Statement of Work.pdf
PDF 131 KB Posted
- Attached to
- Seal Coat Vernal, UT Parking Lot
- Solicitation number
- 1284N820Q0093
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drawings signed.pdf | ||
| QUOTE SHEET WITH TERMS.pdf | ||
| FP03 section 634 paint striping.pdf | ||
| Wage Determination.pdf | ||
| Drawings signed.pdf | ||
| 321214_slurry_sea1.pdf | ||
| fp03 414 crack sealing.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
1.1 SCOPE OF CONTRACT
A. This project includes work to apply a slurry seal on the Vernal Forest Service Office parking lot and paint striping parking stalls as specified in specifications and drawings
B. Quantities associated with this work are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The project is located at the Vernal Forest Service Office, 355 North Vernal Avenue in Vernal, Utah.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Water is available at the site for construction purposes.
2. Toilet facilities are available at the site
3. Electricity is available
1.4 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers.
B. No overnight camping will be allowed on site.
1.5 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.6 START DATE
A. Summer/Fall 2020 – We are flexible and want to allow for good weather conditions.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
1.7 SITE VISIT:
A. If you would like to request a site visit, submit your request to the contracting officer.
1.8 CONTRACT TIME
A. Base Bid: 10 Calendar Days
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
000001- Section C 321214 – Slurry Seal FP-03 Section 414 – Asphalt Pavement Crack and Joint Sealing FP-03 Section 634 – Permanent Pavement Markings
END OF SECTION C
May 2020
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
| Section C - Description/Specifications/Statement of Work |
| 1. Water is available at the site for construction purposes. |
| 2. Toilet facilities are available at the site |
| 3. Electricity is available |
File details come from the government source that posted it. Updated .