This document is a Statement of Work for replacing the refrigeration equipment and refrigerant piping for a seed cooler located at the USDA's Center for Medical, Agricultural and Veterinary Entomology (CMAVE) in Gainesville, FL.
The work required includes reclaiming refrigerant, uninstalling existing condensers and evaporators, installing new condensing units on hurricane racks on the building roof, furnishing and installing a new walk-in cooler system, running new refrigerant piping, installing a new copper drain system with heat tape, and starting up and charging the new systems. The work must be performed in accordance with the provided Statement of Work.
This Statement of Work is associated with a federal contract opportunity, Solicitation Number 12405B24Q0353, for "Refrigeration Equipment and Refrigerant Piping for Seed Cooler Building 11." The solicitation is being conducted as a Request for Quotation (RFQ) under Simplified Acquisition Procedures, with a NAICS code of 238220 - Plumbing, Heating, and Air Conditioning Contractors. Quotations are due by July 30, 2024 at 3:00pm CT. The contracting agency is the USDA's Agricultural Research Service (ARS), Southeast Area.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Location: USDA, ARS, SEA, Center for Medical, Agricultural and Veterinary Entomology (CMAVE) Chemistry Research Unit Bldg. 11 1600 SW 23rd Drive Gainesville, FL 32608
Replace Refrigeration Equipment and Refrigerant Piping for Seed Cooler in Building 11 which includes the following:
· This with Trenton Equipment (Same as existing)
· Reclaim refrigerant from both systems.
· Uninstall condensers and evaporators. 5-year compressor, 1-year parts limited warranty
· Install condensing units on prefabricated, hurricane racks on the roof of the building.
· Furnish and install an appropriately sized split system walk in cooler by Bohn.
· Run refrigerant piping of soft drawn copper, with 3/4” wall insulation on suction line.
· Suspend evaporators from the ceiling of the walk-in box.
· Braze in new refrigerant piping systems to relocated equipment, pressure test to 500 psi with dry nitrogen, and dehydrate to 500 microns or less with vacuum pump.
· Furnish and install Type “L” Copper to brazed for the freezer drain system, along with new heat tape to be wired in to freezer equipment. Furnish and install 1” wall rubber pipe insulation over copper pipe and heat tape.
· Start up and charging of the system.
· Tie refrigeration systems in to controls.