Statement of Work: Removal of Cemented Canons at St. Mary’s Ohio National Guard Armory
1.1 Proposal Project Title:
a. Removal of Cement Canons at St. Mary’s Armory
1.2 Project Scope: The Scope of Service is for the removal of the two cement canons located in front of the St. Mary’s Armory at 109-113 E. South Street, St. Mary’s, Ohio. Contractor will supply all labor, tools, equipment, transportation, and supervision in order to safely remove canons. The canons must be kept intact to the cement base for relocation by National Guard personnel.
1.3 Removal of Cemented Canons: The contractor will remove the two canons and their two-concrete base’s by utilizing proper equipment to do so (concrete cutting saw, gloves, eye and ear pro). The two canons should stay secured to their concrete base’s and undamaged for relocation. The site should be cleaned of any debris caused by the removal of the canons and their concrete base’s. The removal should take the contractor a time estimate of approximately two working hours per canon for a total of four hours for removal and cleanup.
1.4 Applicable Documents
1.4.1 Canon Dimensions
1.4.2 Canon Locations in front of St. Mary’s Armory
1.4.3 Right Canon (Close-up)
1.4.4 Left Canon (Close-up)
1.5 Requirements
1.5.1 Work Scheduling: Normal base work hours for the Contractor will be between the hours of 7:00am through 5:00pm, Monday through Friday. If the Contractor would prefer a different day or time period to conduct their work, they must propose their time at least five business days prior to their expected day of work.
1.5.2 Requests for Information (RFIs): If any RFI’s exists, the Contractor must reach out to Bravo Company, 837th BEB, POC: 1LT Shannon at 513-313-5840, at least five business days prior to expected day of work.
1.5.3 837 BEB must reach out to the USPFO Warehouse, POC 1LT Thrasher 614-336-6301 at least five (5) business days prior to expected day of work to coordinate transportation of the cannons to our warehouse for storage and processing.
1.5.4 Unauthorized Personnel: The contractor shall inform all personnel within and/or around the work site prior to the execution of their work. Notifying personnel is to ensure safety and prevent any injuries to bystanders.
1.5.5 Safety Precautions:
1.5.5.1.1 OSHA Requirements: The contractor shall perform all work in the contract with due regard to the safety and health of all personnel and of the public. The Contractor shall comply with Safety and Health Regulations for Construction, administered by the Federal Occupational Safety and Health Administration (OSHA) regarding the safety and protection of persons employed in construction.
1.5.6 Method of Carrying on the Work: All work under the Contract shall be arranged and carried on to its completion once started. The work should be completed in the least possible time, while ensuring safety and risk mitigations.
1.5.7 Site Clean-up: The Contractor shall maintain the construction site in as clean and orderly condition as possible.
1.5.8 Damages, Repairs: All damages by the Contractor’s operations shall be repaired, or replaced, at the Contractor’s expense, as directed by the Contracting Authority.