Crane and Rigging Services – USCGC VENTUROUS Incline
Location – Work to be performed at USCGC Venturous’s homeport, ST Petersburg FL.
Performance period – March 28 – 12:00 am to 4:00 pm.
March 29 – 07:30 am to approximately 3:00 pm.
Tasking –
1) March 28 (12:00 – 4:00) Provide crane and rigging services as required to load weights up to 5,000 lbs each (CG PROVIDED), on board USCGC VENTUROUS. Crane must be capable of lifting weights at a distance of approximately 60 feet from the edge of the pier
2) March 29 (07:30 – 3:00) Provide crane and rigging services to assist cutter with removal of gangway and other miscellaneous items as required. Provide crane and rigging services to move weights, loaded onto cutter previously, across the deck of the cutter, minimum of 9 weight movements. Provide crane and rigging services to remove weights from the vessel after the cross-deck movements. Provide crane and rigging services to assist the cutter with installation of gangway and other miscellaneous items as requested.
3) March 30 (07:30 – 3:00) Optional day should weather conditions prevent satisfactory testing conditions on March 29.