About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to remove and replace obsolete glass panels from a greenhouse envelope and exterior/interior walls of Building 41 at the USDA, ARS, SEA, Crop Genetics and Breeding Research Unit (CGBRU) location in Tifton, Georgia. The contractor must replace the glass panels with compatible 8mm twin wall polycarbonate panels covering approximately 2,697 square feet. The SOW outlines the base bid requirements, contractor responsibilities, material/submittal details, demolition procedures, project schedule, and inspection criteria.

The related federal contract opportunity, Solicitation Number 12405B24Q0307, is a Request for Quotation (RFQ) under a Total Small Business Set-Aside for the Greenhouse 41 Glass Replacement project. The NAICS code is 238150 - Glass and Glazing Contractors with a small business size standard of $19.0M. Bidders are encouraged to conduct a site visit, submit questions by July 25, 2024, and submit quotations by August 1, 2024. Pricing shall be submitted as a Firm Fixed-Price quotation detailing material, labor, and other costs.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

USDA Building #41 Replace Polycarbonate Panels on Greenhouse Envelope and Exterior & Interior Walls Asset ID # 660200B0041 136 Tobacco Rd. Tifton, Ga 31793

USDA-ARS

Prepared by:

Lee Willis, Facilities Maintenance Mechanic 3 Jan 2024

Reviewed by:

Dr. Corley Holbrooke Location Coordinator 9 Jan 2024

Pictures

Statement of Work: Remove and replace obsolete glass panels from GH envelope as well as all exterior/ interior walls and replace with compatible polycarbonate panels in all areas of B41. All polycarbonate panels are to be compatible in thickness and dimensions with the existing glass panels so that no modifications to the greenhouse structure is required. This building has approximately 2,697 sq ft.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be obtained through:

https://www.sam.gov

Safety: The contractor will submit a Site Safety Specific Plan/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 7 days of contract award. The Plan shall include phone numbers and maps to the local Dr. Office and nearest Hospital.

All employees of the general contractor or subcontractors shall have the 10- hour OSHA certified Construction Safety course and/or other relevant competency training. Supervisors shall have completed the 30-hour OSHA training.

Base Bid: Provide all equipment, labor, and materials necessary (including dumpster/container if applicable)

· Provide all quotes as turnkey completed work,

· Work shall be accomplished in accordance with all local, state and federal codes and regulations,

· Work shall be accomplished by certified technicians,

· Remove obsolete glass panels from GH roof and dispose of them safely and completely leaving no pieces behind in or around the greenhouse.

· Provide and install 8mm twin wall polycarbonate siding on entire building envelope and interior walls of 3 bays of greenhouse,

· Remove any existent sealant from GH structure associated with existing glass panels and replace with new sealant as required when installing new 8mm polycarbonate panels.

· Provide and install new replacement trim, flashing and extrusions to complete installation,

· Provide new mounting hardware necessary, All proposals shall be in unlocked MS Word format and all cost proposals shall be detailed and presented in unlocked MS Excel format with formulas working.

Contractor Responsibility:

1. Contractor will verify all dimensions and site conditions prior to beginning work.

2. Contractor will perform the work as listed in the above outlined Base Bid.

3. Contractor shall keep work area clean daily and take measures to control debris while work is being performed.

4. Contractor is required to manage the project and consult with the Government prior to beginning all work phases. And, to work in a manner that minimizes the impact of the work on Government operations, research, and functions.

5. All work must be performed in such a manner as to not adversely affect daily operations of the facility, its workers, and the onsite facility operations.

6. Contractor must always have a Site Supervisor on the job while working on this project.

7. Contractor will provide their own restroom facility and dumpster.

8. Contractor will remove all demolished material and debris from the worksite and dispose off- site.

9. The Contractor shall confine all operations on Government premises to areas authorized or approved by the Contracting Specialist/Officer or Representative (CO/COR).

10. Employees of general contractor and subcontractors shall comply with ARS security management program, obtain permission from the CO/COR, be identified by project and employer by wearing contractor issued identification badges (if required) at all times on ARS property, and restricted from unauthorized access.

11. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

Material / Submittals:

The Contractor shall supply all materials necessary to successfully complete the project and deliver a functioning system as required. Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project shall be submitted to the Contract Specialist/Officer (CO) and Contracting Officer Representative (COR) as noted in this document. Electronic submittals are acceptable otherwise three written submittals are required.

Demolition Procedure:

1. Contractor will verify all dimensions and site conditions prior to beginning work.

2. Contractor will schedule the work between working hours as listed below.

3. Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor.

4. Contractor will verify all dimensions and site conditions prior to beginning work.

5. Contractor will schedule the work between working hours as listed below.

6. Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor.

7. The contractor shall always be responsible for protecting their work and ensuring the safety of their crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.

8. All items demolished shall become property of the Contractor and be removed by Contractor from ARS property.

9. Contractor shall follow all ARS EMS disposal criteria. Recyclable materials shall be recycled, and the savings shall be included in the contractor’s quote, therefore passed on to the government.

10. Contractor shall be responsible for providing disposal records where applicable.

Damage to Property:

Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government.

Inspection and Acceptance:

A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 10 days in advance, in writing, to the Contracting Officer.

Project Schedule:

The completion of this project shall not exceed 30 days from date of Notice to Proceed. A request for time extension must be submitted to the Contracting Specialist/Officer in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

ARS reserves the right to close down or shut down the project site and order the Contractor’s employees off the premises in the event of a national emergency or Government shutdown. The Contractor may return to the site only with the written approval of the CO/COR.

Work Hours:

Contractor’s working hours shall be scheduled to coincide with the working hours of the Tifton location which are 8 a.m. to 4:30 p.m. Should it be necessary to work hours other than the regular working hours, the contractor shall arrange for access to the area with the CO/COR three days prior to the need.