This Statement of Work (SOW) details a modernization project for the USDA Agricultural Research Service's Poisonous Plant Research Laboratory in Logan, Utah. The project encompasses multiple facility improvements, including replacing irrigation mainlines, repairing a cow barn, replacing a livestock chute, installing a frost-free hydrant, and upgrading VAV (variable air volume) boxes in office and laboratory spaces. The work will be performed at two locations: the Poisonous Plant Research Laboratory and Richmond Farm in Utah.
Key project specifications include replacing approximately 2,540 linear feet of 4-inch PVC pipe for irrigation, demolishing and reconstructing part of a cow barn with a new insulated garage door, reinstalling a wall with a new sill plate, installing a 7-foot frost-free hydrant, and upgrading HVAC control systems using Delta Controls. The project is set aside for small businesses under NAICS code 238220, with a total contract duration of 450 calendar days. The estimated project magnitude is between $100,000 and $250,000, and performance bonds will be required. Mandatory site visits are scheduled for July 16 and 17, 2025, with registration required by July 15, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Sign-In Sheet.pdf | ||
| Drawings.pdf | ||
| SF30 - Amendment 01.pdf | ||
| RFIs.pdf | ||
| Past Performance Questionnaire.pdf | ||
| ARS-372.pdf | ||
| SF-1442.pdf | ||
| Wage Determination.pdf | ||
| ARS-371.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
Modernization of Animal, Farm, and Lab Facilities
Poisonous Plant Research Laboratory
Logan, UT
Date: April 1, 2025
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Number: TBD
b. Project Title: Modernization of Animal, Farm, and Lab Facilities (Repair Cow Barn, Replace Irrigation Mainline, Replace Livestock Chute, Install Frost-Free Hydrant, Office VAV Boxes, and Lab VAV Boxes)
c. Project Location: Poisonous Plant Research Laboratory
1150 E 1400 N, Logan, UT 84322-6300
Richmond Farm 8592 North Highway 91 Richmond, UT 84333
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO)
Joshua J. Dobereiner USDA-ARS-Construction and Facilities Team 1815 N. University Street Peoria, IL 61604 Email: josh.dobereiner@usda.gov Tel. No.: (309) 403-3556
b. LOCATION MONITOR (LM) TBA at Award
c. ADMINISTRATIVE OFFICER
d. SUPERVISORY ENGINEER
e. AREA SAFETY AND HEALTH MANAGER mailto:josh.dobereiner@usda.gov
3.0 PROJECT DESCRIPTION:
Modernization of Animal, Farm, and Lab Facilities
4.0 PROJECT REQUIREMENTS:
a. Do not disturb hazardous materials and report condition immediately to the Contracting Officer’s Representative (COR) regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.
b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
c. Access the site between 7:00 am and 5:00 pm Monday through Friday excluding federal holidays. Contractor staff must sign-in on the first day of arrival and then sign-out on the final day of the project, upon completion.
4.1 Background & Site Description:
Item a. in section 4.2 below is located at the Richmond Farm, 8592 North Highway 91, Richmond, UT. The remainder of the items in section 4.2 below are located at the Poisonous Plant Research Laboratory at the southwest corner of 1400 N and 1200 E in Logan, UT.
4.1 Bid Schedule:
Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.
4.2 Description of Work:
a. Replace Irrigation mainline for irrigation of crops for animal forage to support research mission as shown in picture below.
North-West Yellow line
Qty Size Description 1300 ft. 4" 125# PVC pipe 7 4" Riser tee assemblies 1 4" End of line assembly 1 Fittings to tie onto mainline w/ shut off valve 1300 ft. Pipe installation 2 Thrust blocks
South-West Yellow Line
Qty Size Description 1100 ft. 4" 125# PVC pipe 11 4" Riser tee assemblies 1 4" End of line assembly 1100 ft. Pipe installation
East Yellow Line
Qty Size Description 140 ft. 4" 125# PVC pipe 1 4" Riser tee assemblies 1 Fittings to tie onto pump and get pipe in ground 140 ft. Pipe installation
b. Cow Barn Repair
Demolition:
Demolition to include the endwall, the tracks from the previous garage door, and the existing concrete foundation (indicated by *)
Renovation:
Pour new foundation (concrete) to replace previous foundation using rebar to tie into existing concrete. Rebuild end wall, insulate with R-15 and provide opening for a new (10 X 8) insulated garage door. New insulated garage door (10 X 8) (furnished by contractor) and to be installed.
c. Cow Barn Wall Repair (wall is no longer connected to the foundation).
Disassemble wall (shown below, wall is 8’x26’ and 4” thick). Replace and fasten new sill plate (pressure treated) to the existing foundation (shown by an *, 26’ in width) and then re-assemble (build) the wall to its original form. The wall is insulated (R11) with ½” plywood sheeting on both sides. Plywood and insulation will be reused.
d. Install Frost Free Hydrant (7 ft hydrant) (indicated by * on the picture), 3 feet aboveground, pipe installed following yellow line at depth of 4 feet, install 6 ft bullard near hydrant for protection (3 ft aboveground).
Qty Size Description
162 ft. 1" Polyethylene pipe
1 Frost free hydrant 1 Fittings to tie into main line and new hydrant 162 ft. Pipe installation
e. Replace and Install new Cattle Chute in treatment room
Demolition: removal of old cattle chute, may require concrete and metal cutting.
Installation: Cattle chute to be replaced, new chute must fit through existing garage door which measures 83 inches (height) x 118 inches (wide), new chute when installed can be no taller than 101 inches when opening and closing. Chute to be replaced must be brand name or equivalent to Arrow-quip Q-Catch 74 series squeeze chute (https://arrowquip.com/cattle-equipment/cattle-squeeze-chutes/q-catch-squeeze-chute/) with a detachable sternum bar. Chute must have a ten-year warranty for all parts. New chute will be installed with load bars no taller than 4 inches high, waterproof, 11,000 lb capacity, and that are compatible with the chute. Concrete cutting, new concrete work, and welding work will be required for the installation of the chute as the chute is anchored to the concrete through metal plates that are anchored into the concrete.
Pictures below show garage door that the old chute and new chute must enter and be removed
f. Replacement/upgrade of VAV boxes in offices on the second floor of the main building (some have already been completed), mechanical drawings will be provided upon request. (OPTION 1)
-It is the intent of this project to upgrade the remaining nineteen (19) VAV boxes located on the second floor to Delta Controls. The new controls shall match the existing Delta EZVP controllers, and sensors that were used to upgrade the 1st floor offices and some 2nd -floor offices.
-New controls shall be integrated into the facilities existing Niagara-N4 control system. VAV Graphics, and floor plans shall be created/modified to match existing upgraded areas -Demo existing VAV box controls and deliver to owners designated representative.
-Provide and install new Delta VAV controller, discharge air temperature sensor, and space temperature sensor.
-Install new BACnet communication wire and thermostat wire to new VAVs.
-Remove all unused LON communication wiring. The existing lab controls will remain on the LON communication buss. The contractor shall adjust LON wiring to maintain communication integrity for the Lab control system, with minimum down time.
-REUSE the existing hot water control valves and the existing VAV power wiring.
g. Replacement/upgrade of VAV boxes in the laboratories on the first and second floor of the main building, mechanical drawings will be provided upon request. (OPTION 2)
-It is the intent of this project to upgrade controls in the first and second floor Lab to Delta Controls. The new controls shall match the existing Delta EZVP controllers, and sensors that were used to upgrade the 1st floor offices and some 2nd-floor offices.
-New controls shall be integrated into the facilities existing Niagara-N4 control system. The Lab Graphics, and floor plans shall be created/modified to match existing upgraded areas -Demo existing Lab VAV Tracking pair VAV box controls and air flow monitoring sensors and devices. Deliver parts to owners’ representative.
-Provide and install new Delta VAV controllers, velocity air sensors, discharge air temperature sensors, and space temperature sensors on Lab exhaust and supply VAV boxes.
-Provide and install new velocity probes on lab DDC controllers -Provide new DDC controller for lab exhaust fan control and monitoring additional points.
-Install new BACnet communication wire to new VAVs.
-Remove all unused LON communication wiring. The contractor shall adjust LON wiring to maintain communication integrity for the Lab control system, with minimum down time in labs that have not been upgraded yet.
-REUSE the existing hot water control valves and the existing VAV power wiring.
4.3 Description of Work
a. The contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.
b. The contractor will provide and install the necessary material per Section 4.2 and properly dispose of all material being replaced.
c. Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during installation. The contractor is responsible for making repairs to meet or exceed conditions prior to damage.
d. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.
4.4 Government Furnished Equipment\Services
a. Government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations.
Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor. The Contractor shall retain and pay for the services of an independent inspector or testing laboratory to perform all tests expressly required by this contract.
5.6 Protection of Work and Property/Safety Requirements:
a. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.
b. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
c. Contractor is responsible for verifying location of any underground utilities and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the
Contractor shall obtain approval for such shutdown from the Location Monitor fourteen
(14) calendar days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.
5.10 Warranty:
a. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO
FINAL PAYMENT (other documents may also be required):
a. General contractor’s minimum one (1) year warranty on work.
b. Release of liens
c. Final Invoice
6.0 Project Schedule:
The Contract time for this project is 450 calendar days from Notice to Proceed.