This Statement of Work (SOW) details a contract for the 580th Software Engineering Squadron (SWES) to rebuild four (4) fiber optic cables for a communication processor test bench at Robins Air Force Base. The requirement is a build-to-print contract where the selected contractor must manufacture custom fiber optic cables according to specific technical drawings (U108223-10, U108223-30, U108223-50, U108223-70), with each cable having unique specifications outlined in the technical data package.
Key contract details include a 60-day delivery timeline after order receipt, FOB destination shipping, and delivery to SMXG/580th SWES at 280 Byron St., Bldg 229E, Robins AFB, GA. The solicitation (FA857925Q0016) is being conducted under Simplified Acquisition Procedures as a Request for Quote, with quotes due by Tuesday, 15 July 2025 at 4:00 pm EST. Vendors must email quotes to Jonathon VanBrunt, include their CAGE CODE, and provide a narrative demonstrating financial capability to complete the cable rebuild project. All produced units will become U.S. Government property upon contract completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment-FA857925Q00160002.pdf | ||
| Amendment-FA857925Q00160001.pdf | ||
| Solicitation - FA857925Q0016.pdf | ||
| Equipment List.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
For 580 Software Engineering Squadron (SWES)
12744 B77415 - Fiber Optic Cables
17 January 2025
1.0 GENERAL INFORMATION
Scope The 580th SWES maintains a fiber channel connected communication processor test bench at Robins Air Force Base. There is a requirement to rebuild the interconnecting cable sets inside this test bench, and the 580th needs a contractor to build the four (4) Fiber Optic Cables.
This Statement of Work (SOW) defines contractor tasks and requirements for management, manufacturing, and delivery of the Fiber Optic Cables. A technical data package with drawings and models for each cable has been developed and contains the individual specifications for each assembly. The objective of this effort is to award a single contract to build and produce the four (4) Fiber Optic Cables as directed in Sections 3 & 4 of this SOW.
Background The 580th SWES communication processor test bench has undergone a number of changes that has compromised the current fiber optic cables. The system is being rebuilt to support future workload and as such, length, wear points, and channel quantities have changed. The rebuild effort provides a good opportunity to update the Fiber Optic Cable set to a more reliable and versatile configuration.
2.0 SPECIAL CONSIDERATIONS
2.1 Program and Engineering Management
All contractor tasks and requirements covered by this document shall be coordinated with the 580th SWES team. Overall responsibility and approval of any changes to the contract or attachments resides with the Primary Contracting Officer (PCO).
2.2 Contract Management
Overall responsibility and approval reside with the PCO. No conversation, recommendation, or direction, whether given directly or implied by Government personnel or representative, that will affect the scope, schedule, or price of the program covered by this SOW, shall be acted upon by the contractor unless specifically directed in writing by the PCO.
3.0 GOVERNMENT FURNISHED INFORMATION
All drawings are Distribution Statement D, which requires distribution to only authorized Department of Defense (DoD) and U.S. DoD contractors. Upon proof of DoD contractor certification, access to the drawing will be provided to the contractor. The following documents/drawings will be provided in the Technical Data Package:
| NONMENCLATURE |
| DWG# |
| 12744 B77415 - Data Package - Fiber Optic Cables (U108223).pdf |
| U108223-10 |
U108223-30 U108223-50 U108223-70
4.0 CONTRACTOR TASKING AND REQUIREMENTS
The contractor shall accomplish the following task and requirements during the manufacture, validation and verification, and delivery of the four (4) Fiber Optic Cables:
4.1 Contractor Management
The contractor shall plan, direct, coordinate, monitor, evaluate, and control contractor tasks specified in this SOW. The contractor shall notify the PCO and 580th SWES by email, of any management problems requiring Government action.
4.2 Contractor Specific Requirements
This SOW describes a build-to-print contract. The contractor shall acquire necessary parts, build/assemble, and verify the four (4) Fiber Optic Cables as detailed by the Engineering Drawing # U108223 titled:
12744 B77415 - Data Package - Fiber Optic Cables (U108223).pdf (Design Package attached).
| Cable/Item number |
| Drawing Assembly |
| Data Package pages |
| 1st Cable/Item |
| U108223-10 |
| pages 1, 2, 3 |
| 2nd Cable/Item |
| U108223-30 |
| pages 1, 2, 4 |
| 3rd Cable/Item |
| U108223-50 |
| pages 1, 2, 5 |
| 4th Cable/Item |
| U108223-70 |
| pages 1, 2, 6 |
4.2.1 The Contractor shall build all required cables to the specification provided in the attached Technical Data Package provided by the Government.
4.3 Delivery Schedule
4.3.1 The Contractor shall deliver all four detailed cable assemblies 60 days after receipt of order.
4.3.2 The Contractor is responsible for all shipping costs associated with FOB Destination.
4.3.3 Early or partial deliveries are authorized.
4.4 Packaging and Shipping
| 4.4.1 The Contractor shall ensure all fiber ends are dust-capped and protected, and cable assemblies are packaged separately so as to prevent damage to part features and finishes during shipment. | ||
| 4.4.2 The Contractor shall ensure all parts are properly identified and shipped per the instructions provided in the contract (i.e., CLINs, Ship to DoDAAC and delivery instructions.) | ||
| 4.4.3 The Contract will have the following distinct shipping instructions and addresses: | ||
| ADDRESS: | ||
| SMXG/580th SWES | ||
| Attn: Peter Gilbane | ||
| 280 Byron St., Bldg 229E | ||
| Robins AFB, GA 31098 |
| MARK FOR: | Peter Gilbane (Peter.Gilban@us.af.mil 478-926-0439) |
| Alternate: | Adam Saunders (Adam.Saunders@us.af.mil 478-327-5345) |
5.0. Property
All units produced and ordered through this contract shall become the property of the U.S. Government upon the completion of the contract. All products developed under this contract shall be considered Government work and shall have no license encumbrances.
File details come from the government source that posted it. Updated .