of existing flooring material and vinyl cove base.
3.1.5 Task 5: Prep Subfloor per industry standard to include filling any cracks discovered.
3.1.6 Task 6: Install Epoxy Terrazzo flooring per industry standards.
3.1.7 Task 7: Reinstall and anchor benches in original locations.
3.1.8 Task 8: Install new vinyl cove base around exterior walls and flooring transition strips as required.
3.1.9 Task 9: Site Cleanup and Restoration
Upon completion, and on a daily basis, remove all construction materials and debris, disposing of them offsite.
3.2 Submittals
The contractor shall submit the following for Coast Guard Approval before getting approval to start work. All submittals shall be provided to the Coast Guard within 10 business days of award.
3.2.1 Product details with color samples for new Epoxy Terrazzo flooring. The Coast Guard POC will select from available colors.
3.2.2 Project Schedule. The contractor shall provide their project schedule within 10 business days of award. The Coast Guard and contractor shall work together to determine when to start/finish the schedule to least impact the Coast Guard operations and other contractor work within the building.
4.0 Period of Performance
A schedule for work shall be agreed upon within 15 days of award. All work shall be complete within 60 calendar days from the start date.
5.0 Laydown and Material Storage
The Coast Guard will coordinate an appropriate amount of storage space as necessary for equipment and material storage during the project. The contractor is responsible for maintaining the security of this space and their equipment. This space shall be kept tidy at all times.
6.0 Technical Requirements
6.1 Codes and Standards
All work shall comply with the most current editions of all applicable federal, state, and local codes, all applicable industry standards, and the following USCG-specific standards:
6.1.1 U.S. Coast Guard Safety and Environmental Health Manual, COMDTINST M5100.47(series)
6.1.2 OSHA Regulations
6.2 Materials and Workmanship
All materials shall be new and conform to the specifications detailed in the table below:
New Flooring Material High Performance Epoxy Terrazzo with following specifications:
Minimum 3/8-inch nominal thickness or as recommended by product installation standards
Seamless Low Maintenance Non-porous
Stain Resistant Mold/Mildew resistant Designed for high traffic and wet areas Installed per manufacturer standards and industry standards Approximately 825 sqft installation area Provide color samples to Coast Guard POC for selection
Cove Base 4” Vinyl Cove Base- to replace existing on exterior walls
Transition Strips Sized to fit and installed as required for flooring transitions
7.0 Personnel Security and Base Access
7.1 Access Request: For access to the USCG facility, the contractor is required to submit the name and birthdate for each employee on the approved access request form at least 72 hours before their first day on site (this form will be provided after award). Personnel not listed may be denied access to the Coast Guard facility.
7.2 Identification: A Real ID-compliant driver's license or other federally approved identification is required for base access. Acceptable forms of ID include US Government Dependent ID, Federal PIV Card, TWIC Card, Veteran Health Identification Card, US Passport, or Permanent Resident Card. Driver's licenses from states that are not Real ID compliant will not be accepted.
7.3 Vehicle Requirements: All contractor vehicles must have valid registration and insurance, and all vehicle operators must have a valid driver's license. Vehicles shall always stay on marked and paved roads – vehicles are not permitted to drive or park on the grass at any point in this project performance without written approval from the Coast Guard. Any damage from driving or parking on the grass, to include the sprinkler system, shall be the responsibility of the contractor to repair.
7.4 Conduct: Contractor personnel shall adhere to all base regulations, traffic laws, and security protocols. Contractors must wear company identifying clothing/badging/safety gear, and all contractor vehicles must display company or subcontractor decals.
8.0 Work Hours
Work shall be performed between the hours of 7:00 AM and 5:00 PM, Monday through Friday, excluding Federal Holidays, unless otherwise approved in writing by the Contracting Officer or USCG POC.
9.0 Safety and Environmental Protection
All operations must comply with the USCG Safety and Environmental Health Manual, COMDTINST M5100.47 (series). The contractor is responsible for proper handling and disposal of any hazardous materials and for immediately reporting and containing any spills.
10.0 Government Furnished Services
The Government may furnish potable water and electrical power at no cost to the contractor where available. All electrical connections shall be in accordance with the National Electric Code. The contractor shall provide and use ground fault circuit interrupter (GFCI) devices when connecting to Government power sources.
11.0 Acceptance Criteria
Final acceptance of the work will be granted by the USCG POC after a final inspection confirms that all tasks in this SOW have been completed, the installation meets all technical and safety standards, and the site has been fully restored. Final payment will not be released until all deficient items have been corrected.
12.0 Coast Guard Technical Point of Contact
Primary POC for this Task is: LCDR Bethany Stafford
Secondary POC for this Task is: CWO Joshua Alton
APPENDIX A: Site Drawings
Space layouts and square footage are not guaranteed 100% accurate.
Appendix B: Existing Site Condition Pictures