Statement of Work_420_Refrigerant Monitoring Commissioning Service.docx
DOCX document 16 KB Posted
- Attached to
- Refrigerant monitoring start up service
- Solicitation number
- 70Z08525Q539
About this file
This Statement of Work outlines startup services required for the CGC HEALY's refrigerant monitoring system at USCG Base Seattle, Washington, with a performance period of March 24-April 30, 2025. The work involves commissioning services for a 3300RM2 refrigerant monitoring system, requiring technical verification, configuration, and testing procedures.
The contractor must perform specific tasks including power supply verification, configuration loading, software version checks, LED and keypad testing, relay functionality testing, system testing after 4-hour and 24-hour periods, flow rate measurements, and STYX calibration if needed. The work requires base access credentials and concludes with a written report documenting all services performed and issues encountered. The project falls under Department of Homeland Security US Coast Guard oversight, with both technical and administrative points of contact provided, and is being pursued as a sole source procurement.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work.
Start Up Services to be performed on CGC HEALY at 1519 Alaskan Way S., Seattle, WA 98134.
Description of OEM Tech Commissioning Service.
Period of Performance:
24MAR25 – 30APR25
Point of Contact:
richard.w.guthrie@uscg.mil - (619) 306-9866 Technical POC: forrest.j.heath2@uscg.mil – (253) 263-0521
Security Requirement:
USCG Base Seattle access is required. Contractor shall have a valid driver’s license and show identification.
Tasks:
-Verify all connections are tight and connected per 3300RM2 Manual.
-Connect 120VAC to the monitor and power on.
-Record any problems observed during power up.
-Measure 5, 12 & 24vdc output of Power Supply & Battery Voltage.
-Confirm Battery Isolation Switch is in the On position.
-Load the Latest configuration.
- Identify Configuration Tool Version.
- Record the 3300RM2 S/W version and upgrade if not at Current Spec.
-Verify Display LEDs and Keypad using Test Feature
- Press each keypad 5 times and record results & Verify LED Functionality.
-Record the date and time of the monitor.
-Test all Relays to confirm functionality.
-4 hours after Power up with door closed, perform a Systems Test.
-Confirm Beacon/Sndr Activation after System Test.
-Ensure that all Events were recorded in the Logs.
-Measure and record the flow rate of each pump
- Allow the monitor to Soak for 24 hours, perform a System Test.
-If System Test Fails, perform a Styx calibration and repeat.
-Turn of Power to Monitor for 60 seconds
- Verify the following:
Verify Passcode Functionality.
Record STYX Run Hours & all listed SNs/SWs Match the above.
Clear all Logs.
Verify Beacon Sounder is Turn On.
Remove Power and ensure monitor is locked up.
-Provide a written report of the services provided and any issues found during commissioning service.