STATEMENT OF WORK.pdf
PDF 85 KB Posted
- Attached to
- INSTALLATION OF HARD X-RAY REFLECTOMETER Federal contract opportunity
- Solicitation number
- 80NSSC235138
About this file
This statement of work outlines requirements for the installation of a hard X-ray reflectometer system and radiation enclosure at the Goddard Space Flight Center. Bookholt Associates LLC will perform the installation within one month of being awarded the contract under solicitation number 80NSSC235138. The scope of work involves installing all components of the hard X-ray reflectometer, which are already on site at building B224, as well as the radiation enclosure and preparing it for X-ray testing. All installation activities will be completed within two days at the Goddard Space Flight Center by Bookholt Associates LLC, who originally designed the radiation enclosure.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
1. Objective/Requirements
X-ray optics group in Code 662 (GSFC) obtained an hard X-ray reflectometer and its radiation enclosure from their research collaborator. However, the system did not come with an installation manual. Also the radiation enclosure needs to be installed by people who are authorized to work with radiation safety hardware. The X-ray optics group needs to ask Bookholt Associates LLC who originally designed the radiation enclosure to install the system.
Engineers from Bookholt Associates LLC shall come to GSFC GGAO B224 and install the hard X-ray reflectometer and its radiation enclosure. They will make the radiation enclosure usable for X-ray tests. (All the parts/components are already at B224.)
2. Characteristics, Scope, and Specs
Scope of this work is to install the hard X-ray reflectometer system as well as its radiation enclosure, and make the radiation enclosure usable for X-ray tests.
3. Place of Performance At Goddard Space Flight Center (GGAO B224) by Bookholt Associates LLC
4. Period of Performance The work shall be performed within one month after the PO awarded. The performance period shall be < 2 days (nominally 1 day).
File details come from the government source that posted it. Updated .