Statement of Work.pdf
PDF 79 KB Posted
- Solicitation number
- W911SD26QA056
About this file
This is a Statement of Work (SOW) for the installation and setup of one Instron 1500HDX Universal Testing Machine at the West Point Cyber Engineering and Academic Center, Room 102. The equipment must be delivered and fully operational by August 31, 2026, with all work completed between July 1 and August 31, 2026. The contractor is responsible for rigging services including offloading, positioning, hose connections, electrical wiring, debris disposal, and potential installation of conduit or openings between the pump room (EC-102B) and High Bay (EC-102). The contractor must provide a transformer if power requirements exceed 460V three-phase for the pump or 120V single-phase for other components.
The Universal Testing Machine must have a load capacity of 337,500 lbf, 12-inch actuator stroke, maximum test speed of 4.5 inches per minute, and a 30-inch horizontal clear opening. Space constraints require the equipment to fit through a 7.5-foot by 11-foot door opening, with the hydraulic power unit confined to a 12-foot by 7.5-foot room and all other components fitting in a 20-foot by 7-foot space. The system includes hydraulic crosshead grips, fastener fixtures, 8-inch gage length extensometers, interlock safety enclosures, a Windows 10 Pro computer with 21.5-inch touchscreen monitor, and flexible test software capable of custom procedures and PDF/CSV data export. The contractor must provide on-site installation, calibration, commissioning, one day of operator training, operation and maintenance manuals, and a one-year warranty. All debris must be removed by the contractor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BRAND NAME JA_Redacted.pdf | ||
| Performance Work Statement.pdf | ||
| WAGE DETERMINATION.pdf | ||
| Solicitation Instructions.pdf | ||
| Solicitation - W911SD26QA056.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW / SPECIFICATIONS/REQUIREMENTS INSTALLATION AND SETUP REQUIREMENTS
1. Universal Testing Machine, CEAC Room 102, Quantity (1)
2. Scope
a. The brand name Instron 1500HDX Universal Testing Machine(UTM) is a hydraulic experimental testing machine comprised of multiple components including but not limited to a hydraulic pump, actuators, digital controller, and testing fixtures.
b. All equipment should be delivered to the West Point Cyber Engineering and Academic Center after completion in coordination with the customer.
c. The contractor will provide the rigging services to include manpower, transformer if required, offloading, setting in place, hose connection, electrical wiring, and debris disposal. The contractor may be responsible for installing conduit or creating openings for hoses and wires from the pump room (EC-102B) to the High Bay (EC-102).
d. The entire system including all components, materials, attachments, hoses, fixtures, wires, and software will be purchased by the customer and installed by the manufacturer or verified contractor.
e. Upon receiving final specifications from the contractor, the customer will provide required facility resources (power, water, drainage, compressed air, etc.)
f. Contractor must provide transformer if power requirements exceed 460V 3 phase for the pump or 120V 1 phase for each of the other components.
g. Customer is required to validate all facility requirements to include but not restricted to power, hydraulics, sensor outputs, connectivity, and safety.
h. A one-day on-site operator training will be conducted after installation and validation of all equipment.
i. (on a case-by-case basis – fully meet requirements of customer provided commissioning plan that may include installation, operational training, customer testing, functional performance testing/validation and reach-back customer support during initial break-in period)
3. System Description
a. The Universal Testing Machine will include a minimum of one hydraulic actuators with a maximum capacity of 337.5 kip and a 12 inch stroke, Hydraulic grip actuation, 8 inch gage length rebar extensometer, controller with the specifications outlined below, a computer and monitor with appropriate compatible software for the controller as specified below, and all hoses, cables, cords, and connectors to provide a full-operational hydraulic testing system.
b. Specifications
i. Maximum work envelope: There is a very limited space to transport, setup and operate the hydraulic testing system. The following are the minimum spaced.
1. Must fit through a door opening of 7.5 ft by 11 ft
2. Must be able to fit all components for the Hydraulic power unit (pump) in a room that is 12 ft by 7.5 ft.
3. All other components for the hydraulic testing system must fit in a space 20 ft by 7 ft.
ii. Universal Testing Machine: The universal testing machine will be a high-capacity tension, compression, bend/flex, and shear testing machine. It will have a dual tests space and long test strong
SOW / SPECIFICATIONS/REQUIREMENTS INSTALLATION AND SETUP REQUIREMENTS
1. Load capacity: 337,500 lbf
2. Maximum test speed: 4.5 inches/minute
3. Actuator stroke: 12 inches
4. Horizontal Clear Opening of 30 inches
5. Hydraulic Power Supply Voltage maximums
a. Maximum voltage of 480V, 3 Phase
b. Maximum ampere of 7.6 A
c. Maximum power of 5 HP
6. Accessories:
a. Hydraulic Crosshead grips
b. Fastener fixtures
c. Extensometers with 8 inch gage length, deflectometers
d. Interlocked safety enclosures
7. Accuracy:
a. Digital quadrature transducer with actuator position resolution of 0.00005 in
b. Position accuracy is equal to or less than +/- 0.005 in or +/- 0.5% of displayed reading (whichever is greater)
iii. Operator Dashboard Controller
1. Windows 10 Pro computer or higher.
2. 21.5-inch flat All-in-one touch screen monitor
3. All System Cables
4. Software to create, edit, and run tests with the utmost flexibility. The software allows for the modification of calculations. Software allows for data acquisition. Software allows for custom test procedures with sine, square, triangle, ramp, hold, profile, and custom waveform activities.
Software has standard test modulus. Software can export PDF & CSV results.
iv. On-site services, verification, installation, connection to current electrical supply and training: Includes on-site installation, calibration and commissioning of the system and a training session for basic operation.
v. 1 year warranty
4. Operation and Maintenance Manuals: Physical or electronic equipment operation and maintenance manuals should be provided with each assembly and include instruction leaflets, instruction bulletins and renewal parts lists where applicable.
5. Additional Requirements
a. All debris must be removed and disposed of by the contractor.
b. All work MUST be completed between the dates of 01 July through 31 August 2026.