CRANE RENTAL STATEMENT OF WORK
1. REQUIRE 110 TON (MIN) CRANE WITH OPERATOR AND MANBASKET FOR 8 HOURS ONSITE + TRAVEL TIME. NEED TO BE ONSITE BY 0800 ON 20 MAY 2021. MAX LIFT WEIGHT IS 20,000LBS.
REQUIRE 33 TON (MIN) CRANE WITH OPERATOR AND MANBASKET FOR 8 HOURS ONSITE + TRAVEL TIME. NEED TO BE ONSITE BY 0800 ON 27 MAY 2021. MAX LIFT WEIGHT IS 10,000LBS.
2. NO OTHER SUPPLIES (SLINGS, SHACKLES, ETC.) REQUIRED.
3. AN OILER/RIGGER WILL NOT BE NEEDED UNLESS COMPANY REQUIRES ONE AS PART OF LEASE.
4. COAST GUARD BASE SEATTLE REQUIRES THAT CRANE COMPANY PROVIDE A LIFT PLAN FOR APRROVAL PRIOR TO WORK BEING COMPLETED.
5. USAGE OF PLATES (APPROXIMATELY 10FT x 10FT) UNDERNEATH OUTRIGGER STABILIZER PADS TO DISTRIBUTE WEIGHT; NOT TO EXCEED 600 PSF ON PIER 37.
6. ACCESS TO THE BASE MUST BE THROUGH THE ALASKAN WAY ENTRANCE TO PREVENT CROSSING OF PIER 36 APRON.