This statement of work outlines a project for Flexera software installation and training services. The Federal Energy Regulatory Commission seeks to purchase Flexera Technopedia asset normalization software to integrate with its existing ServiceNow configuration management database. The project objectives include installing Flexera Data Platform on 4,605 devices and 1,292 servers, and configuring standard inventory extractors. Key deliverables and due dates are identified for draft and final project plans, infrastructure sizing documents, system design documents, and non-production and production deployments. The contractor will provide a one-day virtual training session for up to 15 individuals. The period of performance is from September 30, 2021 to September 29, 2022.
The related federal contract opportunity is a solicitation from the Department of Energy's Federal Energy Regulatory Commission to purchase Flexera Software licenses and training services as defined in the attached statement of work. The solicitation seeks bids for 4,605 Data Platform Enterprise Per Device Silver Subscriptions and 1,292 Data Platform Enterprise Server Silver Subscriptions from Flexera.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PAST PERFORMANCE.docx | DOCX document | |
| 89603021Q0071 0001.docx | DOCX document | |
| Brand Name Justification Flexera.pdf | ||
| 89603021Q0071.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Background
FERC would like to purchase Flexera Technopedia asset normalization product to bolt onto our existing Service Now Configuration Management Database to further automate the asset discovery conducted by Service Now to reduce custom configurations, reduce manual processes for tracking obsolescence and reduce manual entry of configuration management information into the FERC Enterprise Management System (FEAMS).
Scope The IT Policy & Resources Management Division requires a vendor for Flexera professional services for the installation, configuration and training for Flexera products within FERC’s environment.
Objectives
Installation support for Flexera Data Platform:
· 4605 Devices
· 1292 Servers
· Configuration of standard extractors
The Project will start with a Project Kickoff meeting followed by a Planning and Design meeting. The project kickoff reviews the scope and execution plan for the project. The planning and design meeting establishes the detailed understanding of FERC’s environment and how Data Platform fits within the environment. It also establishes the core use for Data Platform within FERC’s environment.
Tasks & Deliverables Deliverable Title
Due Date
| Deliverable Title |
| Format |
| Due Date |
Draft Project Plan and Schedule
5 business days after the Project Kickoff Meeting
Planning and Design (P&D) Meeting Summary
Within 10 business days of Project Kickoff
Infrastructure Sizing Document
Within 5 business days of the Planning and Design meeting
System Design Document
Within 10 business days of the Planning and Design meeting
System Build Document
Within 20 business days of the Planning and Design meeting
Final Project Plan and Schedule
Within 20 business days of the Planning and Design meeting
Non-Production Deployment
Once FERC has established the required infrastructure the contractor shall install Data Platform in the non-production environment and configure standard inventory extractors.
Deliverable Title Due Date
| Deliverable Title |
| Format |
| Due Date |
Non-Production install of Data Platform
Per the project schedule
Standard extractor configuration
Per the project schedule
Production Deployment & Training The contractor shall install Data Platform in the production environment and configure the standard and non-standard inventory extractors. Additionally, the contractor shall provide a one-day virtual training session for up to 15 individuals on the use and sustainment of the Data Platform.
Deliverable Title Due Date
| Deliverable Title |
| Format |
| Due Date |
Production install of Data Platform
Per the project schedule
Standard extractor configuration
Per the project schedule
Deliverable Title Due Date Distribution/Copies
| Deliverable Title |
| Format |
| Due Date |
| Distribution/Copies |
Training Plan
| Per the project schedule |
| Standard Distribution |
Training Materials leave behind
| Per the project schedule |
| Standard Distribution |
Live Training
| Per the project schedule |
| Identified attendees |
Government-furnished property
Must be accessible via laptop or desktop computers.
Security Requirement
None Place of performance
Provider will perform its duties at its own site. Depending on state of pandemic, training may be held remotely.
Period of performance
September 30, 2021 – September 29, 2022
File details come from the government source that posted it. Updated .