Statement of Work.pdf

PDF 1 MB Posted

Attached to
Interlock System and Installation Federal contract opportunity
Solicitation number
FA441721QC158
Issued by
Department of the Air Force Special Operations Command

View the file

Other files for this federal contract opportunity

Other files attached to Interlock System and Installation, newest first.
File Type Posted
RFQ - Interlock Extended.pdf PDF
52.204-24 and 26.pdf PDF
RFQ FA441721QC158 - Interlock.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work 1 SOMXG X‐ray Interlock Installation Service

1. REQUIREMENT:

The contractor shall provide all management, tools, specialized equipment, supplies, and labor necessary to perform the installation of an electronic interlock system in the NDI vault, Rm. 123.

The NDI Lab requires that the old interlock system be disconnected and removed and the newer TSG interlock be installed in the x‐ray vault. The interlock is required to be installed for shielded radiography IAW 33B‐1‐1 to prevent accidental x‐ray exposure. The newer TSG interlock is required per Message AFNDIO 04‐2007. It is hardwired and connected to the entrance door, sliding door, and alarm beacons inside and outside the building.

2. BACKGROUND:

The existing system installed in the x‐ray vault is severely outdated and no longer in compliance with current AF instructions. The selected contractor is the supplier of the new parts and is the most economical means of completing the installation of the new, AF approved system. Air Force Civil Engineering was contacted and reported that they do not have the capability to complete the installation, necessitating that a contractor be used.

3. PERIOD OF PERFORMANCE:

Period of Performance for install is requested to be August 1, 2021 to August 31, 2021 (Estimated).

4. PLACE OF PERFORMANCE:

The location for performance of this contract is:

Hurlburt Field, FL 32544

Normal business hours are defined as 24 hour operations, Monday through Friday with the exception of weekends and federal holidays.

5. PERFORMANCE REQUIREMENTS:

Contractor shall remove the existing interlock system and dispose of all debris. Following removal of existing system, contractor will install new system per AFNDIO Msg 004‐2007.

Following installation of the new system, contractor will troubleshoot system for errors, and then validate the systems functionality to ensure compliance with the aforementioned AFNDIO requirements. Special care will be taken to ensure that the system will allow for safe operations of industrial radiation equipment.