This Statement of Work (SOW) details a concrete foundation project for the US Customs and Border Protection (CBP) US Border Patrol El Centro Sector Headquarters. The project requires constructing a 50' x 70' x 5" concrete slab with specific technical specifications, including 5000 psi concrete using ¾" rock mix, 6-6/10-10 wire mesh, a 1% slope, and thicker edges. Site preparation involves installing a plastic water barrier, adding 3" Class II base, grading, and installing two 1 1/2" PVC conduit pipes under the slab.
The contract requires delivery within 30 days After Receipt of Award (ARO) to the El Centro Sector headquarters at 293 West Aten Road, Imperial, CA 92251. The contractor must provide an operations manual and equipment specification in both paper and electronic formats. The project is considered unclassified but Law Enforcement Sensitive, and must comply with the Department of Homeland Security's Green Procurement Program by using environmentally preferable products and services. No government-furnished equipment is anticipated, and no travel is required to support the tasks outlined in the SOW.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA Doc.pdf | ||
| Service Contract Act WD 2015-5607.pdf | ||
| ATTTACHMENT(B)_20250620160510.310_X.pdf | ||
| ATTACHMENT(A)_20250620160512.135_X.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW USBP El Centro Sector MROD – Shoot House Foundation Page 1 of 3
Statement of Work For
US Customs and Border Protection US Border Patrol – El Centro Sector Headquarters
Concrete Foundation for ELC HQ Shoot House
1. BACKGROUND:
This document will serve to inform you that the El Centro Sector Training Branch is requesting to have a concrete foundation and groundwork formed for a shoot house for the El Centro Sector Mission Readiness Operations Directorate. Currently, the property and ground space available is not prepared to accommodate the shoot house.
2. SCOPE:
It is the intent of CBP to procure commercially available equipment and services detailed in Section
5.1 to support the US Border Patrol, El Centro Sector Headquarters. All equipment and services must meet or exceed the minimum specifications as outlined in Section 5 for this requirement.
3. APPLICABLE DOCUMENTS AND STANDARDS:
1. US Customs and Border Protection Authorized Equipment List (AEL) - Rev 02/2021.
2. Commercial standards shall be used wherever practicable.
4. SPECIFIC TASKS:
The contractor shall complete the following tasks as required to comply with this SOW.
4.1 Program Management.
The contractor shall exercise technical direction and control of the engineering, manufacturing, and test effort required to produce the equipment. This requirement includes the necessary management support tasks related to production, configuration control, risk management, testing, quality assurance, and data management required to carry out that task and comply with this SOW.
4.2 Testing.
The contractor shall test and certify the functionality of all equipment prior to delivery.
4.3 Delivery.
The contractor shall deliver the equipment outlined in Section 5.1.
4.4 Documentation.
The contractor shall be responsible for issuing existing documents as requested by CBP. (See section 5.3)
5. DELIVERABLES AND DELIVERY SCHEDULE:
5.1 Equipment and Services.
SOW USBP El Centro Sector MROD – Shoot House Foundation Page 2 of 3
The contractor shall deliver equipment and provide services as outlined in the table below. The equipment shall be drop shipped to the address provided.
Item Part / Model Number Description Qty 1 Concrete Slab with Aggregate
Apron
• Condition: new
• Site preparation:
o Installation of plastic water barrier o Add 3” Class II base to existing elevation
100’ x 100’ area to create a 80’ x 80’ pad o Grading o Install two 1 1/2” PVC conduit pipes under slab o One conduit under north/south 80’ o One conduit under east/west 50’
• Slab requirements:
o 50’ x 70’ x 5” o 5000 psi concrete using ¾” rock mix o Form, pour, finish o 6-6/10-10 wire mesh throughout o 1% slope o Thicker edges
• Finish Grade:
o Build apron around finished slab using
Class II base o 15’ wide surrounding slab
5.2 Shipping Address.
US Customs and Border Protection US Border Patrol Headquarters – El Centro Sector 293 West Aten Road Imperial CA 92251 Attn: SOS Andrew McConahay
5.3 Data.
As referenced in section 4.3 above the contractor shall provide copies of the documents listed below.
One copy of the data shall be delivered in paper form and one copy in electronic form. The electronic form shall be in MS Word format or Adobe Acrobat. The documents are deliverables under the contract and shall be delivered to the COTR no later than thirty days after contract award:
a. Operations Manual
b. Equipment Specification
6. GOVERNMENT-FURNISHED EQUIPMENT AND INFORMATION:
SOW USBP El Centro Sector MROD – Shoot House Foundation Page 3 of 3
The Government does not anticipate providing any GFE or GFI.
7. PLACE OF PERFORMANCE:
Equipment shall be delivered from the contractor’s facility.
8. PERIOD OF PERFORMANCE:
Delivery of all items within 30 days After Receipt of Award (ARO).
9. SECURITY:
There are no specific security classification level requirements associated with this procurement action. Information is deemed unclassified but Law Enforcement Sensitive.
10. SPECIAL CONSIDERATIONS:
10.1 Changes to the SOW
No changes to this SOW or cost increases shall be incurred without written prior approval of the Contracting Officer. Any changes or cost increases will not take effect until the Contracting Officer executes a written modification.
10.2 Green Policy
In order to comply with federally mandated environmental preference programs and Department of Homeland Security (DHS) “Green Procurement Program” (GPP) policy, ELC requires the use of environmentally preferable products and services. These program elements include: recovered material products, energy and water efficient products, alternative fuels and fuel efficiency, bio-based products, non-ozone depleting substances, priority chemicals, and environmentally preferable products. These program elements are described on the Office of the Federal Environment Executive website (http://www.ofee.gov).
10.3 Travel
Travel is not required to support the tasks identified in this SOW.
11. POINTS OF CONTACT:
To be anounced http://www.ofee.gov/
| The contractor shall deliver equipment and provide services as outlined in the table below. The equipment shall be drop shipped to the address provided. |
| a. Operations Manual |