Statement of Work DDHU Rip Saw.pdf

PDF 139 KB Posted

Attached to
Straight Line Rip Saw for DLA Distribution Hill AFB, Utah (DDHU)
Solicitation number
SP3300-25-Q-0133
Issued by

About this file

This Statement of Work (SOW) details the procurement of a Straight-Line Rip Saw for the Defense Logistics Agency (DLA) Distribution at Hill Air Force Base in Utah. The solicitation requires a contractor to provide, deliver, and install one new Straight-Line Rip Saw equivalent to or greater than the Diehl Model SL 65-56, with specific technical requirements including 480-volt electrical operation, a 20 HP belt-driven spindle, 3 HP feed drive motor, and safety features like anti-kickback fingers. The contractor must also provide one 8-hour training session on the saw's safe operation and deliver complete operator, parts, and service manuals.

The document outlines three primary contractor tasks: fabricating and delivering the saw (which can connect to existing electrical and ventilation systems), installation and commissioning by vendor technicians, and conducting on-site training. The shipping location is the Defense Distribution Hill Air Force Base in Hill AFB, Utah, with the point of contact being Jeff Zeigler. The warranty must be the manufacturer's standard but no less than one year for parts and labor, and the exterior color will be the manufacturer's standard. Final acceptance will be performed by personnel at the receiving location.

View the file

Other files

File Type Posted
RFQ SP3300-25-Q-0133.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

Straight-Line Rip Saw

For

DLA Distribution Hill AFB, Utah (DDHU)

1. Background:

a. Requiring Organization

DLA Distribution Hill Air Force Base, Utah

b. History

A new machine is required to keep up with the current mission.

c. Purpose of the Statement of Work (SOW):

The purpose of this SOW is to purchase a new Straight-Line Rip Saw for DDHU

2. Scope of Work to be Performed by Contractor:

The contractor shall provide all necessary labor and material to construct, deliver and install one

(1) new Straight-Line Rip Saw at DDHU. All equipment furnished shall be new from the manufacturer’s most current production and meet current industry standards and conform to the best quality of materials and workmanship. Accessories not specifically mentioned herein, but necessary to furnish complete systems ready for use, shall also be included and named. All transportation/shipping shall be provided by the contractor.

Provide one (1) 8-hour period of training instruction on the safe operation of the installed saw.

Training to be conducted at one location to be identified by personnel at the receiving location after completion of installation and testing of the safe operation of the saw.

3. Salient Characteristics:

- Arranged for 480 volts, 3 phase, 60 cycle electrical operation

- Fitted with isolation transformer/line reactor

- 20 HP belt driven spindle with automatic “dead-man” style brake

- 3HP feed drive motor w/ AC inverter for 70-200 FPM variable feed speed

- The SL65-56 has 56” of throat capacity

- The SL65-56 has 30” of table support to the left of the blade

- Lower anti-kickback fingers mounted in the worktable at the infeed w/ automatic elevation control by contact with lower fingers

- 3/8” minimum, 4 ¼” maximum thickness capacity

- multi-vee chain, chain-race, and drive cam

- Precision spindle, spindle housing, bearings, and saw collars

- Electro-pneumatic feed chain lubrication system

- NEMA TYPE 12, Operator control panel and fascia

- Heavy duty pressure beam, pressure rolls/brackets, and springs

- Infeed safety features w/ cam-controlled claw type upper anti-kickback fingers, lower infeed anti-kickback fingers, LH & RH side pressure beam and outfeed guards

- One (1) 18” diameter, 24 tooth, carbide tipped saw blade

The Straight Line Rip Saw must be equivalent to or greater than the Manufacturer Diehl, Model SL 65-56.

Exterior color – Manufacturer’s standard.

Warranty Coverage – Warranty coverage shall be manufacturer’s standard warranty but not less than one-year parts and labor.

Operator, Parts and Service Manual(s) and Training – The contractor shall provide with delivery, one (1) complete set of manuals with each machine.

4. Definitions of Terms and Abbreviations:

N/A

5. Description of Contractor’s Tasks:

Task 1: Fabricate and deliver one straight-line rip saw. Saw to be connected to existing electrical connections, no requirement for additional electrical work is required. Saw to be connected to existing ventilation system, no additional ventilation system modification is required.

Task 2: Installation and commissioning by vendor technicians.

Task 3: Provide one 8-hour period of training instruction on the safe operation of the installed saw. Training to be conducted on-site on the day of installation.

6. Certification and Acceptance:

Final acceptance of the stretch wrap machines with scales will be performed by personnel at the receiving location.

7. Project Management Approach:

N/A

8. Performance and/or Delivery Schedule:

The contractor shall coordinate the delivery to the locations listed below in the quantities noted with the POC listed below.

9. Shipping Locations

Defense Logistics Agency

Defense Distribution Hill Air Force Base UT

5737 WARDLEIGH RD BLDG 849

HILL AFB, UT 84056

POC: Jeff Zeigler @ 385-460-5792