Statement of Work - Cotton module feeder assembly.pdf
PDF 94 KB Posted
- Attached to
- Assembly of Cotton Module Feeder
- Solicitation number
- 12405B24Q0186
About this file
This document is a Statement of Work (SOW) for the assembly and installation of a 1.5 bed cotton module feeder for the Cotton Ginning Research Unit located in Stoneville, Mississippi. The SOW specifies that the vendor will only be responsible for the mechanical installation, not the electrical connection or ductwork fabrication. The unit is previously purchased and requires assembly and placement on-site.
The related federal contract opportunity is a Request for Quote (RFQ) for the Assembly of Cotton Module Feeder, solicitation number 12405B24Q0186. This is a small business set-aside with a NAICS code of 811310. The government anticipates awarding a firm-fixed price contract to the responsible offeror whose quote conforms to the RFQ and specifications using a best value tradeoff evaluation considering technical acceptance, past performance, and price. Quotes are due by April 16, 2024 at 4:00 pm Central Standard Time, with questions due by April 13, 2024 at 3:00 pm.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Government Furnished Equipment - Cotton module feeder assembly.pdf | ||
| Service Provisions 1128014.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Title: Cotton module feeder assembly
S.O.W.:
The Cotton Ginning Research Unit is in need of the assembly and installation of a 1.5 bed cotton module feeder for the large-scale cotton gin located at 111 Experiment Station Rd., Stoneville, MS 38756
1) Mechanical installation only, no electrical connection or ductwork fabrication and installation
2) Cotton Ginning Research Unit is in possession of a previously purchased new 1.5 bed module feeder which requires mechanical assembly and installation.
3) Module feeder roller bed, disbursing cylinders, and other enclosures to be assembled and placed on site in empty module feeder shed.
4) Electrical connection and ductwork fabrication will be handled separately by Cotton Ginning Research Unit personnel.