This document is a Performance Work Statement (PWS) that outlines the scope of work for a federal contract opportunity to provide services for the U.S. Coast Guard Base in Astoria, Oregon.

The contractor must furnish all personnel, equipment, tools, materials, supervision, and other items and services necessary to remove existing laminate, vinyl, baseboard trim, carpeting and padding in government living quarters, and replace them with new LVP laminate flooring, baseboard trim, and carpet and padding provided by the government. The work must be completed between July 29, 2024 and September 6, 2024, with a one-time site visit on July 23, 2024. The contractor must follow specific requirements for seam installation, carpet edging, cleaning, and restoration. This contract opportunity is a 100% Small Business set-aside with a NAICS code of 541330 and a $25.5M size standard.

View the file

Other files

File Type Posted
Statement of Work.pdf PDF
FP SVC A.pdf PDF
FP SVC R.pdf PDF
Wage Determinations Clatsop County.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT – SCOPE OF WORK

U.S. COAST GUARD BASE ASTORIA

SECTION 1 – GENERAL INFORMATION

1.1 Scope of Work (SOW)

The contractor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform the tasks defined in this Scope of Work (SOW). The contractor must perform to the standards in this contract. Any questions regarding scope of work must be directed to the Contracting Specialist assigned to the contract. One key POC, although subject to change, for this contract is: Matt Piper cell: 503-369- 7797; email: matthew.l.piper@uscg.mil.

1.1.1 Place of Performance

Triumph Housing 200 W. Klaskanine Ave Astoria, OR 97103

1.2 Contractor Personnel

1.2.1 Contract Manager

The contractor must provide a contract manager who must be responsible for the performance of the work.

1.2.1.1 The contract manager or alternate(s) must have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.2.1.2 The contact manager and alternate or alternates must be able to read, write, speak, and understand the English language.

1.2.2 Contractor employees

The contractor must not employ persons for work on this contract if such employee is considered by the contracting officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.

1.2.2.1 Contactor personnel must present a neat appearance and be easily recognized as contractor employees.

1.2.2.2 The contractor must not employ any person who is an employee of the U. S. Government if employing that person would create a conflict of interest. Additionally, the contractor must not employ any person who is an employee of the U. S. Coast Guard unless such person seeks and receives approval according to U. S. Coast Guard regulations.

1.2.3 Security requirements

Due to heightened Security at USCG Facilities, all contractor employees performing tasks related to this SOW, while onboard a Coast Guard facility, shall have proper valid identification. Time spent undergoing entrance to USCG facilities will not be considered a government delay of work or differing site condition.

1.3 Hours of Operation – Projected Date of Completion

1.3.1 The contractor must perform the tasks as required by the SOW under this contract during the following hours: Monday through Friday between 8:00am and 5:00pm unless other time is specified.

1.3.2 Holidays: Not applicable to this contract.

1.3.3 Special event, or adjusted work hours: If circumstances should arise wherein the contractor desires a different work schedule as required in section 1.3.1 above, the contractor must request same in writing. Submit written request to the government Point of Contact POC a minimum of 24 hours before the requested adjusted work schedule. If the desired schedule change is to be effective on a Monday, the request must be submitted to the POC prior to 9:00am on the Friday prior to commencement of work.

SECTION 2 – DEFINITIONS

2.1 General Definitions

When the SOW, solicitation provision or contract clause uses a word or term that is defined in the Federal Acquisition Regulations (FAR), the word or term has the same meaning as the definition as contained in section

2.101 of the FAR. The FAR index is available via the Internet at http://www.acqnet.gov at the end of the FAR, after the FAR Appendix.

2.1.1 Defective Service: A service or commodity output that does not meet the standard of performance requirement specified in the contract for that service or commodity.

2.1.2 Quality Assurance: A planned and systematic pattern of all government actions necessary to provide confidence that adequate technical requirements are established; products and services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the government assurance functions for a contracted service.

2.1.2 Quality Control: Those actions taken by a contractor to control the production of outputs to ensure that they conform to the contract requirements.

SECTION 3 – GOVERNMENT FURNISHED PROPERTY AND SERVICES

3.1 General Information

The Government must provide the facilities, equipment, materials, and services listed here.

3.1.1 Government will furnish approved LVP laminate flooring, baseboard trim, carpet and carpet pad, tack-strips, and transitions.

3.1.2 Government will provide acceptable lay-down area and schedule blocking off area while contractor is performing work.

3.1.3 Government will provide water and electricity necessary for use by contractor in conjunction with this contract.

3.1.4 Contractor is required to schedule with POC to obtain, baseboard trim, transitions, carpet, and carpet pad 24-hours in advance.

SECTION 4 – CONTRACTOR FURNISHED ITEMS AND SERVICES

Except for those items, services, or commodities specifically stated in section 3 above as government furnished, the contractor must furnish everything needed to perform this contract according to all its terms.

SECTION 5 – SPECIFIC TASKS

The contractor shall furnish trained, qualified personnel and any required special tools or equipment necessary to install carpet.

Item No.

Description Units Unit Address

1 8,470 sqft LVP laminate flooring install.

TBD

2 737 sqyd carpet and carpet pad install.

TBD

3 2,320 lf baseboard trim install.

TBD

5.1 Scheduling will be coordinated with local Coast Guard POC a minimum of 7 days prior to work.

5.1.1 Period of Performance is 29JULY2024 – 06SEPTEMBER2024. Units will be made available as residents move out.

5.1.2 A one-time site visit will be held on 23JUL2024 @ 0930, at Housing Unit 1065 Almeda Ave. Astoria, OR. 97103.

5.1.3 The unit at 85 White Bush Rd (2 bedroom, carpet and LVP) MUST be completed by 2 Aug.

5.1.4 10 housing units will be completed: 1 – 2 bedroom units, 2 – 3 bedroom units, 7 – 4 bedroom units.

5.2 Interferences (doors & appliances) - Contractor shall either remove or cover and protect all interferences so surfaces on interferences are not contaminated.

5.3 Project

5.3.1 Contractor shall provide all personnel, equipment, tools, supervision, and other items and services necessary to remove existing laminate, vinal, baseboard trim in non-carpet areas, carpeting and padding in Government Living Quarters; replacing same with new LVP laminate, baseboard trim (LVP area only), carpet and padding provided by the Government as defined in this Statement of Work. Contractor is responsible for the removal and disposal of removed laminate, vinal, baseboard trim, carpet and padding.

5.3.2 Contractor shall install LVP laminate flooring as prescribed by government POC. Install is to be smooth, uniform and without visible gaps.

5.3.3 Contractor shall install all baseboard trim with miter joints and free of any visible gaps.

5.3.4 Contractor shall make carpet seams uniform, unnoticeable, and permanent seams by any of the methods specified below, except when the carpet manufacturer specifies the seaming method. However, treat all joining edges, regardless of seaming method, with a seam adhesive. Seams shall have a minimum breaking strength of 100 pounds per inch and shall be capable of withstanding all carpet cleaning processes.

5.3.5 Contractor shall finish carpet edges meeting hard surface flooring with holdings, installed in accordance with manufacturer’s instructions.

5.3.6 Contractor shall install carpet to be smooth, uniform, and secure with a minimum of seams.

Carpet and wood baseboard shall have no visible gap. Installing quarter-round on the baseboard is not permitted. Base board shall be adjusted if gap is visible and is part of the carpet installation. Run side seams toward the light where practical and where such layout does not increase the number of seams. Install breadths parallel with carpet pile in the same direction.

Fit cutouts such as doorjambs, columns, and ducts neatly and securely. Locate carpet seams at doorways parallel to and centered directly under doors. Ensure proper door clearance to prevent door drag or carpet wear. Do not seam at doorways perpendicular to door or at pivot points.

Stairway carpeting shall only be seamed at intersection of riser and tread. Follow the wall line parallel to the carpet direction for seams at corridor changes of direction. Include all material indicated, specified, or necessary for a complete finished installation by the installation method specified. Contractor shall be responsible for the required quantities of carpet and shall carefully check all dimensions in the field as well as other conditions affecting the work.

Installation shall include re-stretching of the carpet during the warranty period at no additional cost.

5.3.7 Contractor will install carpet as prescribed by the government POC. Carpet will not be installed in the Garage, Kitchen, Bathrooms, Basement, and or any place currently unfinished and/or alternate flooring such as tile, vinyl, and/or laminated flooring is in use. Carpet shall be installed wall to wall.

5.4 Cleaning, protections, and care of property.

5.4.1 Contractor is responsible upon completion of installation to remove all debris, moldings, scraps, and other foreign matter. Remove soiled spots or adhesive from the face of the carpet with the appropriate spot remover. Clip protruding face yard with sharp scissors. Vacuum the carpet clean.

5.4.2 Contractor shall attempt to avoid damaging or altering existing finishes including furniture and equipment and other building contents. If such property is damaged or destroyed, it shall be replaced or repaired, as directed, at the Contractor's Expense. Units may or may not be occupied and contain household furnishings. Upon completion of work, the Contractor shall clean all surfaces of dust and debris resulting from work within the unit to include vacuuming.

5.5 Restoration

5.5.1 Contractor shall return all interferences to proper location and or condition.

5.5.2 Contractor to ensure all waste, garbage, debris, has been removed and disposed of in a proper manor.

5.5.3 Contractor is not permitted to perform on-site clean-up of equipment.

SECTION 6 – INSPECTION

Inspection - Contractor shall schedule inspection with Coast Guard Inspector/POC and supply documents for acceptance of project.

SECTION 7 – APPLICABLE PUBLICATIONS AND FORMS

7.1.1 N/A

SECTION 8-INVOICING

In conjunction with the subject award, proper invoices will be submitted through the Invoice Processing Platform (IPP) at https://www.ipp.gov/. IPP is a secure web-based electronic invoicing system provided by the U.S.

Department of the Treasury’s Bureau of the Fiscal Service in partnership with the Federal Reserve Bank of St. Louis

(FRSTL). IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency.

Actions to take:

If you are already enrolled in IPP:

If your company is already registered to use IPP, you will not be required to re-register and you do not need to contact IPP.

If you are NOT already enrolled in IPP:

The point of contact you provided in your SAM.gov registration will receive two emails from ipp.noreply@mail.eroc.twai.gov. Please note that emails from this email address may filter into your spam or junk folder:

1. The first email will have the IPP Logon ID and a link to the IPP application.

2. A second email, which will be sent within 24 hours of the first email, contains a temporary password.

Once your contact receives these emails, please ensure they log into IPP and complete the registration process.

Once registered to use IPP, your company may submit invoices electronically, receive e-mail notifications when requests are paid, view payment history, and access remittance downloads. The e-mail notification of payment is sent when a payment is distributed to your bank account and may include the following payment information: Date of payment, dollar amount, invoice number, paying agency, payee name, and ACH trace number.

Vendor training materials, including a first time login tutorial, are available on the https://www.ipp.gov/ website.

Once you have logged in to the IPP application, you will have access to user guides that provide step-by-step instructions for all IPP capabilities, ranging from creating and submitting an invoice to setting up email notifications. Live webinars are held monthly and provide a great opportunity to learn the basic of the system and to call in and ask the IPP team questions about the IPP application.

IPP Customer Support is available to assist users of the system and can answer your questions related to accessing IPP or completing the registration process.

Toll-free number: 866-973-3131 Email address: IPPCustomerSupport@fiscal.treasury.gov Hours of operation: Monday through Friday (excluding bank holidays) from 8:00 am - 6:00 pm ET

File details come from the government source that posted it. Updated .