This document is a Statement of Work (SOW) for the fabrication and testing of 1-1/2 inch and 2-inch ID hose assemblies. The hose assemblies must meet specific color, material, dimension, temperature rating, fitting, and performance criteria as outlined in the Ordering Data Sheets. The contractor is required to conduct hydrostatic testing of the hose assemblies and provide test reports to the government. The hose assemblies must be cleaned, packaged, and delivered in a manner that prevents damage. The contractor must also provide a Certificate of Compliance to confirm all design, performance, drawing, and test specifications have been met.
The related federal contract opportunity is a solicitation (N4523A-24-Q-4074) for the supply of 1-1/2 inch and 2-inch ID hose assemblies. The hose assemblies must meet specific requirements for outer cover, bore, pressure rating, temperature rating, coupling material and style, and length. The solicitation requires a Certificate of Compliance and hydrostatic testing to manufacturer's specifications. The contracting agency is the Department of the Navy Naval Supply Systems Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 4151-7990 ODS.docx | DOCX document | |
| 4163-7040 ODS.docx | DOCX document | |
| 4151-7990 CDRL A001 Certificate of Compliance.pdf | ||
| 4151-7990 CDRL A002 Data Item Description TIR.pdf | ||
| Solicitation N4523A-24-Q-4074.pdf | ||
| 4151-7990 CDRL A002 Test Inspection Report.pdf | ||
| 4151-7991 ODS.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3DEC2020
STATEMENT OF WORK (SOW)
FOR
1-1/2 INCH & 2-INCH ID HOSE ASSEMBLIES
Prepared by
PUGET SOUND NAVAL SHIPYARD &
INTERMEDIATE MAINTENANCE FACILITY
CONTENTS
Section/Paragraph
1 Scope
1.1 Background
2 Requirements
2.1 General Requirements
2.2 Technical Objectives and Goals
2.2.1 Design and Fabrication, and Test
2.2.1.1 Design and Fabrication
2.2.1.2 Test
2.2.2 Cleanliness Requirements
2.2.3 Preparation for Delivery
2.3 Certificate of Compliance(COC)
Scope. This Statement of Work (SOW) defines the effort required for the fabrication and testing of 1-1/2 INCH & 2-INCH ID HOSE ASSEMBLIES.
1.1 Background. The 1-1/2 INCH & 2-INCH ID HOSE ASSEMBLIES are required for support of government work.
2 Requirements.
2.1 General Requirements. The 1-1/2 INCH & 2-INCH ID HOSE ASSEMBLIES in the technical Ordering Data Sheets (ODS) shall be manufactured in accordance with the color, material type, dimensions, temperature ratings, fitting specifications and performance criteria specified in the Ordering Data Sheets of this contract and testing requirements of paragraph 2.2.1.2 below.
2.2 Technical Objectives and Goals.
2.2.1 Design and Fabrication, and Test.
2.2.1.1 Design and Fabrication. The contractor shall fabricate 1-1/2 INCH & 2-INCH ID HOSE ASSEMBLIES to meet all color, material type, dimensions, temperature ratings, fitting specifications and performance criteria of Saint Gobain Chemflour Hose (WTLCT) as specified in the Ordering Data Sheets.
2.2.1.2 Test. The tests may be conducted at the contractor's facilities or at an independent laboratory or commercial testing facility. The contractor shall conduct hydrostatic testing of 1-1/2 INCH & 2-INCH ID HOSE ASSEMBLIES to manufacturer’s (Saint-Gobain Performance Plastic’s) specifications and provide the government with the Test Inspection/Report Data for each length of hose procured under this contract.
2.2.1.3 Cleanliness Requirements. The contractor shall maintain cleanliness of hose assemblies per the following:
Parts shall be cleaned by any process or combination of processes which will accomplish thorough cleaning without damage to the part(s). Surfaces shall be examined visually to determine freedom from dirt, corrosion, oil, flux, grease or foreign residue. Preservatives shall not be used on part(s) which are vulnerable to damage by contact preservatives.
Mercury containing compounds shall not be intentionally added or come into direct contact with hose assemblies.
The inner tube surface area shall be visually examined to the maximum extent possible from each end.
2.2.2 Preparation for Delivery. The contractor shall package the hose assemblies per the following:
Transfer hoses must be carefully handled and protected to prevent damage. Hoses must not be sharply bent, kinked, twisted, stretched, dropped, scraped, or otherwise abused. Hoses and hose end fittings must be adequately supported during handling and rigging so that the weight does not bend the hose where it enters the end fittings.
Units to be shipped must be free of loose particles, dirt, grease, oil, etc. with ends capped to prevent dirt from entering. The hose assemblies shall be packaged per commercial standard in a manner that does not violate the minimum bend radius specified by the manufacturer. The hose assemblies shall be packaged in a manner that prevents the hose assemblies from being damaged during shipment and prevents the hose assemblies from being wet and exposed to the elements.
2.3 Certificate of Compliance (COC). The contractor shall provide a COC to confirm all design, performance, drawing and test specifications required by this contract have been met.