Statement of Work.pdf
PDF 1 MB Posted
- Attached to
- Replace Switch Gears FCI Herlong
- Solicitation number
- 15B61926Q00000005
- Issued by
-
Department of Justice Bureau of Prisons
About this file
This Statement of Work (SOW) details a project for the Federal Bureau of Prisons (FBOP) at FCI Herlong in California to replace two medium voltage air switches. The contractor will be responsible for removing existing switches and installing two new Federal Pacific switchgears with outdoor ratings and internal heaters. Key requirements include conducting site visits, performing visual and mechanical inspections, executing electrical tests, providing a 1-year warranty, and offering staff training on the new switches.
The project has specific security and operational guidelines, including work hours from 7:00 AM to 3:00 PM Monday through Friday, mandatory security clearance and orientation for all contractor personnel, and strict protocols for material storage, tool accountability, and personal protective equipment. The contractor must submit various documents within specified timeframes, including security clearance paperwork, progress schedules, and Material Safety Data Sheets. The FBOP will provide minimal electricity and coordinate site access, while the contractor must ensure minimal disruption to the facility's operations during the switchgear replacement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cover Letter.pdf | ||
| Product Specifications.docx | DOCX document | |
| 15B61926Q00000005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES DEPARTMENT OF JUSTICE
FEDERAL BUREAU OF PRISONS
FCI Herlong
741-925 Herlong Access Road A-25 Herlong, CA 96113
B&F PROJECT# 26Z6AH9 REPLACE ADMIN BUILDING SWITCHGEAR
STATEMENT OF WORK
1. SPECIFICATIONS:
A. INTRODUCTION
1. The Federal Bureau of Prisons (FBOP), Federal Correctional Institution in Herlong, California intends to make a single award to a responsible entity to provide all necessary equipment, labor, materials, and incidentals to replace the current medium voltage air switches located at the Federal Correctional Institution (FCI), Herlong. 741-925 Herlong Access Road, A-25 Herlong, CA 96113. The contractor is responsible for replacing and installing all components of two (2) medium voltage air switches. It is the contractor's responsibility to obtain permitting, should it be required.
B. SCOPE OF WORK
1. The contractor shall be responsible for removing, replacing, and installing two (2) medium voltage air switches; to include parts, materials and services needed for project. Upon completion of installation, it shall be tested by the contractor to demonstrate the systems' functionality. For security and safety purposes, at no time shall more than one (1) medium voltage switchgear be non-operational without the authorization of the Contracting Officer's Representative (COR).
The Contractor will be responsible for the following:
a.
b.
c.
d.
e.
f.
g.
h.
i.
ii.
iii.
iv.
Ensuring the new switchgear will be manufactured by Federal Pacific to match the existing recently replaced switchgear located at the Outside Warehouse and Pump House Contractor will conduct a site visit to ensure the two new Federal Pacific switchgears match the existing KVA of the switches to be replaced prior to the start of work.
The new Switchgears will be outdoor rated with internal heaters to control excess moisture.
Shutdown and remove the two existing medium voltage air switches.
Contractor will provide all operators manual for the new switches.
Contractor to provide a 1-year warranty on all products and parts installed.
Contractor to provide staff training on the new switches.
Conducting Visual and Mechanical Inspections to include;
Inspect anchorage, alignment, grounding and required clearances.
Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation and mechanical operation.
Verify fuse sizes and types are in accordance with drawings, short-circuit studies and coordination studies.
Verify expulsion-limiting devices are in place on all fuses having expulsion- type