This document is a Statement of Work (SOW) for a federal contract opportunity to restripe lines and markings on the ramp at USCG AIRSTA Detroit in Selfridge Air National Guard Base, Michigan. The work includes restriping multiple lines and markings such as 50' and 20' diameter circles, yellow striping, white striping, red striping, and yellow curbing. The contractor must be licensed in the State of Michigan and specialize in painting and marking regulations for airfields. The period of performance is 30 days after contract award, with work to commence within 5 calendar days of the notice to proceed. The applicable NAICS code is 237310 (Highway, Street, and Bridge Construction) with a small business size standard of $45.0M. The related federal contract opportunity, Solicitation Number 70Z03024QCLEV0141, is for the US Coast Guard AIRSTA Detroit Ramp Restriping Project. The solicitation will not be extended due to end of fiscal year funding sweeps, and a site visit is highly recommended for accurate pricing.

View the file

Other files

File Type Posted
Solicitation 70Z03024QCLEV0141.docx DOCX document
REFERENCE INFORMATION.pdf PDF
REQUEST FOR INFORMATION.pdf PDF
Solicitation 70Z03024QCLEV0141 Letter.pdf PDF
Solicitation 70Z03024QCLEV0141 - SF 1442.pdf PDF
Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Updated July 2024

SCOPE OF WORK: Ramp Restriping at CG AIRSTA Detroit

1. GENERAL REQUIREMENTS:

The work consists of providing all labor, materials, and equipment necessary to restripe lines and markings on the ramp at USCG AIRSTA Detroit, 1461 N Perimeter Rd, Selfridge Air National Guard Base, MI 48045.

2. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK:

Upon acceptance the contractor shall commence work NLT five (5) calendar days after notice to proceed and work diligently to complete the entire work ready for use by 30 days after contract award.

3. SCOPE OF WORK:

The unit has multiple markings and lines on the ramp used for various reasons that need to be restriped in order to meet ramp marking regulations at Selfridge Air National Guard Base (SANGB). Reason for failure is assumed to be aging and weathering of current markings. The contractor shall restripe all markings necessary for operations at USCG AIRSTA Detroit, 1461 N Perimeter Rd, Selfridge Air National Guard Base, MI 48045.

4. DESCRIPTION OF FACILITY:

The ramp markings are located on the east side of the Maintenance Hangar (building 1401) and the south side of the Operations Hangar (building 1461), leading out to the SANGB taxiway on USCG AIRSTA Detroit and SANGB. The contractor will be escorted to this location by the Contracting Officer’s Representative.

5. CONTRACTOR CERTIFICATIONS:

The contractor shall currently be licensed in the State of Michigan, specializing in painting and marking regulations for airfields. The Contractor shall submit a photocopy of certification to the contracting officer.

6. DESCRIPTION OF WORK:

The contractor shall provide labor, equipment, and materials necessary to restripe multiple lines and markings on the ramp to include 4” line striping of the following: 50’ dia black/yellow circle (1), 20’ dia black/yellow circle (1), 50’ dia yellow circle (4), 20’ dia yellow circle (4), 4’ dia yellow circle (5), 20’ dia red circle (1), 100’ dia red dashed circle (1), 1200 linear feet of yellow striping, 250 linear feet of white striping, 550 linear feet of red striping, and 1515 linear feet of yellow curbing.

7. CONTACT ADMINISTRATOR/POINT OF CONTACT:

The following employees of the U.S. Coast Guard identified will use all powers under the contract to enforce its faithful performance: EMC Alexander E Karjala & LCDR Mark C. Dukti.

8. CONTRACTING OFFICER:

All orders from the U.S. Coast Guard shall be transmitted and communicated through the Contracting Officer. The appointed Contracting Officer is _____.

Updated July 2024

9. CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE (COTR):

The COR shall work with the contractor on a daily basis in scheduling and coordinating services, answering questions in conjunction with the scope of work (SOW), and provide general direction under the resulting contract: _____.

10. INCURRED COSTS:

The contractor shall furnish all supplies including consumable materials and tools to replace discrepant items from the inspection.

11. ENVIRONMENTAL PROTECTION REQUIREMENTS:

Hazardous materials used by a contractor are required to be disposed of by that contractor.

Disposal must be in accordance with federal, state, and local guidelines.