This document contains two Statements of Work (SOW) for repair and painting projects at the Timucuan Ecological and Historical Preserve in Jacksonville, Florida. The first SOW details roof repair work involving replacing rotted roof sheathing in two valleys of the Headquarters/POD structure, which includes removing metal gutters and roof panels, replacing damaged wood components, installing waterproof underlayment, and reinstalling roof panels. The project requires matching existing Forest Green metal roof panels and ensuring watertight transitions, with no building permit needed but work to comply with Florida Building Codes.
The second SOW covers exterior painting of the TRA Headquarters/POD structure, involving approximately 15,000 square feet of surface preparation and painting. The scope includes pressure washing, sanding, caulking, priming, and painting exterior surfaces such as walls, doors, window frames, floor trim, and roof structure undersides. The contractor will use top-quality Benjamin Moore acrylic exterior latex paint in low luster and satin finishes, with colors matched to an existing Curatorial Building. Specific areas like deck boards, ramps, and steps are to remain unpainted, and the contractor must carefully protect electrical items and prevent paint intrusion into the building.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P5425R0012_Amd_0001.pdf | ||
| Past_Performance_Questionnaire.pdf | ||
| Sol_140P5425R0012.pdf | ||
| Wage_Determination.pdf | ||
| Project_Pictures.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1/13/2025 Rev 1
STATEMENT OF WORK Rev 1
FOR THE REPLACEMENT OF ROTTED ROOF SHEATHING ON THE 2 VALLEYS OF THE
HEADQUARTERS/POD STRUCTURE
LOCATION: Project is located at 13165 Mt Pleasant Road, Jacksonville, Florida, 32225.
REQUIREMENT: This project is to replace the rotted sheathing in the two valleys of the HQ & Pod building transition prior to the structural exterior painting project. Particulars are;
1. Remove the metal gutters, and downspouts + metal roof panels (Approx 650sqft total) as needed to expose areas of repair from the outer/bottom edge of the porch fascia, up toward the main building, into solid/intact sheathing. Gutters, downspouts, and metal roof panels will be re-installed and as such, should be stored onsite to reduce handling.
2. Cut out all rotted valley roof decking back to un-damaged joists/rafters. Replace with appropriately sized (15/32”?) materials.
3. Replace/Sister/Scab any rotted rafters/joists/fascia with appropriately sized #1 grade lumber.
4. Install high temperature/waterproof peel and stick rubber type sublayer rated for metal roofing.
5. Install new valley and offset cleats for the roof panels. Color of roof panels to match as close as possible.
6. Install custom made side flashing under the valley area to cover all exposed wood.
7. Re-Install panels in accordance with manufacturer’s standards using appropriate non-corrosive cleats, screw/rivets
8. If needed install new ridge cap to disturbed areas. Color to match as close as possible.
9. Ensure all tie ins/transitions are watertight.
10. Provide standard commercial industry warranty on workmanship/materials
Contractor shall furnish all labor, materials, equipment, and related miscellaneous details necessary to complete the work as specified herein. Building Permit IS NOT required. All work, however, will be completed according to state of Florida Building Codes.
** Contractor can dispose of debris in the 20YD Dumpster located at our Maintenance Shop 12713 Ft Caroline Rd, Jacksonville, FL 32225**
**Metal Roof was installed in April 2018. Metal Panels, Forest Green SL150 integral 1.5” Snap-Lock, 24 GA standing Seam, smooth finish 16” width, were purchased by the GC from Union Corrugating Company Fayetteville, NC 28302 (www.unioncorrugating.com) and installed over 15/32” Plywood. (Old Asphalt Shingle roofing was removed prior to metal roof installation). Water Ice Shield Underlayment was installed over entire roofing substrate in accordance with manufacturer’s standards and FL building code. **
Point of Contact: David Foley (904) 545-8221 David_Foley@nps.gov http://www.unioncorrugating.com/ mailto:David_Foley@nps.gov
1/13/2025
STATEMENT OF WORK
FOR THE PAINTING OF THE TRA HEADQUARTERS/POD EXTERIOR STRUCTURE
LOCATION: Project is located at 13165 Mt Pleasant Road, Jacksonville, Florida, 32225.
REQUIREMENT: This project is to Prepare (Pressure wash, sand, caulk, prime etc.) and paint exterior surfaces of the HQ & Pod buildings. Surfaces include the exterior walls, doors (Ext & Int), window frames, floor trim, the underside of the roof structure (apply rust preventive to nails), soffit, sill plate, mailbox post and all other previously painted structure members. Total area to be painted is approximately 15,000sqft and DOES NOT Include the pressure treated deck boards, ramps, steps, rails, and posts. These areas must remain "paint free".
All lighting, placards and vent covers will be removed by NPS. Any items left to include fans, switches, power boxes, hose bibs, drain lines, door hardware etc. if not previously painted, will be protected and remain paint free.
Contractor will take great care in not allowing the intrusion of water and paint spray into the building and electrical items.
Paint will be top of the line Benjamin Moore acrylic exterior latex low luster on walls and ceiling, and satin on trim and doors. Colors will be selected to match our Curatorial Building down the hill.
Contractor shall furnish all labor, materials, equipment, and related miscellaneous details necessary to complete the work as specified herein.
mailto:David_Foley@nps.gov
| Statement of Work REPAIR ROOF SHEATHING ON BOTH VALLEYS HQ-POD STRUCTURE (Rev 1) |
| STATEMENT OF WORK PREP and PAINT EXTERIOR HQ-POD STRUCTURE |
File details come from the government source that posted it. Updated .