This is a Statement of Work for Code 139 Certification and Training Test Props to be performed for Norfolk Naval Shipyard (NNSY). The contractor shall micro-drill holes in five provided c-canopy weld test blanks according to specifications detailed on NNSY-provided drawings. Hole specifications include 1/64 inch holes drilled to 0.003 inches in diameter by 0.009 inches deep, and 1/32 inch holes drilled to 0.0045 inches in diameter by 0.009 inches deep. The contractor must drill holes in exact locations as shown on the drawings, with quantity and location varying per test prop. The contractor is also responsible for creating AutoCAD or similar answer keys (both filled and blank) corresponding to each individual test prop.
Work will be performed at the contractor's facilities with delivery to Norfolk Naval Shipyard, Building 276 Beatty Street, Portsmouth, VA 23709. The estimated period of performance is 6/30/2026 through 12/31/2026 (4-6 weeks from contract award). Government-furnished property includes the blank c-canopy weld props. No security requirements apply. Certification testing must comply with NAVSEA 250-1500-1 Welding Standard and NSTR-99 Qualification Examination Requirements for Nondestructive Test Personnel. Contact information will be provided upon contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sole Source Memo-eSign Rev 1KO_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Code 139 Certification and Training Test Props
Section A: Scope
1. Objective:
Code 138.3 Test Examiners and code 139 training section need of updated training and certification test props to certify Code 139 nuclear non-destructive test inspectors.
2. Background/Introduction
Currently Code 138.3 utilizes bevel canopy type weld test props in the certification process of Code 139 nuclear inspectors. Bevel type canopies are rarely seen in production work. Code 139 typically encounters c-canopy type welds. Code 138.3 is trying to realign inspector certification testing with the inspectors’ actual deck plate work experiences. This requires changing out of bevel type weld canopies to c-canopy type welds.
3. Limitations of Work
N/A
Section B: Applicable Documents
4. Documentation:
Certification testing is required by NAVSEA 250-1500-1 Welding Standard and NSTR-99 Qualification Examination Requirements for Nondestructive Test Personnel.
Section C: Requirements
5. Scope of Work:
NNSY requires certification and training test props to support Code 139 nuclear production work. This will require the vendor to micro-drill holes in FIVE provided c-canopy test blanks. The holes shall be drilled in the corresponding locations shown on the drawings provided by NNSY for each canopy and they shall be drilled in the exact locations as shown on the drawings. The quantity and location of the holes will vary per test prop. The sizes of the holes will either be 1/64 inch or 1/32 inch as documented on the drawings. The 1/64 in hole shall be drilled to 0.003 inches in diameter by 0.009 inches deep.
The 1/32 inch hole shall be drilled to 0.0045 inches in diameter by 0.009 inches deep, as noted on the drawing.
6. Contractor Responsibilities: The Contractor shall drill the test props with micro-drilled holes based on the instructions provided in the drawings and create an AutoCAD or similar answer key and blank answer key that corresponds to the individual test props.
7. NNSY Responsibilities: NNSY will provide blank / not drilled test props and location, quantity, and size of holes to be drilled.
8. Government Furnished Property: Blank c-canopy weld props will be provided to the vendor.
9. Security Requirements: None.
10. Delivery Terms/Shipping/Transportation: Once complete, vendor will ship to Norfolk Naval
Shipyard, Bldg. 276 Beatty St. Portsmouth, VA 23709
11. Place of Performance/Delivery Location: The work will be performed at the contractor’s facilities.
12. Period of Performance (PoP)/ Completion Date/ Delivery Date: W Estimate: 6/30/2026 start, 12/31/2026 end (date of award plus 4 -6 weeks).