This document is a Statement of Work (SOW) for a requirement to replace refrigeration components for a tree cooler at the USDA Tahoe National Forest, Foresthill Ranger District location. The SOW outlines the contractor requirements, including dismantling and removing the existing mechanical refrigeration equipment, installing a new outdoor condensing unit and indoor evaporator system, running new refrigeration piping, and charging the system with new refrigerant. The work must be completed within 30 days of award, and no government-furnished equipment or travel is required. The contractor must provide a professional journeyman-class technician to perform the work. This SOW is associated with Solicitation Number 12970224Q0049, issued by the USDA Forest Service, for the Tree Cooler Repair requirement. Responses are due by 1700hrs on 26 July 2024 and should be sent to Veronica.Beck@usda.gov.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12970224Q0049 RFQ AARD Cooler Repair Clauses and Provisions.pdf | ||
| 12970224Q0049 RFQ AARD Cooler Repair.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment ............................................................................................................................................. Error! Bookmark not defined.
Project ARRD Cooler Repair
General Information
1.0 Scope of Work
Replace refrigeration components for the tree cooler.
2.0 Background
The tree cooler is no longer functioning. The cooler needs to maintain a temperature of 32-36 degrees.
Contractor Requirements
3.0 Technical Requirements / Tasks
Dismantle and remove existing Mechanical Refrigeration equipment from site. Install new Outdoor condensing unit in place of old one. Install new Indoor evaporator system with new TXV, solenoid valve and coil and new temp/defrost controls. Run new insulated refrigeration copper pipe from outdoor unit to new indoor unit. Braze all connections, Pressure test with Nitrogen to 300 PSI and pull vacuum on refrigeration system to hold at 500 microns to prove leak free. Charge system with all new R-448 refrigerant. Start up and test equipment. Set all controls for proper operation.
Outdoor Condensing Unit, 2 horsepower, 1 phase, 208/230 volts Indoor Evaporator Assembly All Necessary Valves and Controls The cooler needs to maintain a temperature of 32-36 degrees.
Location:
FORESTHILL RANGER DISTRICT
22830 FORESTHILL RD
FORESTHILL CA 95631
4.0 Government Furnished
None.
5.0 Deliverables / Schedule
Complete work within 30 days of award.
6.0 Travel
None
7.0 Contractor’s Key Personnel
Professional journeyman class technician
8.0 Security Requirements
None
9.0 Data Rights
None
10.0 Section 508 – Electronic and Information Technology Standards None
| Project |
| General Information |
| 1.0 Scope of Work |
| Replace refrigeration components for the tree cooler. |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |