Statement of Work- Patt-Cook Cable Repair (2).docx
DOCX document 19 KB Posted
- Attached to
- PATTON & COOKE SHIP TO SHORE CABLE
- Solicitation number
- N4215825QS020
About this file
This Statement of Work (SOW) details a cable repair project for the Norfolk Naval Shipyard (NNSY) involving the replacement of four Patton & Cooke C-150 15 KV male couplers. The contractor is required to provide all labor, tools, and materials to replace the shore power cable connectors, with specific testing and documentation requirements. Key responsibilities include performing comprehensive insulation resistance tests on cable phases before and after installation, verifying cable ground continuity, and ensuring precise phase positioning (Phase A: Black, Phase B: White, Phase C: Red).
The project has critical time constraints, with a maximum completion timeline of 5 days, and will be conducted in Building 298 and an adjacent Cable Storage Tent. Contractor personnel will need CIA access and must comply with OSHA and Norfolk Naval Shipyard safety requirements. The solicitation (N4215825QS020) is issued by the Department of the Navy Naval Sea Systems Command, with specific technical and certifying points of contact to be determined. The contractor must provide Objective Quality Evidence in the form of test reports demonstrating that each cable successfully meets the specified test requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Patton Cooke COMBINED SYNOPSIS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of work for Male Coupler
Performance:
On-site to provide all labor, tools, and materials to replace four (4) Patton & Cooke C -150 15 KV male couplers.
Period of Performance:
TBD
Equipment Specifications:
Four (4) each Shore Power P&C C-150 15KV male coupler connector.
Contractor Responsibilities:
The contractor shall supply all labor, tools, and materials to replace four (4) Patton & Cooke C-150 15 kV male coupler. The contractor shall provide Objective Quality Evidence (OQE) in the form of contractor test reports each cable successful met the test requirement listed.
Shipyard Responsibilities NNSY shall provide onsite location for the replace the four (4) P&C C-150 15 KV male coupler.
Lifting and Handling Requirements:
NNSY shall bear the responsibility for moving the SP cables to the work location as required by the contractor.
Testing:
1) Prior to the removal of the shore end coupler of each SP cable, the contractor shall:
1.1) Verify and record the continuity level of the connecter grounds for each cable.
1.2) Preform an insulation resistance test, on each cable, from Phase A to Phase to B; Phase B to Phase C; Phase C to Phase A; Phase A to ground; Phase B to ground; Phase C to ground. Document each value for each cable phase.
2. After the installation of the P&C C-150 15 KV male coupler replacement, the contractor shall:
2.1) All cables shall not vary more than 12 inches in total length from each other.
2.2) Verify correct phase positioning on the newly installed connector. The phase positioning order shall be Phase A (Black), Phase B (white), Phase C (red).
2.3) Perform an insulation resistance test, on each cable, from Phase A to Phase to B; Phase B to Phase C; Phase C to Phase A; Phase A to ground; Phase B to ground; Phase C to ground. Document each of the value for each cable phase. 2GΩ or greater is satisfactory.
2.4 Measure and record the level of continuity between the shore end coupler and the cable ground for each cable. A reading of ∞ is satisfactory.
Safety or Security:
Contractor will need CIA access and PPE. "Per FAR 22.102-1(a) entitled "Safety", Contractors are hereby informed that their employees or representatives present on property under Norfolk Naval Shipyard cognizance must follow Federal and State OSHA requirements and Norfolk Naval Shipyard OSHE Program Manual, NAVSHIPYDNORINST P5090.2 requirements or safety requirements for site specific location of the contract."
Critical time Constraints:
The Contractor shall start replacing the four (4) Patton & Cooke C-150 15 KV male coupler and the work shall be completed in 5 days or less from the start date.
Location:
NNSY shall provide space in Building 298 and the Cable Storage Tent adjacent to Building 298 as a work site for cable modification.
Technical POC:
TBD
Certifying POC:
TBD