Statement of Work - Exterior Window Cleaning Services.pdf
PDF 108 KB Posted
- Solicitation number
- FA442726Q1144
About this file
Statement of Work Summary: Exterior Window Cleaning Services
This Statement of Work (SOW) specifies professional exterior window cleaning services for the Westwind Inn (Building 402) at Travis Air Force Base, California. The contractor shall clean approximately 930 exterior window panes using a water-fed brush and deionized water system to achieve a clean, streak-free finish free of dirt, grime, and hard water stains. The scope encompasses all necessary labor, supervision, materials, tools, and equipment, with the contractor responsible for providing hoses, connectors, and extension cords while the Government furnishes water supply and electricity access. Additional requirements include site protection of the building exterior and surrounding landscape, daily clean-up and debris removal, and compliance with base security procedures including obtaining necessary passes for personnel and vehicles.
The work must be completed within three consecutive working days during normal duty hours (0800-1700, Monday-Friday), excluding federal holidays, unless otherwise coordinated with the facility manager. Performance will occur at Westwind Inn, Building 402, 570 Travis Avenue, Travis AFB, CA 94535. Final acceptance will be conducted by the Lodging Manager or designated representative through joint inspection, with work considered complete when all windows meet the acceptance criteria of being clean, streak-free, and free of hard water stains and residue. No pricing information, response dates, award dates, or contract vehicle type is specified in this SOW document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| TAFB Security Requirements.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
For Exterior Window Cleaning Services Westwind Inn Lodging, Travis AFB
1.0 BACKGROUND
The Westwind Inn (BLDG 402) at Travis AFB, CA requires professional exterior window cleaning services to maintain facility cleanliness and appearance. This service is essential for ensuring a high standard of quality for lodging guests and personnel.
2.0 SCOPE OF WORK
The contractor shall provide all necessary labor, supervision, materials, tools, and equipment required to perform comprehensive exterior window cleaning for approximately 930 window panes at the Westwind Inn, BLDG 402. The service includes the removal of dirt, grime, and hard water stains to ensure a clean and streak-free finish.
3.0 SPECIFIC TASKS
The contractor shall:
• 3.1 Window Cleaning: Clean the exterior surface of all 930 window panes. The cleaning method shall include, at a minimum, the use of a water-fed brush and deionized water system to prevent spotting.
• 3.2 Stain Removal: Treat and remove hard water stains from all affected windows to the greatest extent possible.
• 3.3 Site Protection: Take all necessary precautions to protect the BLDG exterior, surrounding landscape, and walkways from damage during cleaning operations.
• 3.4 Clean-Up: Upon completion of the work each day, the contractor shall clean the entire work area, removing any debris, equipment, and materials. The area shall be left in a clean and orderly condition.
4.0 PERIOD OF PERFORMANCE
The work shall be completed within three (3) consecutive working days from the start date. The work is to be performed during normal duty hours (0800-1700, Monday-Friday), excluding federal holidays, unless otherwise coordinated and approved by the facility manager.
5.0 PLACE OF PERFORMANCE
Westwind Inn, BLDG 402 570 Travis Ave Travis AFB, CA 94535
6.0 GOVERNMENT-FURNISHED ITEMS & SERVICES
The Government will provide access to an external water supply and electricity as needed. The contractor is responsible for providing all necessary hoses, connectors, and extension cords.
7.0 SECURITY REQUIREMENTS
The contractor and all contractor personnel shall comply with all installation security procedures, including obtaining necessary base passes for personnel and vehicles.
8.0 ACCEPTANCE CRITERIA
Final acceptance of the work will be performed by the Lodging Manager or a designated representative upon completion. The work will be considered complete when all tasks in Section
3.0 have been performed to a satisfactory level, with all windows being clean, streak-free, and free of hard water stains and residue. A final joint inspection will be conducted to verify completion.
File details come from the government source that posted it. Updated .