This is a Statement of Work for the installation and upgrade of overhead patient ceiling lifts at the Michael E. DeBakey VA Medical Center in Houston, Texas. The Department of Veterans Affairs intends to award a sole source firm fixed price contract to Premier Medical Distributers LLC, an SDVOSB located in Myrtle Beach, South Carolina, for the procurement and installation of Guldmann GH3+ patient lift systems. The work involves site preparation and installation of multiple lift units across various clinical departments, including the Proctology Clinic (1 unit), Radiology (5 units), GI Clinic (6 units), and SCI Unit PT Gym (1 unit), among others. The lifts specified are 605-pound safe working load systems with WiFi capability, integrated control and monitoring modules, hanger bars, rails, trolleys, and hardware, configured for either 3-meter by 3-meter or 5-meter by 5-meter spaces depending on departmental requirements.
The procurement is classified under NAICS code 339113 (Surgical and Medical Instrument Manufacturing) with a small business size standard of 800 employees and is assigned FSC/PSC code 6515. The sole source justification is based on market research findings that only one responsible SDVOSB source can provide the required upgrades, authorized under the Veterans Benefits Act of 2003 and FAR 19.1406. This notice constitutes both the Notice of Intent to Sole Source and the synopsis of proposed action, serving as the primary notification for this non-competitive acquisition.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626Q0974.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Installation and Site Prep of Overhead (Ceiling) Patient Lifts Michael E. DeBakey VA Medical Center Houston, TX
Scope of Work:
The contractor shall provide all labor, materials, engineering design, equipment, tools, supervision, and transportation necessary to design, supply, and install overhead ceiling-mounted patient lift systems in nineteen (19) designated clinical spaces at the Michael E. DeBakey VA Medical Center (MEDVAMC), Houston, Texas.
The installation shall support the facility’s Safe Patient Handling and Mobility (SPHM) Program, which requires mechanical lift equipment to be available to caregivers when performing patient handling tasks involving lifting, transferring, repositioning, and mobility assistance in accordance with VHA Directive 1611.
The contractor shall install fixed ceiling-mounted patient lift systems designed to provide safe patient transfers and repositioning capability throughout the full usable area of each designated room.
The contractor shall provide all personnel necessary to complete installation. All contractor employees shall be properly trained, qualified, and licensed (where applicable) to install patient lifting systems.
All installed lift systems must have a minimum lifting capacity of 605 pounds.
| DESCRIPTION |
| QTY |
GH3+ 605lb SWL, wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware - 3mx3m or smaller.
103633 Proctology Clinic.
GH3+ 605lb SWL, wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware - 3mx3m or smaller.
103203 Radiology.
GH3+ 605lb SWL, wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware - 3mx3m or smaller.
102371 GI Clinic.
GH3+ 605lb SWL,duynaic lift system, integrated scale wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware- 5mx5m or smaller.
103568 SCI Unit PT Gym.
GH3+ 605lb SWL, wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware - 4mx3m.
Cancer Clinic.
GH3+ 605lb SWL, wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware - 4mx3m.
5H Surgery Center
GH3+ 605lb SWL, wifi capable, CLM and service modules, hanger bar, rails, trolleys, hardware - 4mx3m.
Dental Clinic.
| GULDMANN CERTIFIED INSTALLATION. Non Union Labor [and hardware] to install lifts in a typical 4m x 3m room. 1 room per day, [2] mobilization(s) of installation team. Electrical work, existing structure demo, modification, or reinstallation including but not limited to ceilings, walls, tile, patching, painting, acoustic caulking, asbestos abatement, smoke/fire wall repair, fireproofing reapplication, sprinkler relocation and door header modification is outside the scope of work for Guldmann installers and Guldmann is not licensed for performing such work, nor is Guldmann responsible for hiring specific contractors/trades to perform such work. ICRA up to level II provided; additional is responsibility of facility. Guldmann will perform light cleaning of the area but returning room to original condition is outside of scope of work for Guldmann installers. If an Above Ceiling Work Permit is required, facility must provide. |
| 18 |
| GULDMANN CERTIFIED INSTALLATION. Non Union Labor [and hardware] to install lifts in a typical 4m x 3m room. 1 room per day, [2] mobilization(s) of installation team. Electrical work, existing structure demo, modification, or reinstallation including but not limited to ceilings, walls, tile, patching, painting, acoustic caulking, asbestos abatement, smoke/fire wall repair, fireproofing reapplication, sprinkler relocation and door header modification is outside the scope of work for Guldmann installers and Guldmann is not licensed for performing such work, nor is Guldmann responsible for hiring specific contractors/trades to perform such work. ICRA up to level II provided; additional is responsibility of facility. Guldmann will perform light cleaning of the area but returning room to original condition is outside of scope of work for Guldmann installers. If an Above Ceiling Work Permit is required, facility must provide. 103568 SCI Unit PT Gym. |
| 1 |
| Third party licensed structural engineered STAMPED drawings |
| 1 |
System Design Requirements:
The ceiling-lift system shall be designed as a room-covering X-Y track system to maximize the usable lift coverage within each room.
The lift system must:
• Allow smooth horizontal and vertical patient movement
• Provide adequate lifting height for safe transfers from beds, chairs, wheelchairs, and stretchers
• Operate with smooth motor movement without jerky starts or stops
• Allow patient lifting from floor level
Track systems shall be self-supporting from the building structure, either through ceiling suspension or post-mounted support structures when required due to existing building conditions.
Existing building infrastructure such as utility systems, hangers, or structural supports not designed for lift loads shall not be used to support the lift system.
All structural support components must connect directly to the building’s structural elements.
Technical Requirements:
All mobile floor lifts supplied under this contract shall meet the following minimum specifications:
1. Structural Engineering
a. All lift installations shall be supported by structural designs stamped by a licensed structural engineer.
b. The contractor shall provide site-specific installation drawings identifying:
• Track locations
• Structural attachment points
• Support structure above ceiling
• Methods of attachment to building structure
3. Existing door frames shall not be cut or modified unless approved through engineering documentation certified by a licensed structural engineer and accepted by the VA.
2. Weight Testing and Certification
a. Each installed lift system shall undergo weight testing prior to acceptance.
b. Weight tests shall be performed using 150% of the rated load capacity.
c. Testing shall be witnessed by the VA Contracting Officer Representative (COR).
d. Written testing reports shall be provided and shall include:
• Test weight applied
• Deflection measurements
• Structural performance verification
e. Final equipment certification must be provided prior to system acceptance.
3. Ceiling Lift System Performance Requirements Installed ceiling lift equipment shall meet the following minimum specifications.
Contractor shall provide the following:
1) Lift Motor Requirements
• Minimum lifting capacity of 605lbs.
• Soft start and soft stop motor operation
• Emergency stop functionality
• Emergency lowering capability
• Visual low-battery indicator
• Over-speed safety governor
• Maximum sound level not exceeding 52 dB(A)
2) Track System Requirements
• Anodized aluminum track construction to prevent corrosion and surface degradation
• Track systems designed to allow maximum patient coverage within the room
• Track end stops installed and secured at all track ends
• Rail systems must support un-spliced spans consistent with manufacturer specifications
3) Monitoring and Data Capability
The ceiling lift system must support facility-wide lift utilization monitoring.
Lift motors must be capable of communicating with a Wi-Fi enabled monitoring system that tracks:
· Lift usage frequency
· Patient weight data
· Service and maintenance alerts
· Equipment utilization statistics
This capability supports monitoring of mechanical lift use for patient safety and staff injury prevention programs.
4) Installation Requirements The contractor shall:
· Provide a detailed installation schedule and project timeline
· Coordinate installation activities with MEDVAMC Engineering and clinical leadership
· Minimize disruption to patient care operations
Installation shall include:
• Dust containment measures
• Tacky mats at construction entrances
• Cleaning and restoration of all work areas
All rooms shall be returned to original condition following installation.
Any damage to ceilings, walls, floors, or fixtures shall be repaired by the contractor.
5) Infrastructure Protection
Contractor installation activities shall not interfere with:
• Fire sprinkler systems
• Lighting fixtures
• HVAC systems
• Medical gas systems
• Permanent building infrastructure
Contractor shall not breach fire barriers or fire walls without prior approval from VA Engineering and Safety personnel.
All penetrations must be properly sealed to maintain fire safety integrity.
Electrical installations must comply with:
• National Electrical Code (NEC)
• NFPA 70
• NFPA 99
6) Infection Control Requirements Contractor shall follow all MEDVAMC Infection Control Risk Assessment (ICRA) requirements during installation.
The contractor must:
• Implement dust containment measures
• Protect patient care areas from contamination
• Maintain safe work environments for patients, visitors, and staff All work areas shall be cleaned and disinfected upon completion.
4. Training Requirements Patient Care Staff Training Training must include:
• Proper operation of ceiling lifts
• Safe patient transfer techniques
• Sling compatibility and usage
• Emergency procedures Initial training shall be completed within two weeks of installation completion and must include staff across multiple shifts.
Follow-up training shall be provided at:
• One month post-installation
• One year post-installation Biomedical / Engineering Training The contractor shall provide technical training for facility maintenance personnel including:
• Preventive maintenance procedures
• Equipment troubleshooting
• Service requirements The contractor shall provide any specialized tools required for maintenance
5. Documentation Requirements
The contractor shall provide:
• Operator manuals
• Maintenance manuals
• Installation drawings
• Model and serial numbers for installed equipment
• Preventive maintenance schedules
• Warranty documentation
All documentation shall be provided in electronic format.
6. Contractor Conduct Requirements
Contractor personnel shall:
• Wear visible company identification at all times
• Follow all MEDVAMC safety policies
• Conduct work in a manner that does not interfere with hospital operations All contractor personnel must possess OSHA 10-hour construction safety training certification.
· Electronic copies of operator manuals and maintenance manuals
· Equipment model and serial number documentation
· Preventative maintenance schedules
· Warranty documentation
7. Security Requirements:
All personnel employed by the contractor in the performance of this contract, or any representative of the contractor entering the government facility, shall abide by all security regulations of the facility. Contractor/installers have to sign in with the VA Police Department prior to starting to work.
image1.jpeg
File details come from the government source that posted it. Updated .