About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace the front doors in Building 1 (B-1) at the USDA, ARS, National Sedimentation Laboratory in Oxford, Mississippi.

The project requirements include removing and replacing two sets of exterior and interior doors, including the associated hardware and integration with the existing Lenel Enterprise Physical Access Control System (ePACS). The work must be completed within 60 calendar days. The SOW provides details on the scope of work, project contacts, project requirements, general requirements, and the project schedule.

The related federal contract opportunity, Solicitation Number 12405B25R0002, is a Total Small Business Set-Aside with a North American Industry Classification System (NAICS) code of 236220 and a small business size standard of $45.0M. The magnitude of the project is between $25,000 and $100,000. A site visit is scheduled for November 14, 2024, and proposals are due by December 6, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Front Doors (2 sets) in Building 1 Integrating with ePACS, newest first.
File Type Posted
AMENDMENT 0001 SOLICITATION 12405B25R0002.pdf PDF
SOLICITATION 12405B25R0002.pdf PDF
Photographs Solicitation 12405B25R0002.pdf PDF
Wage Determination DBA WD MS20240041 Lafayette County MS 12405B25R0002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Replace Front Doors B-1 Asset ID 640800B001

National Sedimentation Laboratory Oxford, MS

Prepared by: J. Kevin Magee, P.E.

October 2024

STATEMENT OF WORK

Construction

1.0 PROJECT: Project Title: “Replace Front Doors B-1” at the USDA, ARS, National Sedimentation Laboratory at Oxford Mississippi

2.0 PROJECT CONTACT PERSONS:

CONTRACT SPECIALIST (CS):

Monte Jordan Email: monte.jordan@usda.gov

USDA, ARS, SEA

Acquisitions and Personal Property/Fleet 141 Experiment Station Road Stoneville, MS 38776 Phone: (662)686-5361

LOCAL POINT OF CONTACT (POC):

Roy Waits Email: roy.waits@USDA.gov

USDA, ARS NSL

598 McElroy Drive Oxford, MS 38655 Phone: 662-232-2933

ADMINISTRATIVE OFFICER (AO):

Darren Middleton Email: Darren.Middleton@USDA.gov

USDA, ARS NSL

598 McElroy Drive Oxford, MS 38655 Phone: 662-232-2908

LAB DIRECTOR:

Dr. Martin Locke Email: Martin.Locke@usda.gov

USDA, ARS NSL

598 McElroy Drive Oxford, MS 38655 Phone: 662-232-2009

ENGINEER PROJECT MANAGER (EPM)

J. Kevin Magee, PE Email: kevin.magee@usda.gov USDA, ARS, SEA Facilities EPM 141 Experiment Station Road Stoneville, MS 38776 Phone: (662) 336-0712

3.0 SCOPE OF SERVICES:

The Contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.

1. The Contractor shall provide services for the following tasks marked by an “X”:

[X] Provide a technical proposal and cost proposal to complete the project as per project requirements.

[X] Provide information for 3 reference projects with similar scopes of work along with contact information for each project.

[X]Complete the project as per project requirements.
4.0PROJECT REQUIREMENTS:

The Contractor shall furnish reference projects, a technical proposal, and a cost proposal for “Replace Front Doors B-1” at the USDA, ARS, National Sedimentation Laboratory at Oxford Mississippi. The project is located at the USDA ARS National Sedimentation Laboratory, 598 McElroy Drive, Oxford, MS 38655.

1. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.

1. Davis Bacon Wage Rates apply to all construction contracts in excess of $2,000. Employee payroll logs for the project will be required to verify wage rates are being adhered to.

4.1 BID SCHEDULE:

1. The Base Bid shall include all work described in 4.2 Description of Work.

4.2 DESCRIPTION OF WORK:

4.2.1 Background and Objective – The front door of this lab building consists of 2 sets of doors with an enclosed vestibule between them. The exterior 6’X7’ glass front doors and the inner 6’X7’ vestibule glass front doors, hinges, and operating hardware have deteriorated due to age and use and are nearly inoperable. Timely replacement is imperative. The present doors are set within a bronze anodized storefront. Both pairs of doors have a key locking system. The inner pair of vestibule doors have an additional magnetic locking system which is operated by our Lenel Enterprise Physical Access Control System (ePACS). The objective of this project is to replace both the inner and outer pairs of doors within the present storefront framing and matching the existing bronze anodized framing. The existing magnetic locking system on the inner vestibule doors as well as the request to exit detection (REX) and push-to-exit button are to be removed and replaced by an electric door strike system installed in the new interior active entrance door and integrated into the existing Lenel ePACS system.

4.2.2 Base Bid: The door replacement work shall consist of the following:

· Removal and disposal of existing doors

· Each pair of doors is approximately 6’ X 7’ (Contractor is to verify all dimensions)

· Doors are to be installed in existing storefront frames

· Finishes are to match existing bronze anodized finish

· Glazing is to be ¼” clear tempered glass

· Continuous hinges are to be used

· Outward swinging doors

· Rim Panic exit devises are to be used

· Removable mullions are to be installed

· Exterior pulls are to be installed

· Surface mounted closers are to be installed

· Each pair of doors are to be key lockable

· Interior doors must be compatible with the current enterprise physical access control system (ePACS).

· Current magnetic lock on interior door, Push-to-Exit Button, and Request-to-Exit (REX) sensor is to be replaced with an electric strike on the “active” interior door and integrated into the existing Lenel ePACS system by a qualified technician. Any unused conductors are to be properly terminated and protected. All exposed holes are to be plated to match existing finishes.

· Exterior door shall have the following lettering in a font and color to be chosen by the Location Point of Contact:

United States Department of Agriculture Agriculture Research Service National Sedimentation Laboratory Oxford, MS Open: Mon. – Fri (Except Holidays) Hours: 8:00 a.m. – 5:00 p.m.

All visitors are required to check in at main office

· Existing Aiphone intercom and ePACS card reader are to be relocated to the nearest available location on the storefront frame and the existing holes are to be plated. Both are to be tested to ensure they are functioning properly.

4.3 Government Furnished Equipment\Services

1. The Government will furnish a reasonable amount of electricity and water.

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Site Visit: Bidders are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing firsthand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions that are readily observable.

5.3 Registration: Contractor must be registered in System for Award Management, (SAM), and STATUS MUST BE ACTIVE, prior to submitting a bid. Registration can be obtained through:

https://www.sam.gov/

5.4 Existing Installations / Demolition: Contractor shall coordinate demolition of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disconnecting equipment that might jeopardize on-going research.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.

5.6 Protection of Work and Property/Safety Requirements:

1. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.

1. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required to protect pedestrian and vehicle traffic in close proximity to the work.

5.7 Temporary Facilities:

1. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

1. Should the Contractor require any power or utility shutdowns during demolition, the Contractor shall obtain approval for such shutdown from the COR three working days prior to the need.

5.8 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

5.9 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):

1. Release of liens.

1. Employee payroll\time sheets

1. Invoice

6.0 PROJECT SCHEDULE: The government will provide access to the facility during normal business hours 0800 to 1630 Monday – Friday except federal holidays. The Contract time for this project is 60 calendar days. Notice to proceed shall be issued at the mandatory preconstruction conference.

7.0 PHOTOS:

Figure 1 Outside doors

Figure 2 Outside doors from interior

Figure 3 Inside doors

Figure 4 Inside doors from interior image4.jpg image5.jpeg image6.jpeg image7.jpeg image1.png image2.png image3.jpeg