Statement_of_Work.pdf

PDF 80 KB Posted

Attached to
BLM-WY WORLAND STOCKWATER PIPELINE
Solicitation number
140L6224Q0048
Issued by

About this file

This document is a Statement of Work that provides specifications for furnishing 28,000 feet of 1-inch diameter HDPE pipe suitable for various water applications such as potable water, geothermal, reclaim water, intake water, raw water, and wastewater. The materials are to be delivered to a location in Worland, Wyoming behind a secured gate, with deliveries accepted between 8:00 AM and 3:00 PM excluding weekends and federal holidays. The contractor shall deliver all materials within one month after the award has been signed. There will be no separate measurement or direct payment for the work; it will be included in the lump sum bid price.

The related federal contract opportunity is a combined synopsis/solicitation for the BLM-WY Worland Stockwater Pipeline project. This is a firm-fixed price contract for the 28,000 feet of 1-inch HDPE pipe per the attached specifications. The contracting agency is the Department of the Interior Bureau of Land Management Wyoming Region. This is a total small business set-aside under NAICS code 332996. Offers must meet or exceed the stated specifications. Key requirements include an active SAM.gov registration, compliance with Section 889 clauses, and invoicing/payment through www.ipp.gov with 30-day prompt pay. Quotes must be valid for 60 days and emailed to the specified Contracting Specialist by the required response date.

View the file

Other files

File Type Posted
Sol_140L6224Q0048_Amd_0001.pdf PDF
Statement_of_Work_Updated_0001.pdf PDF
Questions_Addressed_0001.pdf PDF
Sol_140L6224Q0048.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. BUREAU OF LAND MANAGEMENT

WORLAND FIELD OFFICE, WYOMING

Pipe Materials Only

Material Specifications

PART 1: GENERAL

1.1 SUMMARY

A. Description of Work: Furnishing pipe materials as per specifications, material list, and attached bid schedule. Contract is for materials only.

B. Materials Transport: Materials will be protected from damage while in transit to the site. Products must be transported/delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.

C. Materials Delivery: The materials shall be delivered to the located at 4162 Gooseberry Creek Rd Worland, Wyoming. This location is behind a secured gate. Contractor shall have materials delivered between 8:00 AM to 3:00 PM excluding weekends and federal holidays. The Contractor shall notify the Contracting Officer three (3) business days before delivery of material.

D. Delivery Schedule: Contractor shall deliver all fence material within one

(1) month after the Award has been signed.

E. General Material Information:

• Total Pipeline = 28,000 Feet

• Design: HDPE Pipe DR 11, HDPE pipe HD-6. Pipleine 1 ½” in diameter.

1.2 REFERENCES

A. Referenced Specifications/Standards with Abbreviations and/or

Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/ standards referred to herein may be procured by the Contractor, from the following:

CFR Code of Federal Regulations (Available from the Government

Printing Office)

N. Capitol St. between G and H St., NW

Washington, DC 20402

FS Federal Standard

General Services Administration

Specifications Branch

Room 6039, GSA Building

7th and D Streets, S.W.

Washington, DC 20407

GSA General Services Administration

F St. and 18th St., NW

Washington, DC 20405

OSHA Occupational Safety and Health Administration

US Department of Labor

200 Constitution Ave., NW

Washington DC 20210

OSHA 2207-91 Construction Industry

PART 2: PRODUCT SPECIFICATIONS

A. 1 1/2 “Diameter HDPE pipe DR-11, 250 PSI: Pipe that is suitable applications include Potable Water, Geothermal, Reclaim Water, Intake Water, Raw Water and Wastewater. Joints are leak proof that are heat fused and fully restrained. Maintains flow rates due to resistance to corrosion and biological growth and fatigue resistant.

PART 3: MEASUREMENT AND PAYMENT

3.1 METHOD OF MEASUREMENT

A. Units: There will be no separate measurement for individual items of work done under this Contract.

3.2 BASIS OF PAYMENT

A. Payment: No direct payment for the work described under this section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.

Pay Unit

Lump Sum with attached bid schedule.

END OF SECTION

File details come from the government source that posted it. Updated .