Statement of Work Summary: LECO CS 744 Combustion Carbon Sulfur Analyzer Service Contract

This is a Statement of Work (SOW) for a service and maintenance contract for a LECO CS 744 combustion carbon sulfur analyzer required by the Material and Structural Systems Division (Division 731) at NIST's Engineering Laboratory. The analyzer is used to measure carbon and sulfur composition in cementitious materials, hydraulic cement, fly ash, slag, and related construction materials through qualitative and quantitative analyses.

The contractor shall provide preventative and corrective maintenance, phone and remote desktop support, and onsite services during normal business hours (Monday through Friday, 8:30 a.m. to 5:00 p.m. ET) using original equipment manufacturer (OEM) authorized service engineers and repair parts. Specific deliverables include one preventative maintenance visit annually with parts kit included, one service/repair visit per year with replacement parts not included, unlimited remote diagnostic tool access, and software updates. All travel, labor, and supplies for preventative maintenance visits are the contractor's responsibility. Other Direct Costs (ODCs) for replacement parts beyond those specified are not authorized; any additional parts required during emergency visits must be procured separately. The base performance period runs from June 30, 2026, through June 29, 2027, with the primary place of performance at NIST Gaithersburg, Maryland (100 Bureau Drive, Gaithersburg, MD 20899). The contractor must submit detailed service tickets after each visit documenting arrival/departure times, work performed, parts repaired or replaced, diagnostic results, and signatures from both service personnel and the NIST Contracting Officer's Representative (COR). Payment is made at 100 percent upon COR receipt and acceptance of fully delivered service and parts under Net 30-day payment terms. The Government reserves the right to perform performance tests and reject any defective or nonconforming work, with the contractor responsible for correcting deficiencies at no additional cost.

View the file

Other files

File Type Posted
Sole Source Notice of Intent .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

TITLE:

Service Contract for LECO CS 744 Combustion Carbon Sulfur Analyzer

REQUESTING LAB:

Material and Structural Systems Division - 731(Engineering Laboratory)

Background

The Materials and Structural Systems Division is involved in the analysis, standards and codes involving a wide range of construction materials, including cement clinker, cement, fly ash, blast furnace slag, aggregate, and composites and is seeking a service and maintenance contract for a combustion carbon sulfur analyzer used to measure the carbon and sulfur composition of cementitious minerals, hydraulic cement, fly ash, slag, clays and other materials by qualitative and quantitative analyses.

Objective(s)

The Contractor shall provide a service agreement for the service and maintenance for a LECO CS 744 combustion carbon sulfur analyzer and associated components to ensure uninterrupted performance within manufacturers’ specifications on a scheduled and as-needed basis.

Scope/General Requirements

The Contractor shall provide preventative maintenance, corrective maintenance, phone and remote desktop support for hardware, software, and applications with onsite services being available during normal business hours. The Contractor shall provide these services using original equipment manufacturer (OEM) authorized service engineers and repair parts.

The Contractor shall provide:

• Preventative and corrective maintenance, using OEM authorized service engineers and repair parts for:

o LECO CS 744 combustion carbon sulfur analyzer, SN 59956 induction furnace capable of achieving 1700 C or greater programmable automatic furnace cleaner with vacuum- assisted dust removal non-dispersive infrared absorption detection method integrated carrier gas scrubbers and heated flow controllers automated combustion tube exchange for combustion maintenance that is backed up by a manual exchange system autoloader with a capacity of 50 samples instrument software

• One preventative maintenance visit a year with parts kit included and one service/repair visit per year with replacement parts not included:

o The Contractor shall coordinate with the NIST COR to schedule each respective service visit. Each visit shall be performed within NIST’s normal operation hours (Monday through Friday; 8:30 a.m. ET through 5:00 p.m. ET).

o All travel, labor, and supplies necessary for performance of the aforementioned preventative maintenance visits shall be the responsibility of the Contractor.

o Other Direct Costs (ODCs) for replacement parts are not authorized for this requirement. In the event during an emergency service visit, the Contractor identifies that a replacement part other than those specified in the listing above is required, and such a replacement part has an individual cost associated with it, such a replacement part is not authorized by this requirement and would have to be procured outside of this requirement.

• Unlimited use of remote diagnostic tool

• Software updates

The Contractor shall submit a service ticket prior to departure from NIST on any given service call for maintenance or repairs. The service ticket shall include the following, at a minimum:

1) Date and time of arrival to NIST

2) Description of service performed;

3) Name and quantity of any parts that were repaired;

4) Name and quantity of any parts that were replaced;

5) Date and time of departure from NIST;

6) Diagnostic test results or narrative summary demonstrating the equipment is meeting the manufacturer’s specifications;

7) Any comments or recommendations;

8) Signature of Contractor’s service personnel;

9) Signature from NIST COR accepting the service rendered.

Deliverable Schedule

Deliverable Delivery Due Date Recipient

Base Period Service and maintenance for a LECO CS744 combustion carbon sulfur analyzer and associated components

06/30/2026 COR Review

Period of Performance:

Base Period: 06/30/2026 – 06/29/2027

Place of Performance:

The primary place of performance shall be the NIST Gaithersburg, MD site located at 100 Bureau Drive; Gaithersburg, MD 20899. More specifically, the scheduled maintenance visits shall take place at the NIST Gaithersburg, MD site.

Inspection and Acceptance

In addition to the inspection and acceptance terms articulated in 52.212-4, the Government reserves the right to perform such performance tests and evaluation as defined below to verify specified system performance. Such test and evaluations, if performed, shall be conducted within the environment that the system is to be operated. The contractor has the right to be present during the tests and evaluations, if performed, at the contractor’s expense.

Performance Test:

Government will test equipment prior to contractor’s departure from NIST Campus.

NIST may choose at its discretion to forego this part of acceptance testing.

The Government, through the Contracting Officer's Representative (COR), will inspect the repair services performed to verify that all work has been completed in accordance with the requirements of the contract and accepted industry standards.

The Government reserves the right to reject any repair services or replacement parts that are determined to be defective, incomplete, nonconforming, or otherwise fail to meet the requirements of the contract. The Contractor shall, at no additional cost to the Government, correct any deficiencies identified by the Government within a reasonable timeframe mutually agreed upon by the parties.

Acceptance of repair services shall occur upon successful completion of the required work and verification by the Government that the equipment is functioning in accordance with the manufacturer's specifications and the requirements of this contract. Acceptance by the Government shall not relieve the Contractor of responsibility for latent defects, fraud, gross mistakes amounting to fraud, or the Contractor's warranty obligations, if applicable.

The Government may perform operational testing, inspection, or other quality assurance measures to verify that the repaired equipment meets the manufacturer's performance specifications and is operating as intended. Any deficiencies identified during testing that are attributable to the Contractor's workmanship, materials, or replacement parts shall be corrected by the Contractor at no additional cost to the Government.

Any replacement parts furnished under this contract shall be new or manufacturer-authorized equivalent parts, unless otherwise approved by the Government, and shall be free from defects in material and workmanship.

GENERAL INFORMATION

This work does not involve confidential or proprietary data.

Safety:

The Contractor employee shall be responsible for knowing and complying with all installation safety prevention regulations. Such regulations include, but are not limited to, general safety, fire prevention, and waste disposal.

Security:

The Contractor will be allowed on site as visitor pass and NIST staff will escort the Contractor to the chambers on days of scheduled maintenance and repairs. NIST staff will check on the Contractor on a regular basis.

Regular Business Hours:

Regular business hours are Monday through Friday, 8:00 am to 5:00 pm Eastern Time.

Identification Badges:

Contractor employees shall comply with NIST identification and access requirements. Each Contractor employee shall wear a visible identification badge provided by the NIST Security Office.

Vehicle Registration:

All Contractor employees must register their vehicles with the NIST Security Office to gain access to the campus. A valid driver’s license, Government-furnished civilian ID, proof of insurance and current registration must be presented to the NIST Security Office, at which time a NIST vehicle pass will be issued. The pass shall be displayed on the vehicle in accordance with NIST Security Office instructions.

PAYMENT SCHEDULE

The Contractor shall be paid, in accordance with Net 30-day payment terms, upon receipt and acceptance of a proper invoice, in accordance with the following schedule:

1. 100% after receipt and acceptance by the COR of fully delivered service and parts.

2. The Government anticipates inspection will occur upon:

a. After testing the integrity of the service work, as soon as possible.

Title:
Requesting Lab:
GENERAL INFORMATION
Safety:
Security:
Regular Business Hours:
Identification Badges:
Vehicle Registration:

Payment Schedule

File details come from the government source that posted it. Updated .