This document is a Statement of Work (SOW) for a federal contract opportunity to replace a fume hood fan at a government facility in Gainesville, Florida. The key details are:

The contractor will be required to adapt the existing fan ductwork, install roof curb adaptors to accommodate the new fan's size, install a new motor starter, and install weight-appropriate vibration eliminators. The government will provide the replacement fan. Contractors are encouraged to schedule a site visit to inspect the existing conditions before submitting a quotation. Quotations are due by August 20, 2024 at 3:00 PM CT and must include a completed SF1449, acknowledgement of any amendments, SAM registration information, and a firm-fixed price proposal detailing the required scope of work. The contract will be awarded to the responsible offeror whose quotation represents the best value to the government, considering technical acceptability, past performance, and price. This is a full and open competition under FAR Part 13 Simplified Acquisition Procedures with a NAICS code of 238220 - Plumbing, Heating, and Air Conditioning Contractors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Fume Hood Fan Replacement

We are requesting a site visit by any contractors who wishes to bid on this.

Government supplied fan will be used.

The fan is located on Building No. 1 at 1600 SW 23rd Drive; Gainesville, FL 32608.

Scope of work which includes items that need to be provided by contractor.

1.) Fan duct work will have to be adapted to replacement fan.

2.) Roof curb adaptors will have to be added to accommodate the additional width of the new fan.

3.) New motor starter needs to be installed.

4.) Install weight appropriate vibrations eliminators.

If possible, we would like the current stabilizer to be used which is already attached to our roof.