STATEMENT OF WORK.docx

DOCX document 305 KB Posted

Attached to
Y1DA--FY23: NRM -Tier 1 (PROJ: 573-23-800) Install Boiler Plant Stairs
Solicitation number
36C24823R0019
Issued by

About this file

This document contains a Statement of Work and related Federal Contract Opportunity notice. The Statement of Work is for a design-build project to install boiler plant stairs at the Malcom Randall VA Medical Center in Gainesville, Florida. Services required include design, engineering, permitting, construction, and installation of a new staircase and platforms providing safe access to overhead equipment areas at the newly constructed boiler plant. Compliance with VA standards and codes is mandatory. The contractor must have experience designing and constructing industrial stairs and platforms. The estimated cost is between $500,000 to $1,000,000. The opportunity notice is for this project and specifies a response deadline of November 12, 2022. The solicitation will be set aside for Service-Disabled Veteran-Owned Small Businesses and issued on October 21, 2022 via SAM.gov. The Department of Veterans Affairs Veterans Health Administration VISN 8 is the contracting agency.

View the file

Other files

File Type Posted
36C24823R0019_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 11 21

REQUEST FOR PROPOSAL TO DESIGN BUILD

Project 573-23-800 Statement of Work Install Boiler Plant Stairs Malcom Randall VA Medical Center Gainesville, FL

(MRVAMC)

Main Hospital

Preface Acronyms

The following acronyms may be used in the body of this document.
811Sunshine 811 Utility Locator
http://www.sunshine811.com/
ACIAmerican Concrete Institute
ACMAsbestos Containing Materials
ADAAmericans with Disabilities Act of 1990
AEArchitect or Engineer
AHAActivity Hazard Analysis
AHUAir Handling Unit
APPAccident Prevention Plan
ASAPAs Soon As Possible
BAABuy American Act of 1933
BASBuilding Automation System
BIMBuilding Information Modeling
BOMABuilding Owners and Managers Association
https://www.boma.org/
CAConstruction Administration
CADComputer Aided Design
CAICapital Asset Inventory
CAMCapital Assets Management
CBOCCommunity Based Outpatient Clinic
CECost Estimator
CEOSHCenter for Engineering and Occupational Safety and Health
http://vaww.dushom.va.gov/ceosh.asp
CFRCode of Federal Regulations
https://www.gpo.gov/help/index.html#about_code_of_federal_regulations.htm
CFMOffice of Construction & Facilities Management
http://vaww.cfm.va.gov/
CICUCardiac Intensive Care Unit
CIHCertified Industrial Hygienist
CITPCertified Independent Third Party
CO or KOContracting Officer
CORContracting Officer’s Representative
CPCompetent Person (OSHA definition)
CPMConstruction Project Management
CPPContract Performance Period
CPSConstruction Period Services
CSIClinical Specific Initiative
DARDesign Analysis Review
DBDesign Build
DBTDesign Build Team (AE, GC & subcontractors)
DWGNative AutoCAD electronic design file
EDEmergency Department
EEElectrical Engineer
EIFSExterior Insulation and Finish System
EMSEnvironmental Management Service
FARFederal Acquisition Regulation
https://www.acquisition.gov/sites/default/files/current/far/pdf/FAR.pdf
FBCFlorida Building Code
FCAFacility Condition Assessment
FDOTFlorida Department of Transportation
http://fdot.gov/
FLState of Florida
FMSFacilities Management Service
FOIAFreedom of Information Act
FPFire Protection
FPEFire Protection Engineer
GCGeneral Contractor
GEMSGreen Environmental Management System
GISGeographic Information Systems
GRUGainesville Regional Utilities
http://www.gru.com/
HAZMATHazardous Materials
HVACHeating, Ventilation, and Air Conditioning
IAWIn Accordance With
IBCInternational Building Code
ICCInternational Code Council
ICRAInfection Control Risk Assessment
ICUIntensive Care Unit
IDIQIndefinite Delivery Indefinite Quantity
ISLMInterim Life Safety Measures
MEPMechanical Engineer
MICUMedical Intensive Care Unit
MOTMaintenance of Traffic
MRIMagnetic Resonance Imaging
MRVAMCMalcom Randall Veterans Affairs Medical Center
https://www.northflorida.va.gov/locations/gainesville.asp
NACNational Acquisition Center
NECNational Electrical Code (aka NFPA 70)
NEPANational Environmental Policy Act
https://ceq.doe.gov/
NFPANational Fire Protection Association
https://www.nfpa.org/
NFSGNorth Florida / South Georgia Veterans Health System
https://www.northflorida.va.gov/
NRMNon-Recurring Maintenance
NTPNotice to Proceed
OALOffice of Acquisition and Logistics
OITOffice of Information Technology
OROperating Room
OSHAOccupational Safety and Health Administration
https://www.osha.gov/
OSHA 10OSHA 10-hour safety certification
OSHA 30OSHA 30-hour safety certification
OTIOSHA Training Institute Education Centers
PDFPortable Document Format
PEProfessional Engineer
PGProgram Guide
PMProject Manager
PRCAPre-Construction Risk Assessment
PSDMPhysical Security Design Manual
PWSPerformance Work Statement
QAQuality Assurance
QCQuality Control
RARegistered Architect
RFIRequest For Information
RFPRequest For Proposal
SASupplemental Agreement
SATSimplified Acquisition Threshold
SDSSafety Data Sheet (aka “MSDS” Material Safety Data Sheet)
SICUSurgical Intensive Care Unit
SEPSSpace & Equipment Planning System
SOWStatement of Work (aka PWS)
SOTStatement of Task
TILTechnical Information Library
https://www.cfm.va.gov/til/
TJCThe Joint Commission (fka JCAHO or JCAH)
UFUniversity of Florida
VAUnited States Department of Veterans Affairs
VAARVeterans Administration Acquisition Regulation
https://www.va.gov/oal/library/vaar/index.asp
VAMCVeterans Affairs Medical Center
VCSVeterans Canteen Service
VHAVeterans Health Administration
VISNVeterans Integrated Service Networks (VISN08)

Common Industry Software

AutoCADComputer Aided Design software developed by Autodesk.
RevitBuilding Information Modeling software developed by Autodesk.
ArcGISGeographic Information System software developed by ESRI.
CoreconConstruction Project Management software by Corecon Technologies.
ProcoreConstruction Project Management software by Procore Technologies.
AcrobatPDF software developed by Adobe Software.

I. DEFINITIONS:

A. Design-Build (DB): as defined by the Department of Veterans Affairs (DVA) is the procurement by the Government, under one contract, with one firm (which may be a joint venture) for both design and construction services on a specific project.

B. Contracting Officer (CO): The services to be performed under this contract are subject to the general supervision, direction, control and approval of the Contracting Officer.

C. Project Manager (PM)/Contracting Officers Representative (COR): The Contracting Officer's representative responsible for administering contracts under the immediate direction of the Contracting Officer.

D. Design Build Contract: This term, as used herein, refers to the Contract(s) to perform the design and construction of the project.

E. Contractor: This term, as used herein, refers to the contractor under this contract.

F. A/E: This term, as used herein, refers to the Architect/Engineer firm(s) that are a part of the DB team, also referred to as DB A/E.

G. Design-Build Team: This term, as used herein, to refer to the entire Design-Build Team (Contractor, A/E and any sub-contractors) all inclusive.

H. Pre-Construction Risk Assessment (PRCA): Used to identify potential risks associated with the renovation, construction and some maintenance & repair activities and to develop risk mitigation strategies to minimize these risks. Prior to beginning work this assessment will be completed.

I. Interim Life Safety Measures (ILSM): Measures that are instituted to compensate for significant hazards posed by existing life safety (fire) code deficiencies or construction/renovation activities.

J. Request for Proposal (RFP): Is a solicitation made, often through a bidding process, by an agency or company interested in procurement of a commodity or service, to potential suppliers to submit proposals.

K. Certified Independent Third-Party Safety Professional (CITP): Certified Independent Third-Party Safety Professional for the review of the design documents for compliance with national and local codes, standards, federal and state regulations.

L. National Fire Protection Association (NFPA): The world's leading advocate of fire prevention and an authoritative source on public safety, NFPA develops, publishes, and disseminates codes and standards intended to minimize the possibility and effects of fire and other risks.

M. The Joint Commission (TJC): Formerly the Joint Commission on Accreditation of Healthcare Organizations (JCAHO) and previous to that the Joint Commission on Accreditation of Hospitals (JCAH). The Joint Commission provides evaluation, accreditation and disease-specific certification programs for healthcare facilities.

II. General Requirements Provide all Design-Build services including, but not limited to, labor, materials, tools, equipment, supervision, transportation necessary for design and construct the project described herein and other specific tasks as further defined by this Request for Proposal (RFP). All proposals are to provide both design and construction services for this project. The scope of work requires an onsite visit to fully assess the newly built boiler plant building’s spare boiler pad, the overhead platform above boilers, and the deaerator (DA) access upper-level platform. The requirements for this design-build project shall meet VA standards and design guides listed below in Section VIII Resouces.

The contractor or one of its sub-contractors shall be experienced in the design and construction of industrial stairs and platform connections. The contractor shall provide a minimum of three (3) past performance summaries of industrial stairs and platform connections design or renovation of similar scope and size. The Contractor will be required to retain an external Certified Independent Third-Party Safety Professional or Professional Credential (CITP) consultant for the design of the above project. The Certified Independent Third-Party Safety Professional or Professional Credential (CITP) consultant will review the design to verify compliance with the National Fire Protection Agency (NFPA) codes, State and local building codes, OSHA, and Life Safety Codes, etc.

1) Project Overview:

The Malcom Randall VA Medical Center has recently completed the construction of a new Boiler Plant. Currently, the new Boiler Plant has vertical ladders access to the Upper-Level Equipment Platform. The Upper-Level Equipment platform is over 28 feet high and creates safety risks of climbing the vertical ladders. Therefore creating a need for a set of stairs to be built to safely access the platforms.

Work associated with this project will include but not be limited to:

A. Staircase Design:

1. Design the fabrication and installation of a Staircase to the Plant Upper-Level Platform.

2. Perform a Structural assessment of the Design.

3. Provide COR with detailed drawings for review and approval.

B. Boiler’s Platform Design:

1. Design the fabrication and installation of a platform from the Staircase to Boiler’s Platform.

2. Perform a Structural assessment of the Design.

3. Provide COR with detailed drawings for review and approval.

C. DA Tank Platform Design:

1. Design the fabrication and installation of a platform from the DA Tank Platform to the Plant Upper-Level Platform.

2. Perform a Structural assessment of the Design.

3. Provide COR with detailed drawings for review and approval.

D. Staircase Installation:

1. Contractor provides tower frame, stair sections, and all other materials.

2. Project includes the installation of handrails.

3. Project includes painting of materials and erection of stair sections.

4. All piping and conduits in the way of staircase installation shall be relocated.

5. Provide a summary report of all findings and repairs to the COR.

E. Boiler’s Platform Installation:

1. Contractor provides all materials.

2. Project includes crosswalk connector from first stair tower to adjacent upper boiler platform.

3. All piping and conduit in the way of connecting the platforms shall be relocated.

4. Provide a summary report of all findings and repairs to the COR.

F. DA Tank Platform Installation:

1. Contractor provides all materials.

2. Project includes crosswalk connector from Upper-Level Equipment Platform to DA Upper-Level Platform.

3. All piping and conduits in the way of connecting the platforms shall be relocated.

4. Provide a summary report of all findings and repairs to the COR.

The touch-up and repair of damages created during the installation of the staircase and platforms will be an integral part of this project. All finishes will match the existing conditions as approved by the VA.

NOTE 1: The goal of this SOW is to ensure the quality of VA facilities while controlling the construction and operating costs. The D/B Team is responsible to develop a complete and accurate project that best meets the users' needs in compliance with referenced design and construction guidelines, standards and code requirements.

NOTE 2: The existing drawings on file at the VA may not be 100% accurate and may not exactly reflect the current conditions of the VA’s Boiler Plant. It is the responsibility of the D/B Team to review the existing facility record and prior project design drawings and verify the existing site conditions and prior design criteria.

NOTE 3: No separate staging, office or workshop area outside of the project limits will be provided. Access to the job site is permissible to drop off materials and project personnel. No long-term (more than necessary for drop-off/pick-up of personnel or materials) parking for contractor of subcontractor vehicles on the VA premises will be permitted. At the start of the project, the Glory Lot located behind the furthest garage (Independence) will be the site location for a dumpster and a maximum twenty foot long single storage container for storage of contractors material, including subcontractor materials.

Design-Build Team shall provide complete design documentation (Design Analysis Report, drawings and specifications) for the installation of staircase and platforms. The scope of work calls for an onsite visit to look at the existing space in the boiler plant. Drawings and specifications will be the primary reference to develop construction documents, drawings and specifications, for this design/build project and shall fully be used to the possible extent. With these provided drawings and specifications the contractor will create and be responsible for a full design package that will address, but will not be limited to, the following items:

· Provide Structural Design and Engineering and any other services required to complete the scope of work. The design and construction will need to adhere to VA specifications.

· Design-Build Team shall complete assessment and design of staircase and platforms to meet VA requirements (VA’s design manual) and life Safety 101.

· Design-Build Team shall install staircase and new platforms while existing boilers are in service and operating. If a need to have a boiler not operating to perform needed work, COR needs to be notified far in advance as possible (7 days).

· Mold abatement/remediation will be conducted by the contractor as required during the execution of the project. There are no significant known mold issues at this time.

· Design-Build Team is responsible for obtaining required permits from the VA COR for such work as welding or grinding.

· Design-Build Team will be responsible for all necessary inspections, tests, and certifications. Test results and certifications shall be provided to the VA.

· Provide updated conceptual design for VA review incorporating the results of the site investigations, criteria review and initial meeting.

· Construction activities are to be contained so as to not affect other areas of the Boiler Plant.

· Develop a construction plan that will permit the facility to remain in operation throughout construction.

· Design-Build Team is responsible to remove any obstruction to access and performing the required work (e.g. ceiling tiles, walls, equipment, etc.) and replace at its original condition. Any damage to existing materials by the contractor must be repaired or replaced at no cost to the VA.

· Design-Build Team shall take before and after pictures that clearly show the condition and cleanliness prior to and the following cleaning for operational areas returned to service during phased operations. This must be sent daily to the COR.

Special Notes:

· The Contractor will be required to retain an external Certified Independent Third-Party Safety Professional or Professional Credential (CITP) consultant for the design of the above project.

· The Certified Independent Third-Party Safety Professional or Professional Credential (CITP) consultant will review the design to verify compliance with the National Fire Protection Agency (NFPA) codes, State and local building codes, OSHA, and Life Safety Codes, etc.

· The detailed project design should begin with the above-mentioned intense on-site physical survey to validate and correct previous project drawings and specifications.

III. Scheduling, phasing, and Working Hours:

Performance Period Schedule Objectives – The anticipated completion of this project is 365 days after “Notice to Proceed” (NTP).

Hours of Work

· The classification of work hours is listed as follows:

Normal Business
7:00 am to 5:00 pm
After Hours
5:01 pm to 10:00 pm
Nights
10:01 pm to 6:59 am
Weekends
12:00 am Saturday to 11:59pm Sunday
Holidays
Federally recognized holidays

· Most of the work is intended to be performed After Hours and into Nights; however, lifting and deliveries should be conducted After Hours or on Weekends to minimize any impacts to the hospital operations or safety concerns.

· Non-scheduled Normal Business, Nights and Weekends/Holidays work will need to be approved by the COR ahead of time, with as much advance notice as is practicable.

· There may be times where SPS operational issues arise, and the work hours will need to shift to accommodate a resolution to the work complication.

· No work shall be scheduled during Federal Holidays.

IV. SAFETY REQUIREMENTS:

· All DB's construction personal are required to have completed an OSHA-approved 10-hour construction worker course prior to working on the site.

· The On-site general superintendent/supervisor is required to have completed an OSHA-approved 30-hour construction course prior to working on the site and an OSHA 30-hour CP on site whenever work is being performed.

· Every worker must provide the Contracting Officer a copy of current certificates identifying successful completion of the OSHA training prior to executing work for the VA.

· Contractor shall provide submittals for contract construction or renovation work which include the names, qualifications, and training dates for Contractor’s Competent Persons (CP), who has been designated to administer the site-specific safety program, as well as the CP for other activities as required by OSHA regulation 29 CFR 1926.32 (such as scaffolds, cranes, excavations, etc.).

· Contractor’s CP are required to implement and maintain effective safety programs that identify and control hazards that may cause injury or illness to VA patients, staff, visitors, and contractor employees. The VA CP does not take the place of Contractor’s CP nor acts on their behalf.

· The VA CP determines if Contractor is meeting VA standards and contractual requirements for safety and OSHA compliance. When these standards and contract requirements are not being met, the VA COR and/or CP will take immediate action to prevent injury, non-compliance, and/or property damage.

· The Contractor shall submit an Activity Hazard Analysis, and an Accident Prevention Plan as per FAR 52.236-13 prior to commencement of site activities. The Government shall have 21 calendar days to review the AHA and APP.

Patient Safety, Care, and Fundamental

· The Design-Build Team are reminded that this is a hospital environment, first and foremost and the Sterile Processing Service is an integral part of providing patient care to our veterans.

· There will be times that concerns over patient care will impact the construction schedule, this may limit access to certain areas or cause a change in the process, schedule or intended manner of performing the contractual work.

· The Design-Build Team is to remain flexible and plan ahead for potential patient care impacts.

V. Quality Assurance/Quality Control:

A. To reduce design errors and omissions, the Design-Build Team’s A/E shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.

B. Within 2 weeks after receipt of Notice to Proceed, the Design-Build Team A/E will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the Design-Build Team A/E member responsible for QA/QC.

1. Upon its completion each task shall be initialed and dated by the responsible Design-Build Team A/E member.

2. A 100% completed A/E QA/QC plan shall be submitted with the final construction document submission package.

VI. Design and Document requirements:

A. Design Requirements - Compliance with codes and standards.

1. Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials. See “Resources” below

2. See “Approved Construction documents”, below, for required inclusion of design review comments.

3. In the design of new building and alteration work under this contract, the Design-Build Team A/E shall consider all requirements (other than procedural requirements) of:

(1) Environmental and erosion control regulations; and

(2) Laws, of the State and local political division, which would apply to the building if it, were not to be constructed or altered by the U.S. Government. The Design-Build Team A/E shall consult with appropriate officials of the Federal, state, and political subdivision, and submit plans under the rules prescribed by those reviewing authorities. The Design-Build Team A/E and VA shall give due consideration to the recommendations of the referenced building officials. VA will also permit inspection by the officials described above during the construction period in accordance with the customary schedule of inspections in the locality of the building construction. Such officials shall provide VA with a copy of the schedule before construction begins or give reasonable notice of their intention to inspect before conducting an inspection.

4. The Design-Build Team A/E shall provide prompt, written notification to the Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering OR increasing the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer.

5. No action may be brought against the VA and no fine or penalty may be imposed for failure to carry out any of the previously described recommendations of Federal, state, or local officials. VA and its contractors, including A/E, shall not be required to pay any amount for any action taken by a state or political division of a state in carrying out functions described in this article, including reviewing plans, carrying out on-site inspections, issuing permits, and making recommendations.

6. The Design-Build Team A/E shall advise the Contracting Officer of any variances with the applicable Department of Labor, Occupational Safety and Health Standards, for occupancy requirements.

B. Design Review Meetings:

1. A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others).

2. Participants will include VA Staff and Design-Build Team A/E members as appropriate for the specific package to be reviewed and others. The Design-Build Team A/E members will each allow for (1) full day for each package design review meeting. Design-Build Team A/E management shall be present at each review meeting.

3. The DB team shall allow a minimum of fourteen (14) calendar days for each review cycle. A cycle includes:

a.The VA’s receipt of the design review submission package.
b.The review meeting.
c.DB teams’ receipt of comments from the VA, either electronically, by fax, or by hard copy delivery.

4. Coordination of the review meeting schedules will be the responsibility of the VA Project Manager/COR (for the VA) and the Design-Build Team A/E Project Manager (for the Design-Build Team A/E). See Quality Assurance/Quality Control.

C. Design Review Submissions:

1. The Design-Build Team A/E shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice and prevailing codes.

2. The documents may be divided into multiple review submission packages. The VA will review as many as six (6) package submissions (examples: demolition, architectural, structural, mechanical, electrical, plumbing etc.) to facilitate the start of construction.

3. All submission packages will be reviewed at Schematic Design (25%), Design Development (50%), Construction Documents (75%) and Final Documents (100%) completion stages. The (100%) review submission packages will incorporate the final review comments from the (75%) review. If any package is not complete for the required stage a post review may be required, the cost of which will be borne by the DB Team. The (100%) set of drawings will be the final set of drawings that will be used for construction and signed and sealed by professional engineer and registered architect of record.

4. Each review submission package shall include 2 hard copy sets (1 Full Size & 3 Half Size) and 1 PDF sets on CD-ROM. The package will include an index of drawings (by sheet number and title) and specifications (by section number and title) submitted. The packages will be distributed to the VA Project’s COR, the VA Contracting Officer (CO). and others as determined to be appropriate by the VA.

5. Upon Contractor review of the TIL Specifications and Design Guidelines associated with the Project Scope of Work, the Design-Build Team A/E shall be responsible to prepare and submit for Government review and acceptance a full set of specifications (2 hard copies, 2 electronic), specific to the project, from the Master Specifications located in the TIL. The Specifications shall be contractor modified to include VA Guidelines and Code requirements consistent with NFPA, IBC, FBC, FGI Guidelines for Design and Construction of Health Care Facilities, 2010 edition.

6. In addition to the Project Specific Specifications, the Contractor shall submit a binder of product cut sheets, MSDSs, and all required Contract submittals.

7. Contractor will be responsible to submit as-build CAD drawings at the end of the project reflecting the new floor layout changes to the VA Engineering office as part of the close out documents.

D. Electronic Media:

1. REVIT design files are to be submitted in the latest version or the version just prior to the latest version available at the time of award. AutoCAD drawing files are to be submitted in the latest version or the version available at the time of award representing each plan sheet created from the REVIT file.

2. Drawings should be submitted in the native AutoCAD format, layers unlocked, purged of superfluous data and bound to dependent XREF files. Also, submit all individual drawing sheets in PDF format.

3. CD Index to cross reference of digital BIM & CAD files to PDF drawing sheet numbers.

4. Design review submission specifications, final Construction Document submission specifications and other 8 1/2 by 11 formatted material will be executed in electronic format Microsoft Word with a pdf record file of submitted documents.

5. The referenced VA Guide specifications shall be available to the Design-Build Team A/E in electronic format in Microsoft Word, for use in preparing the construction specifications.

E. Professional Licensing:

1. The Design-Build Team A/E who prepares the construction documents shall be a professional architect or engineer licensed in the State of Florida.

2. The professional seal indicating such license by the state shall appear on the final construction documents. The architect whose seal is shown will be known as the Architect of Record. The Design-Build Team A/E shall certify compliance with the VA RFP and all applicable codes.

F. Approved Construction Documents:

1. The final construction document submission package will be submitted by the Design-Build Team A/E for approval by the VA after completion of the 75% review cycle for the final package to be submitted by the Design-Build Team A/E. The VA will have 14 calendar days to take approval action.

2. The final construction documents submission package will include a full set of construction documents including all disciplines/packages.

3. The final construction documents submission package will incorporate all VA supplied comments from the earlier 25%, 50% and 75% submission package reviews and will comply with the VA requirements.

4. If the final construction documents submission package is not complete a post submittal may be required, the cost of which will be borne by the Design-Build Team A/E.

5. The approved final construction documents include such details that the project can be constructed and will be used for construction of the project.

G. Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the Design-Build Team A/E. The construction drawings shall include a coordinated set of the following. (Reference Program Guide, PG-18-15, Volume C)

1. Structural drawings: including foundation plans, framing plans, schedules, and details, including general notes and all calculations.

2. Architectural drawings: including floor plans, building elevations, building sections, wall sections, reflected ceiling plans, stair details, toilet and bath details, door schedules and details, window schedules and details, room finish schedules, auto transport and other details.

3. Fire protection drawings: including floor and roof plans, riser diagrams, equipment schedules, and details, including general notes calculations and all related calculations.

4. Plumbing drawings: including floor and roof plans, riser diagrams equipment schedules, plumbing fixture schedules, and details, including general notes, and all related calculations.

5. HVAC drawings: including floor and roof plans, one-line flow diagrams, equipment schedules, and details, including general notes and all related calculations. Also provide sections for mechanical equipment rooms and sequence of operation for all HVAC equipment.

6. Electrical drawings: including site demolition plans, site, floor and roof plans (power, lighting, and other systems), one-line diagrams, panel schedules, equipment schedules, light fixture schedules calculations and details

7. Asbestos abatement: drawings including site demolition plans and floor plans indicating asbestos abatement method.

H. Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA requirements. The specification submitted for review shall include:

1. The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project;

2. Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e. shop drawings, product data, and samples as required by the VA documents; and

3. The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the project’s requirements.

VII. CONSTRUCTION PERIOD SERVICES

A. Pre-Construction Meeting The DB A/E, as part of the Design-Build Team A/E, shall participate in the pre-construction meeting with the VA and DB Contractor. The DB A/E shall be prepared to respond to the VA concerns, and shall provide overview of the design.

B. Site Visits & Inspections

1. During Construction Period Services, the DB A/E shall visit the job site as appropriate to the stage of construction to determine in general if the work is being performed in a manner indicating that the work, when completed, will be in accordance with the working drawings.

2. During the construction period the DB A/E shall make weekly visits to the project site when requested by the Contracting Officers Representative (COR). The Contracting Officers Representative (COR) may also request visits for special purposes. Only registered architects and engineers thoroughly familiar with the project may make these site visits. The Contracting Officers Representative (COR) has the prerogative to determine the professional discipline(s) required for any visit. The DB A/E shall observe the construction, advise the COR of any deviations or deficiencies or solutions to issues discussed. A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the Contracting Officers Representative (COR) within three workdays following the site visit date.

C. Disputes, Interpretations and Clarifications Upon written request from the VA, the DB Contractor shall furnish to the VA, with reasonable promptness, in writing or in the form of drawings, interpretations of the Contract Documents prepared by the DB A/E, if, in the opinion of the VA, such interpretations are necessary for the proper execution or progress of the Work.

D. Other submittals The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturer’s field reports, etc. as required by the VA RFP specifications, to the VA Project Manager/COR.

E. Project record drawings

The Design-Build Team A/E will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the RFP specifications. The project record drawings will be available for review by the VA Resident Engineer at all times.
F.Shop drawings and submittals
The DB A/E shall check government furnished and/or the contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA. The VA will have final approval authority. The DB A/E shall evaluate the submittals with reference to any companion submittals that constitute a system. When necessary, the DB A/E will request the Contractor to submit related components of a system before acting on a single component. Should this procedure be inappropriate, the DB A/E shall review all prior submittals for related components of the system before acting on a single component. The DB A/E may be required to hold joint reviews with the VA technical staff and /or the Contractor on complicated system submittals. The DB A/E shall notify the VA COR in writing of any and all deviations from the requirements of the construction documents that he has found in the submittals.

G. Inspections and Testing

1. DB A/E shall be present during one (1) Pre-Final inspection and one (1) Final inspection of Work and shall generate Punch List and forward the list to the VA with explanations of found deficiencies and/or omissions in work, and recommended correctives.

2. DB A/E shall review and approve or take other appropriate action on test reports and Punch List items to be completed or corrected. DB A/E shall approve or disapprove test reports and forward findings to the VA for final disposition. DB Team shall forward approved inspection and testing document or lists to the VA for final disposition.

H. Review of Documents and Work Acceptance On closeout of Construction Period Services, the Design-Build Team A/E shall certify that the Contract Documents requirements and intent have been satisfied, workmanship is Professional and at an acceptable level, submittals and other DB supplied Documents as required in Contract Documents are in order and stamped approved. However, the Government’s final acceptance of the Work is at the discretion of the COR and shall be authorized in writing by the VA Contracting Officer only.

I. Project Close-Out The Design-Build Team A/E shall comply with the requirements in the “General Conditions”, Section 01001, and “General Requirements”, Section 01010, for submission of final RFP as built drawings, manuals, and other documents as noted. Required as built drawings and specifications will be submitted in the same format required for the construction documents.

J. AS BUILT

The Design-Build Team A/E shall prepare and submit AS-BUILT drawings as developed from the Construction activities re-lined as-built. Drawings shall be submitted in REVIT 2019 (or earlier) and AUTOCAD format and shall reflect the actual as-built conditions. Stamp drawings in large red bold letters “AS-BUILT” in the lower right-hand corner of all drawings. Drawings shall be submitted on full size consistent with previous requirements herein.

VIII. Resources:

All designs shall comply with applicable sections of VA standards and publications, and all references therein. Ensure that construction documents comply with the latest edition of these VA construction and design standards. VA standards can be found on the World Wide Web at http://www.cfm.va.gov/TIL/ (see below for example page) VA publications and standards shall include but shall not be limited to the following:

1. Office of Construction & Facilities Management Site Map:

http://www.cfm.va.gov/sitemap.asp

2. The Technical Information Library (TIL): http://www.cfm.va.gov/TIL/

a) Master Construction Specifications Index (PG-18-1)

b) Design and Construction Procedures (PG-18-3)

c) VA Standard Details and CAD Standards (PG-18-4)

d) Equipment Guide List (PG-18-5)

e) Equipment Inspection Manual (Program Guide 7610.2)

f) Equipment Reference Manual (PG-18-6)

g) Space Planning Criteria (PG-18-9)

h) Design Manuals (by discipline) (PG-18-10)

i) Design Guides (graphical, by function) (PG-18-12)

j) Barrier Free Design Guide (PG-18-13)

k) Room Finishes, Door and Hardware Schedules (PG-18-14)

l) Minimum Requirements for A/E Submissions (PG-18-15)

m) Environmental Planning Guidance (PG-18-17)

n) HVAC Design Manual for Hospitals Amendment B

o) Lighting Study

p) Design Alerts

q) Quality Alerts

r) VA Signage Design Guide

s) Fire Protection Design Manual – Latest Edition

t) Cost Estimating

u) Physical Security Design Manuals for VA Facilities – Mission Critical Facilities (VA Handbook 0730)

v) Information Security Handbook VA 6500

w) Energy Reduction Manual (First Draft) 3.TIL - Master Construction Specifications: http://www.cfm.va.gov/til/spec.asp

4. Department of Veterans Affair Utilities Design Manual.

I. Office of Construction & Facilities Management: http://www.cfm.va.gov/index.asp

1. VA Office of Facilities Management citations of the AIA design standards found on the world wide web at http://cfm.va.gov.TIL/

2. VA Office of Health and Safety (OHS): http://www1.va.gov/vasafety/

3. Construction Infection Control Risk Assessment Memorandum

J. Other design and construction standards and publications that shall be applied to this work includes, but are not limited to:

1. American Society of Heating, Refrigerating and Air-Conditioning Engineers Manual (ASHRAE)

2. National Fire Protection Association (NFPA) Codes & Standards - www.nfpa.org

3. OSHA Rules and Regulations

4. International Building Code (ICC) latest edition

5. Life Safety Code (NFPA 101) latest edition

6. The Joint Commission (TJC) Accreditation manual (latest edition)

7. Sustainable Design Requirements (01 81 11)

8. Construction Waste Management (01 74 19) K. Applicable sections of the VA Master Construction Specifications will be prepared by the Architect/Engineer, including all the necessary adaptations.

L. Particular attention is called to CD4, Symbol Identification of Contract Drawings.

M. Equipment symbols shall be in accordance with PG-18-6, Equipment Reference Manual (previously List of Equipment Symbols, H-08-6).

N. Standard Drawing Details, in accordance with PG-18-4, shall be utilized to the greatest extent practicable.

O. Cost estimates shall be developed in strict conformance with VA’s Manual for Preparation of Cost Estimates & Related Documents for VA Facilities (March 8, 2011). http://www.cfm.va.gov/til/dManual/dmCost.pdf P. Guidelines for Design and Construction of Health Care Facilities, Latest Edition, published by The Facilities Guidelines Institute (FGI). http://www.fgiguidelines.org/ Q. Physical Security Standard, compliance with Medical Center Policy 138-3 and VHA Handbook 0730/2 dated May 27, 2010 “Space Key Control”.

R. Plumbing System Design & Water Treatment/Design to prevent Legionnaires. VA Plumbing Design Manual and VHA Directive 2008-010, prevention of legionella disease, and VHA directive 2009-009, domestic hot water temperature limits for legionella prevention and scald control.

https://www.cfm.va.gov/til/ example Figure 1. This VA site is commonly referred to as “the TIL”.