This is a Statement of Work (SOW) for the purchase and installation of a Luminex 200 System for Salmonella serotyping at the USDA-APHIS-VS-NVSL facility in Ames, Iowa.

The contractor must deliver the Luminex 200 System with xPONENT, RUO within 30 days of contract award on a FOB Destination basis. The system is the only instrument compatible with the xMAP Salmonella serotyping assay, which utilizes microsphere-based PCR technology, and Luminex holds sole proprietorship of this technology. The delivered system must include specified components and software (LX200, XYP, xPonent Software, Sheath Delivery System, flow-based bead reader, x-y plate platform, heater block, automated maintenance plate, xMap sheath fluid 20L, and Dell Optiplex PC with monitor) and meet detailed technical specifications including multiplexing capacity of up to 100 analytes per sample, dynamic range of >3.5 logs, sensitivity of ≤45 minutes for a 96-well plate, sample volume of 25-80 μL, support for protein and nucleic acid multiplex assays, and specified physical dimensions and power requirements. The contractor must also provide Luminex 200 Calibration and Verification Kits, conduct on-site installation, and verify system functionality. Contractor personnel must be trained and certified to install the system and capable of meeting facility security requirements including U.S. citizenship and criminal background investigation. Installation technicians must be accompanied by a federal employee escort at all times and cannot have independent facility access. Travel costs will not be reimbursed.

View the file

Other files

File Type Posted
JA for Under SAT Final_Redacted.pdf PDF
12639526Q0225.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

Project Luminex 200 System

General Information

1.0 Scope of Work

To purchase the Luminex 200 System with xPONENT, RUO for the purpose of Salmonella serotyping.

2.0 Background

To purchase the Luminex 200 System which is the only instrument that can be used with the xMAP Salmonella serotyping assay, which utilizes microsphere-based PCR for the purpose of Salmonella serotyping. Luminex is the sole proprietor of this technology.

Contractor Requirements

3.0 Technical Requirements / Tasks

Contractor will deliver Luminex 200 System within 30 days of award, conduct on-site installation and verification of system functionality. The Luminex 200 System must meet the following technical requirements:

Luminex 200 system with xPonent LX200, XYP and xPonent Software Sheath Delivery System Flow-based bead reader x-y plate platform Heater block Automated maintenance plate xMap sheath fluid 20L Dell Optiplex PC, monitor with stand Multiplexing capacity: up to 100 analytes per sample Dynamic range: >3.5 logs Sensitivity: </= 45 minutes for a 96 well plate; up to 12,800 results/hour Sample volume: 25-80 μL depending on assay Supported Assay Type: Protein and nucleic acid multiplex assays Dimensions: 17x20x9.5 inches Weight: 60 lbs Power 100-200 V Luminex 200 Calibration Kit Luminex 200 Verification Kit

5.0 Deliverables / Schedule

Delivery must be made (FOB Destination) within 30 days within contract award.

Delivery and Installation Location:

USDA-APHIS-VS-NVSL

1920 Dayton Ave.

Ames, IA 50010

6.0 Travel

Travel costs will not be reimbursed to the contractor.

7.0 Contractor’s Key Personnel

Personnel must be trained and certified to install the system.

8.0 Security Requirements

The visiting personnel must be capable of meeting facility entry security requirements which may include (but not be limited to) U.S. citizenship, criminal background investigation, and submission of access paperwork in a timely fashion.

Independent access to the facility will not be permitted – the technician/contractor must be accompanied by a federal employee (escort) at all times.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements

File details come from the government source that posted it. Updated .