OFFER SHEET - DRYDOCKING
ITEM DESCRIPTION QTY UOM UNIT PRICE TOTAL
001 SAFETY PLANS AND SUBMITTALS, BARGE BC-6214 1 JB
002 DOCKING AND UNDOCKING, BARGE BC-6214 1 JB
003 CLEAN AND RECOAT HULL, BARGE BC-6214 1 JB
004 AUDIOGAGE READINGS, BARGE BC-6214 (ESTIMATED QUANTITY) 200 EA
005 CATHODIC PROTECTION INSPECTION, BARGE BC-6214 1 JB
TOTAL of BASE Items 1-5
006 LEAK TESTING, BARGE BC-6214 (OPTIONAL) 1 JB
007 ADDITIONAL LAY DAYS, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY) 5 DY
008 DOCKAGE, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY) 3 DY
009 ELECTRIC WELDING, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY) 40 HR
010 CROP AND RENEW STEEL, FLAT, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY) 200 LB 011 CROP AND RENEW STEEL, SHAPED, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY) 200 LB 012 CATHODIC PROTECTION ANODES, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY) 10 EA
013 ICE BREAKING SERVICES (OPTIONAL, ESTIMATED QUANTITY) 2 EA
TOTAL of OPTIONAL Items 6-13
TOTAL of ALL Items 1-13
Notes:
1.
2.
3.
4.
5.
6. Basis of award will be lowest price.
Notice of Award shall constitute Notice to Proceed with the work of this Contract, and the date of award shall be the first day of the performance period.
Offers must be complete as to all items on the Offer Sheet. Failure to complete all items will render the bid non-responsive.
The Government will evaluate offers for award purposes by adding the total price for the BASE Items requirement to the total price for the OPTIONAL Items. Evaluation of options does not obligate the Government to execute any options.
The Government may elect to award any combination of option items or none of the option items. If any option items are exercised, the Government reserves the right to limit the quantity of material up to the estimated quantity of the option item. Additionally, the Contractor shall perform the work included in any or all of such items as directed and shall be paid therefore at rates appearing in the schedule of quantities and prices as applicable to the amount of work directed.
The Government reserves the right to award optional items of work no later than 100 days after the date of Contract award.
Page 1 of 1 REV 14 JUL 2021
PART 1 – Performance Work Statement
DRY DOCKING PERFORMANCE WORK STATEMENT – Rev 01 JUL 2021 PAGE 1 of 6
PERFORMANCE WORK STATEMENT – DRYDOCKING
ITEM 1. SAFETY PLANS AND SUBMITTALS, BARGE BC-6214
Accident Prevention Plans in accordance with specification Section 01 35 29, SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS and USACE Engineer Manual 385-1-1 Appendix A shall be prepared and submitted within 14 days of award of the contract. No work on the vessels will be permitted until the Contracting Officer has reviewed and found the plan acceptable. Portions of the plan that are disapproved shall be promptly corrected and re-submitted. If additional work items are added to the contract work the Accident Prevention Plan shall be amended as necessary and approved prior to the start of the additional work items. A combined safety plan may be prepared for all of the vessels as long as sufficient detail is provided to address all unique conditions and work for each vessel.
The interior of BARGE BC-6214 was originally primed with lead paint, and this paint is still present on the interior of the vessel. No lead paint exists on the exterior surfaces in way of the work of Item CLEAN AND RECOAT HULL, BARGE BC-6214. However, it is possible that lead paint will be present in way of repair work awarded under the Optional Items for ELECTRIC WELDING and/or CROP AND RENEW STEEL, BARGE BC-6214. Because of this risk, a Lead Compliance Plan as described in specification Section 02 83 00 LEAD REMEDIATION and USACE Engineer Manual 385-1-1 must be submitted for this Item. The Lead Compliance Plan must include a discussion of the measures that will be put in place to prevent dispersal of lead and protect the safety of workers during construction, to remove hazardous material, to transport hazardous waste, and to dispose of hazardous waste. The Lead Compliance Plan must also include a discussion of the elevated risk of dealing with hazardous wastes and the measures implemented in order to mitigate those risks.
The price offered for this item shall include the costs for preparing and revising the Plan as required, and reporting to the government. All other costs associated with performance of the work of the Contract in accordance with the Lead Compliance Plan, including containment, personal protective equipment, ventilation, cleanup, handling, transport, disposal, environmental and regulatory compliance, etc., shall be included in the prices offered for the associated items of work. The contractor shall be the responsible party for the testing, generation, documentation and disposal of the lead-based paint related debris. Copies of all tests, manifests, etc. shall be provided to the government in a cradle to grave paper trail sequence. The government shall be held harmless in any subsequent action regarding this matter.
ITEM 2. DOCKING AND UNDOCKING, BARGE BC-6214
Properly drydock the vessels for such time as may be necessary to complete all underwater work specified herein including sight and survey (including ABS survey), inspection, repairs, and to refloat the vessels upon completion of all work. Blocking for BARGE BC-6214 shall be sufficient to safely support the total weight of the vessel and water as required for ITEM LEAK TESTING, BARGE BC-6214. Provide safe and convenient means of boarding the vessels at all times. This item will include any charges for
DRY DOCKING PERFORMANCE WORK STATEMENT – Rev 01 JUL 2021 PAGE 2 of 6 altering blocks, providing the services specified under Paragraph SP 12 (electric service, trash removal, etc, as applicable), and for the drydock foreman's charge. This item shall also include facilitation and coordination of all inspections of the vessel and witnessing of various repairs and maintenance work to satisfy ABS requirements. Allow a sufficient number of days in drydock to complete the mandatory underwater work herein specified. The contractor shall state in their proposal the schedule to perform all mandatory items after delivery of the plant. Assume that a maximum of one day per week that the vessel is in the contractor’s facility will be unsuitable for painting. If unsuitable days are more frequent, time allowances will be made by the Government. Proposals will be evaluated on the basis of time to complete the work in addition to price and other factors. Payment for these items will be lump sum.
ITEM 3. CLEAN AND RECOAT HULL, BARGE BC-6214
Pressure wash to clean, sweep blast to profile, and then spray paint to preserve the hull and skegs of the barge. All coatings shall be delivered to the work site in sealed containers. Each container shall show:
Name of the manufacturer, name of the paint, formula of the paint, the batch number and date of manufacture (not coded). The paint shall be thoroughly mixed in accordance with the manufacturer’s instructions. All painting shall be done during daylight hours, and then only when atmospheric conditions will permit proper curing and bonding. Scaffolds or other means of providing access to the surfaces to be worked on shall be provided for use by the persons blasting and painting, and included in the cost of this item. The use of extension pipes for abrasive blasting and paint spraying will not be permitted. All abrasive blasting shall be done from above when working the sides of the vessel, with the blast nozzles pointed downward to minimize the spread of abrasive to the upper portion of the vessel.
All ventilating air inlets and other openings into the vessels shall be secured so that no abrasive grit or debris enters the vessel. No paint shall be applied until the surfaces to be coated have been inspected and approved for painting, and in no case shall paint be applied over damp, oily, or greasy surfaces or over any foreign substances. The offeror may be required to provide a covered and heated enclosure to ensure that the paint is applied and cured in accordance with manufacturer’s requirements.
The contractor shall ensure that surface preparation and paint application are performed in accordance with the paint manufacturer’s requirements. The contractor shall provide a written report to the Corps of Engineers documenting the application parameters, coating thickness applied, and stating that the paint system application meets all manufacturer’s requirements for warranty coverage.
The entire hull and skeg exteriors shall be high-pressure water blasted in order to remove any fouling or other contaminants and allowed to dry. Any areas of failed paint shall be blasted to near white metal (SSPC SP-10) and immediately primed with a primer compatible with the selected paint system (see below), to the minimum dry film thickness recommended by the manufacturer of the primer. Assume that no more than 300 square feet of the exterior of the vessel will require blasting to near white metal and repainting under this payment item. If the area is greater or lesser an adjustment will be made to the price to reflect the actual cost of the work.
DRY DOCKING PERFORMANCE WORK STATEMENT – Rev 01 JUL 2021 PAGE 3 of 6
This work shall be coordinated with the work of ITEM CATHODIC PROTECTION INSPECTION, BARGE BC- 6214and ITEM CATHODIC PROTECTION ANODES, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY).
After inspection of the anodes and award of any anode replacements, remove and dispose of all anodes approved for replacement, and temporarily remove and store any anodes not being replaced, so that the hull is fully exposed prior to cleaning, profiling, and preserving. Install any new anodes and reinstall any stored anodes once this work is complete and accepted.
Fleet and re-block the vessel to expose portions of the hull previously covered by blocking, etc., then clean and paint these areas. Repaint the draft markings and barge name on the barge. The paint system shall be one of the following:
Coating Model No – Minimum Dry Film Thickness - Color Manufacturer PPG/Amercoat International
Paint Sherwin- Williams
Carboline Jotun
1st Coat AMERCOAT 240 w/Additive 880 - 6 mils - Red
INTERZONE
505 - 6 mils - Red
SherGlass - 6 mils - Red
Carboguard 890 Glass Flake - 5 mils- Red
Jotamastic 87 GF - 5 mils - Red
2nd Coat AMERCOAT 240 w/Additive 880 - 6 mils - Black
INTERZONE
505 - 6 mils - Black
SherGlass - 6 mils - Black
Carboguard 890 Glass Flake - 5 mils- Black
Jotamastic 87 GF - 5 mils - Black
3rd Coat (Above 3 ft Draft Mark Only)
AMERCOAT
450 H - 2 mils - Black
INTERTHANE
990 - 2 mils - Black
Acrolon 218 HS - 2 mils - Black
Carbothane 134HG - 2 mils
- Black
Hardtop XP - 2 mils - Black
Hull Markings AMERCOAT 450 H - 2 mils - White
INTERTHANE
990 - 2 mils White
Acrolon 218 HS - 2 mils - White
Carbothane 134HG - 2 mils
- White
Hardtop XP - 2 mils - White
ITEM 4. AUDIOGAGE READINGS, BARGE BC-6214 (ESTIMATED QUANTITY)
The contractor shall perform audiogage readings of the vessel hull and skegs as directed by the government representative. Two copies of the readings shall be provided to the government in the form of sketches and tables clearly indicating the location and value of each reading. The readings shall be provided to the government no later than 3 workdays after the readings are taken. Readings shall be taken in 3 transverse belts, with readings at 3 ft intervals, across the bottom and up the sides. Belts of readings shall be taken 36 ft from each end of the vessel and amidships. Readings shall also be taken across each rake end at 3 ft intervals at the 2 ft, 4 ft and 6 ft depths. Skegs: Take sixteen readings on each side, five readings on the bottom, and three readings on the end of each skeg, evenly spaced. The locations of the readings may be adjusted if structure behind the plate prevents true readings of the plate. For proposal purposes the total number of audiogage readings required is estimated to be 200.
DRY DOCKING PERFORMANCE WORK STATEMENT – Rev 01 JUL 2021 PAGE 4 of 6
ITEM 5. CATHODIC PROTECTION INSPECTION, BARGE BC-6214
Under this item, the contractor shall inspect the existing anodes and provide a report to the government on their sufficiency and condition, with recommendations for anode supplementation and replacement if needed. Criteria for replacement shall be if the anodes would not be sufficient to provide corrosion protection for another 5 years. Criteria for supplementation shall be if the spacing or number of existing anodes is not sufficient to provide protection to the entire vessel.
ITEM 6. LEAK TESTING, BARGE BC-6214 (OPTIONAL)
The contractor shall perform an initial leak test of each compartment. It is known that the vessel hull has slow leaks, which are believed to be occurring at hull plate seams. The contractor shall perform the initial leak tests for a sufficient period of time to allow the leaks to be detected (minimum 24 hours).
The contractor shall mark the locations of all leaks found and shall provide a report to the government documenting the leaks and providing details of work recommended to repair them. Any necessary work to repair the leaks shall be the subject of a contract modification once the extent of repairs to be made is known. The contract modification shall include the cost of a final leak test for each compartment where repairs are made, as described below.
If needed, after the performance of leak repair work, a final leak test shall be performed for each compartment that was repaired, and any leakage marked and reported to the government as with the initial test. Any areas that are still leaking after having been repaired will be the responsibility of the contractor to correct and retest at no additional cost to the government. Any new leakage areas identified will be considered for repair by the government, and will be the subject of an additional contract modification if necessary.
It is intended that leak testing will be performed while the vessel is in dry dock, and that the manner of the test shall be to flood the interior compartments of the vessel with water to a maximum depth of 4 ft (if allowable) and observe the exterior of the vessel to find all areas of leakage. The contractor shall employ a registered Naval Architect or Marine Engineer to determine the maximum allowable depth of flooding of the vessel compartments, and to perform calculations to ensure that the safe structural capacity of the of the vessel and supporting blocking are not exceeded during leak testing. All water shall be removed from the barge compartments after leak testing.
ITEM 7. ADDITIONAL LAY DAYS, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY)
If ordered, provide additional lay days on the drydock to perform work which cannot be completed within the time needed for completion of the work awarded as part of this contract, and which may be required in addition to that herein specified or by an emergency. This item is to include the drydock foreman's charge, and services specified under Paragraph SP 12. If needed, this item will be awarded in conjunction with contract modifications needed to award such additional work, and payment for this
DRY DOCKING PERFORMANCE WORK STATEMENT – Rev 01 JUL 2021 PAGE 5 of 6 will be made at the contract proposal price per day. Proposals will be evaluated on the basis of an estimated five days.
ITEM 8. DOCKAGE, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY)
If ordered, provide dockage for the vessel at the Contractor’s facility to perform work which does not require the vessel to be in the dry dock, which cannot be completed within the time allowed for completion of the work awarded as part of this contract, and which may be required in addition to that herein specified or by an emergency. Provide services as specified under Paragraph SP 12. If needed, this item will be awarded in conjunction with contract modifications needed to award such unforeseen work. This item may also be used to pay for daily dockage in the event the vessel cannot return safely to the home port in Cleveland, OH due to weather. Proposals will be evaluated on the basis of an estimated three days.
ITEM 9. ELECTRIC WELDING, BARGE BC-6214 (OPTIONAL/EST. QTY.)
If required and directed to, the contractor will perform electric welding on the vessels, beyond what is required for the work of other items in the contract, as ordered by the Contracting Officer. A price per hour will be quoted based on an estimated requirement of 40 hours. The price shall include all welding rod, gasses, misc. materials, and labor to accomplish one hour of welding. Any steel required will be paid separately under the CROP AND RENEW STEEL items for BARGE BC-6214. Lead compliance costs associated with this work shall be included in this item of work in accordance with ITEM SAFETY PLANS
AND SUBMITTALS, BARGE BC-6214.
ITEM 10. CROP AND RENEW STEEL, FLAT, BARGE BC-6214 (OPTIONAL/EST. QTY.)
If required and directed to, the contractor will crop out and replace flat steel plate and/or framing (rolled shapes) on the vessel as ordered by the Contracting Officer. The price per pound for new steel in place will be quoted based on an estimated requirement of 200 pounds. The cost of electric welding to install the steel will be paid under Item ELECTRIC WELDING, BARGE BC-6214. All interior disturbed and new steel surfaces shall be prepared and painted in accordance with the provisions of ITEM CLEAN AND RECOAT HULL, BARGE BC-6214, using one of the specified paint systems, with the cost included in the price bid for this item.
Interior surfaces of the vessel are known to have been painted with lead-based paint. Perform all work in accordance with the accepted Lead Compliance Plan, Specification Section 02 83 00 LEAD REMEDIATION, and USACE Engineer Manual 385-1-1. Properly dispose of any resulting lead contaminated waste in accordance with local state and federal regulations. Lead compliance costs associated with this work shall be included in this item of work in accordance with ITEM SAFETY PLANS
AND SUBMITTALS, BARGE BC-6214.
ITEM 11. CROP OUT AND RENEW STEEL, SHAPED, BARGE BC-6214 (OPTIONAL/EST. QTY.)
DRY DOCKING PERFORMANCE WORK STATEMENT – Rev 01 JUL 2021 PAGE 6 of 6
If required and directed to, the contractor will crop out and replace shaped steel plate on the vessel as ordered by the Contracting Officer. The price per pound for new steel in place will be quoted based on an estimated requirement of 200 pounds and will include the cost of shaping the plate as required to conform to the original vessel design. The cost of electric welding to install the steel will be paid under Item ELECTRIC WELDING. All interior disturbed and new steel surfaces shall be prepared and painted in accordance with the provisions of ITEM CLEAN AND RECOAT HULL, BARGE BC-6214, using one of the specified paint systems, with the cost included in the price bid for this item.
Interior surfaces of the vessel are known to have been painted with lead-based paint. Perform all work in accordance with the accepted Lead Compliance Plan, Specification Section 02 83 00 LEAD REMEDIATION, and USACE Engineer Manual 385-1-1. Properly dispose of any resulting lead contaminated waste in accordance with local state and federal regulations. Lead compliance costs associated with this work shall be included in this item of work in accordance with ITEM SAFETY PLANS
AND SUBMITTALS, BARGE BC-6214.
ITEM 12. CATHODIC PROTECTION ANODES, BARGE BC-6214 (OPTIONAL, ESTIMATED QUANTITY)
Under this item, the contractor shall replace existing anodes in kind, or install new anodes where needed to supplement the existing anodes. The contractor shall provide all new hardware and replace or install new brackets as needed. The contractor shall blast, prime, and repaint all areas of damaged or missing paint, including the brackets. This work shall comply with the requirements for and be performed in conjunction with the work of ITEM CLEAN AND RECOAT HULL, but will be included in the cost for this item. If needed, this item will be awarded by contract modification after completion of the Cathodic Protection Inspection item, and payment for this will be made at the contract proposal price per anode. For bidding purposes, the estimated quantity of anodes to be replaced or installed new is 10.
ITEM 13. ICE BREAKING SERVICES (OPTIONAL, ESTIMATED QUANTITY)
If ordered, the contractor shall provide ice breaking services to provide for safe transport by government plant of the vessels to be dry docked, one-way, in either direction, between the USACE dock (at the foot of East Ninth Street, Cleveland, Ohio) and the Contractor’s shipyard facility. Ice breaking will be performed in conjunction with transport just before commencement of the repair work, and/or promptly upon completion of the dry dock work to be performed under this contract. If awarded, this work shall be performed within the overall contract performance period and shall be shown on the project schedule submitted to the government. Contractor vessels and crew personnel engaged in ice breaking shall have and be current with all required US Coast Guard licenses and ABS classing required for commercial ice breaking in open waters of the Great Lakes, and documentation thereof shall be submitted to the government for review and acceptance no later than 14 calendar days prior to the proposed dates of ice breaking. Ice breaking operations shall be performed in compliance with all applicable local, state, and federal laws and regulations. If needed, this item may be awarded once for each direction of travel. For bid evaluation purposes, the estimated quantity will be 2.
PART 2 – Special and Technical Provisions
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 1 of 10
SPECIAL PROVISIONS – DRY DOCKING TUG DONLON AND BARGE BC-6472
SP-1 SCOPE OF WORK AND SCHEDULE- The work to be done under this Job Order consists of furnishing all labor, material (except Government furnished materials, see Paragraph SP-8), equipment, supplies, facilities, and services required, and performing the work described herein for repairing the Tug Donlon, and Barges BC-6472 in strict accordance with these specifications and the Master Agreement for Repair and Alteration of Vessels. This document can be found on line at:
http://www.acq.osd.mil/dpap/dars/dfars/html/current/217_71.htm
The government will transport the vessels to and from the contractor’s facility for this work, with support from the Contractor if the optional item for ice breaking is awarded. The government intends to transport the vessels to the contractor’s facility the week of 15-19 November 2022. All work of this Contract (including ice breaking if awarded) is to be complete and the vessel returned to the government dock in Cleveland no later than 25 March 2022. The Contractor shall allow for up to 10 days on their schedule for return transport of the vessels. The Contractual period of performance may be adjusted if transport is delayed due to weather conditions other than ice.
The anticipated date of award of this Contract is 01 October 2021.
SP-2 QUANTITIES-
SP-2.1 When any item of work hereinafter described specifies a definite quantity of work to be done, it is contemplated that such quantity will be required; however, the right is reserved to increase or decrease the amount of work under the Job Order in accordance with the provisions set forth in Paragraph SP-6.
SP-2.2 Quantities of work indicated for performance are not in all cases exact, being in such cases estimates only and are intended to indicate the approximate quantities. Such work will be pointed out and definitely designated as to location and quantities by the Contracting Officer and will be done on a unit price basis. The Contractor will be required to complete the work at the unit price or prices stated in the Job order, whether it involves quantities greater or less than those specified.
SP-3 OPTIONAL ITEMS OF WORK- Items of work designated in the specifications, price schedule, and in the schedule of quantities and prices in the Job Order as "Optional" are to be performed only to the extent required by the Government as determined by the Contracting Officer. The Contractor shall perform the work included in any or all of such items as directed and shall be paid therefore at the rates appearing in the schedule of quantities and prices as applicable to the amount of work performed. The Government is under no obligation to require the performance of any such items of work.
http://www.acq.osd.mil/dpap/dars/dfars/html/current/217_71.htm
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 2 of 10
SP-4 DIMENSIONS OF PLANT- The approximate physical dimensions and physical data of the vessel covered by these specifications are as follows:
Vessel BC-6214 Type of Plant Deck Cargo Barge Length, overall 120 ft. 0 in.
Beam, molded 33 ft. 0 in.
Depth, amidships, molded 10 ft. 6 in.
Draft, mean, loaded Displacement, long tons Gross Tonnage Hull Material Steel Construction Welded & bolted
SP-5 DELIVERY AND RETURN OF PLANT-
SP-5.1 Plant transported by the Government will be delivered to the Contractor in open water clear of and adjacent to the Contractor's yard. The plant will be delivered as close as is practical to the time agreed to by both parties to the contract. The Government requires that the plant be delivered to the Contractor as close to the end of the normal operating season as is practicable, weather permitting.
SP-5.2 Upon completion of the work, the Government will accept return of the plant at the point where it was delivered to the Contractor. The date and hour of return of the plant to the Government shall be considered to be the time of the completion of the work, subject to the provisions of Paragraph SP-6.
SP-5.3 Any tug or pilot services required between open water and the drydock, slip, or berth at the Contractor's yard shall be promptly furnished by the Contractor at his expense. The government tug will deliver the plant to the drydock if conditions (water depth, etc) safely permit.
SP-5.4 If awarded, the Contractor shall provide ice-breaking services as needed for the government to safely transport the vessels between the USACE dock in Cleveland Harbor and the point of delivery to/return from the Contractor, at the beginning and/or end of the Contract.
SP-6 COMMENCEMENT, PROSECUTION, AND COMPLETION- The Contractor will be required to commence work under the Job Order within one working day after delivery of the plant, to prosecute the work with faithfulness and diligence, and to complete it within the time specified, provided that, if the Contracting Officer orders any additional work to be done beyond that called for by these specifications and/or orders any work described and required in these specifications not be done, appropriate adjustments in the time and/or price shall be made in accordance with the Master
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 3 of 10
Agreement for Repair and Alteration of Vessels. The time stated for completion is to include final cleanup of the plant.
SP-7 DRAWINGS-
SP-7.1 The following drawings are made a part of these specifications:
VESSEL: BARGE BC-6214
DRAWING NUMBER TITLE
194111 General Arrangement, Deck and Bottom Framing, Inboard and
Outboard Profile 194112 Knuckle Plates, Rake Side Plates, and Corner Plates 194113 Transverse Bulkheads, Buck Frames, and Headlog Plates 194114 Longitudinal Bulkhead 194116 Deck and Bottom Plates 194117 Side Plates 1941120 Lines 1941121 Skegs
Note: The barges were built in accordance with Army Standard Barge Design 231-A. The Buffalo District does not have a full set of drawings for this design, and the provided reference drawings are not specific to the Buffalo District barges, but were produced for the construction of a different series of barges constructed to the same standard. Additionally, modifications have been made to the barges after construction (e.g., addition of rock enclosure). The contractor shall verify any elements of construction of the barges relied upon for proposal preparation and execution of the work.
SP-7.2 Drawings are available at the Office of the District Engineer, Buffalo District, 1776 Niagara Street, Buffalo, NY 14207. Additional copies of the above listed drawing and of these specifications will be furnished to the successful Offeror without charge upon request.
SP-8 SHIFTING, ALTERATIONS, ETC.- Should the removal or shifting of any parts of the plant or its fittings, stores, fuel, water, etc., be necessary for carrying out the repairs specified, the same shall be done by the Contractor at his expense and all such removals shall be subsequently replaced and any damage or loss resulting from such removal or shifting or replacement shall be made good by the contractor at his expense. Should any portion of the plant's structure, housing, fixtures, or equipment require alteration in order to carry out the work, the Contractor shall make such alterations at his expense.
SP-9 DISPOSITION OF SCRAP AND SALVAGEABLE MATERIAL- Notwithstanding the requirements of the Master Agreement for Repair and Alteration of Vessels, all items designated as scrap resulting from the work shall become the property of the Contractor, and due consideration of the value of such scrap shall
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 4 of 10 be reflected in the proposal price of the individual items concerned. This shall not apply to salvageable items ordered to remain property of the Government, which shall be loaded and returned to the Government on truck or on board the vessel as directed. The determination of whether or not an item is salvageable shall rest with the Contracting Officer's Representative if not stated in the specifications.
SP-10 REPAIRS TO BE MADE BY THE GOVERNMENT- Government personnel may work on the vessels while in the Contractor's yard, making repairs not covered in these specifications. Work done by Government personnel will be performed in such a manner as not to delay the work of the Contractor.
Work planned by the government includes but may not be limited to:
- No specific work is planned at this time.
SP-11 CLEANLINESS ABOARD PLANT- The Contractor shall keep working areas clean and shall clean up such working areas to a condition "as found prior to commencement of work." The Contractor shall at all times refrain from marring, marking, or defacing any portion of the interior of the vessel. Any such marring, marking, or defacing shall be restored to it's original condition by and at the expense of the Contractor prior to acceptance of the plant by the Government as provided in Paragraph SP-5.
SP-12 SERVICES TO BE FURNISHED BY THE CONTRACTOR WITHOUT FURTHER COST- The Contractor shall furnish without further cost to the Government the services listed below.
SP-12.1 The Contractor shall make provisions to remove the garbage and trash from each vessel at least once daily.
SP-12.1 The Contractor shall furnish crane service to place stores and other Government equipment aboard the vessel and to remove supplies and equipment from the vessel. Crane services shall be provided at times mutually agreeable to the Contractor and the Contracting Officer.
SP-13 FINAL EXAMINATION AND ACCEPTANCE- As soon as practical after the completion of the entire work as may be designated in the specifications a thorough examination thereof will be made by the Contracting Officer's Representative at the site of the work. If such work is found to comply fully with the requirements of the Contract Job Order it will be accepted, and final payment will be made in accordance with the Contract article entitled "Payment".
SP-14 LIQUIDATED DAMAGES- For each work day beyond the adjusted scheduled completion date that completion of the work is delayed, liquidated damages will be assessed at the following rates:
Administrative Costs $1000/work day
For the purposes of this paragraph work days consist of Monday through Friday inclusive with the exception of Federal holidays. A current list of Federal holidays can be found at https://www.opm.gov/policy-data-oversight/pay-leave/pay-administration/fact-sheets/holidays-work-schedules-and-pay https://www.opm.gov/policy-data-oversight/pay-leave/pay-administration/fact-sheets/holidays-work-schedules-and-pay https://www.opm.gov/policy-data-oversight/pay-leave/pay-administration/fact-sheets/holidays-work-schedules-and-pay
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 5 of 10
SP-15 PROPOSAL EVALUATION
The award decision will be made based upon the total sum of the Proposed Price for all work on the Proposal Schedules (including optional items).
SP-16 SUBMITTALS
SP-16.1 Safety Submittals
All safety and other submittals shall be provided to the government within 14 calendar days after contract award. No work on the vessel will be permitted until the COE Safety Office has reviewed and found the submittals to be acceptable. The COE Safety Office will have 7 calendar days to review and respond to submittals.
The Contractor shall submit to the government representative any Requests for Information and/or Condition Found Reports that are needed during the Contract performance period within 24 hours of discovery of the need for the RFI or CFR. The contractor shall allow 7 calendar days for the government to review and respond to the RFI or CFR.
SP-16.2 Schedule
In addition to the schedule information required with the proposal, the Contractor shall submit and maintain a detailed schedule showing the planned dates of starting and completing each item of work awarded. The initial schedule shall be submitted within 14 calendar days after contract award. A revised schedule shall be submitted monthly. In addition, schedule updates shall be issued within 3 calendar days following any event that affects the dates of completion of the work, such as award of optional work. Schedule updates shall also be submitted as part of documentation for progress payments. The project schedule shall be prepared using the critical path method, and shall identify all work that is critical to timely completion.
SP-16.3 Product Data
Submit product data for all products to be incorporated into the work for the following items within 14 days after contract award. The Government will have 7 calendar days to review and respond to submittals.
- Paint
SP-17 SITE VISIT
The vessels will be available for inspection in Cleveland Harbor, OH from 9:00 AM to 12:00 PM Eastern Time on Monday August 16, 2021. Reservations are required. To make a reservation and get detailed directions to the location of the vessels please contact Mr. Timothy Colburn at Timothy.E.Colburn@usace.army.mil 216-973-8517.
mailto:Timothy.E.Colburn@usace.army.mil
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 6 of 10
Address of the site visit is:
USACE Cleveland Reservation 1035 E 9th Street Cleveland, OH 4411
SP-18 E-VERIFY PROGRAM
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
SP-19 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
SP-20 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
U.S. Department of Labor Veterans employment: www.vets.gov/ Federal veteran employment information: www.fedshirevets.gov/index.aspx Veterans’ Employment and Training Service (VETS): http://www.dol.gov/vets/ http://www.vets.gov/ http://www.fedshirevets.gov/index.aspx http://www.dol.gov/vets/ http://benefits.va.gov/vow/ http://www.uschamberfoundation.org/hiring-our-heroes https://www.dol.gov/sites/dolgov/files/VETS/files/Employer-Guide-to-Hiring-Veterans.pdf
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 7 of 10
Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/ U.S. Army Warrior Transition Command Employment Index:
wtc.army.mil/modules/employers/index.html Hiring Our Heroes initiative: www.uschamberfoundation.org/hiring-our-heroes Guide to Hiring Veterans:
https://www.dol.gov/sites/dolgov/files/VETS/files/Employer-Guide-to-Hiring-Veterans.pdf
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 8 of 10
TECHNICAL PROVISIONS– DRY DOCKING BARGE BC-6214
TP-1 WORKMANSHIP
TP-1.1 General
a. All labor shall be especially skilled for each kind of work, thorough, and first class in every respect, and under competent and coordinated supervision.
b. Where work of one trade joins, passes through, or is on other work, there shall be no discrepancy or misfit when completed. In engaging one kind of work with another, marring or damaging previously acceptable construction shall be cause for rejection.
c. All parts of the work intended to join or bear upon others shall have complete and solid surface contact and fit together neatly without excessive cold work during erection. All faying surfaces shall be painted and shall be clean and smooth before bolting up. Shims or liners shall not be used for the purpose of overcovering a bad fit.
d. Workmanship throughout shall be in accordance with the best modern practice and shall conform to the current edition of the American Bureau of Shipping's "Rules for Building and Classing Steel Vessels", and U.S. Coast Guard rules as applicable.
TP-1.2 Cutting. All edges and corners of plates and shapes shall be smooth and free of burrs. The use of a cutting torch is permissible for cutting plates and shapes to size, but the burning of bolt holes will not be permitted.
TP-1.3 Welders and Welding.
a. All welding under this job order shall be done only by welders who have successfully passed the qualification test of the American Bureau of Shipping except that any welding coming under the jurisdiction of the U.S. Coast Guard Marine Inspection shall be done only by welders having passed the qualification test of the U.S. Coast Guard or equal.
b. The electrodes used throughout the work shall be suitable for use with the parent metal at each weld. Electrodes shall be received on the job in unbroken packages bearing the manufacturer's label or be similarly marked.
c. Assembly of all welded joints before welding shall be such as to secure proper gaps in butt welds and metal to metal contact on fillet welds. Welding shall not be used to close openings larger that stipulated for each plate thickness by the American Bureau of Shipping. Surfaces to be welded shall be free from paint, scale, etc.
d. Welding procedures, as to direction, length, number and sequence of beads, shall be carefully planned so as to minimize locked up stresses.
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 9 of 10
e. All welding is to conform to the specifications set up by the American Welding Society and shall be in compliance with the latest edition of "Rules for Building and Classing Steel Vessels" as published by the American Bureau of Shipping.
TP-2 INSPECTION AND TESTS-
TP-2.1 The work will be conducted under the general direction of the Contracting Officer and is subject to inspection by any appointed inspectors to insure strict compliance with the terms of the Contract. No inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer, nor shall the presence or absence of an inspector relieve the Contractor from any requirements of the Contract.
TP-2.2 Inspection and tests shall be made at such times and in a manner satisfactory to the Contracting Officer. The Contractor shall keep the Contracting Officer informed of the desired time of all proposed tests or inspections. Trial of machinery shall be conducted by the Contractor at this expense.
TP-2.3 When any workmanship, material, or apparatus fails to pass any test or inspection it shall be fully retested only after all known defects have been eliminated therefrom.
TP-3 PAINTS-
TP-3.1 Paints shall be accurately compounded of materials as called for in the applicable specifications therefore.
TP-3.2 Paint shall be well mixed before use so that it can be readily broken with a paddle to a smooth uniform paint of good spraying consistency. Paint shall be applied in accordance with the manufacturers standards or recommendations for proper application.
TP-3.3 Commercial paint systems shall be those of a reputable manufacturer of marine coatings, of a premium grade, and suitable for fresh water service. The paint system shall be applied properly allowing adequate drying times. If the surface preparation recommended by the manufacturer and the preparation called for in these specifications are different, the method calling for the higher degree of surface preparation shall be used.
TP-3.4 The Contractor shall furnish paint combs and a reliable dry film thickness gage and take random measurements in the presence of the Government Inspector to demonstrate that the specified paint film thicknesses are achieved for each coat of paint.
TP-4 MATERIALS, OPERATING CHARACTERISTICS, ETC.- Any material not specified shall be the best of its kind, suitable for the purpose intended, and subject to the approval of the Contracting Officer.
Where sizes, firs, operating characteristics or controls are not specified, they shall be as approved by the Contracting Officer.
TP-5 REFERENCES- The latest edition of the following references are made part of this specification:
DRY DOCKING BARGE BC-6214 SPEC & TECH PROVISIONS– Rev 04 AUG 2021 PAGE 10 of 10
American Bureau of Shipping Rules for Building and Classing Steel Vessels
Code of Federal Regulations 29CFR1915, Occupational Safety and Health Standards for Shipyard Employees
Army Corps of Engineers EM 385-1-1, Safety and Health
Requirements Manual
American society for Testing ASTM A-36, Structural Shapes and Materials
American Iron and Steel AISI-1015, Low Carbon Steel Institute Plate
Institute of Electrical and IEEE-45, IEEE Recommended Electronic Engineers Practice for Electric
Installations on Shipboard
International Association of Rec. No. 47, Shipbuilding and Repair Classification Societies Quality Standard http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
Safety Requirements – Rev 14 JUL 2021 PAGE 1 of 2
Part 3 – SAFETY REQUIREMENTS
Safety is a key operating principle for the USACE, and, therefore, the Contractor shall adhere to the application of all applicable local, state, and federal requirements.
Prior to any work associated with this contract, the Contractor is required to develop the submittals noted below and subsequently submit them as required. Contractor will comply with the USACE Safety & Health Requirements Manual (EM385-1-1) which is available on-line at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
Required Safety Submittals (APP) Accident Prevention Plan Completed APP Checklist (Attachment 4) (AHA’s) Activity Hazard Analysis (Attachment 5) Competent Person/Site Safety and Health Officer (SSHO) Qualifications (per EM 385-1-1
01.A.17) Accident Investigation Reports as incidents occur (Attachment 6) Monthly Man-Hour Reports by the 5th of every month (Attachment 7) Confined Space Entry Permit as issued Hot work permit as issued Welding personnel qualifications Certification of Compliance for Load Handling Equipment (LHE) and Rigging (Attachment 8) Certification of medical fitness for crane operators (Per EM 385-1-1 16.B.05) Crane Standard Pre-Lift Plan and/or Critical Lift Plan(s) Lead Compliance Plan Fall Protection Plan Scaffolding Plan Respiratory Protection Program Hazard Communication Program Confined Space Entry Program Chromium (VI) Exposure Evaluation (Per EM 385-1-1 Section 06.M) Medical and First Aid Plan (Per EM 385-1-1 Section 3)
Work shall not proceed until the APP has been submitted to, and accepted by, the USACE Buffalo District Safety Office. The Contractor shall avoid providing material of a general nature not specifically related to this project or site. Previous versions of existing off-the-shelf APP are not acceptable. The APP shall be prepared following the format found in USACE publication U.S. Army Corps of Engineers (USACE) Safety and Health Requirements Manual ER 385-1-1, Appendix A. The following documents shall be considered in the preparation of the APP:
USACE EM 385-1-1 Safety and Health Requirements Manual;
UFGS-01 35 26 Governmental Safety Requirements USDOL OSHA 29 CFR 1926 Safety and Health Regulations for Construction USDOL OSHA 29 CFR 1910 Occupational Safety and Health Standards http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
Safety Requirements – Rev 14 JUL 2021 PAGE 2 of 2
UFGS- 02 83 00 20 LEAD REMEDIATION
The written Lead Compliance Plan shall be in accordance with the latest versions of EM 385-1-1, UFGS- 02 83 00 20 LEAD REMEDIATION, and 29 CFR 1926.62 LEAD. The Lead Compliance Plan shall include a description of each work activity where lead may be emitted, a description of equipment and materials used, crew size, job responsibilities, means to achieve exposure compliance, employee exposure monitoring procedures, Competent Person (CP) and employee training, security required for each lead hazard control area.
AHA shall be compliant with the requirements of EM 385-1-1 Section 01.A12. A suggested format is provided in Attachment 5. As long as the contractor captures the required AHA categories, AHA format may be varied.
All Contractor accidents/incidents that occur during the execution of this contract and meet or exceed one of the following thresholds shall be reported to USACE within 4 hours of the contractor becoming aware of their occurrence:
Personal injury $2000 of property damage Any incident with the potential to generate public or media interest
Notification will include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). The USACE initial contact must be made personally (telephone or email messages only are not acceptable) to one of the following:
1. Contracting Officer’s Representative = Gregory Krzys work (216) 685-1203; Cell (951) 970-
Email to: Gregory.A.Krzys@usace.army.mil
2. Project Manager = Paul Bijhouwer work (716) 879-4377; Cell (716) 374-1472 Email to: Paul.Bijhouwer@usace.army.mil
Additional safety requirements will be found in UFGS 01 35 26 (Attachment 1). Lead Based Paint requirements will be found in UFGS 02 83 00 (Attachment 2) and EM 385-1-1 (2014 Edition, Section 06.C.02).
mailto:Gregory.A.Krzys@usace.army.mil mailto:Paul.Bijhouwer@usace.army.mil
List of Attachments– Rev 14 NOV 2019 PAGE 1 of 1
Part 4 – LIST OF ATTACHMENTS
The following is a list of attached documents hereby incorporated into this Contract. Some of the forms are available in Excel, Word, or fillable pdf format so that they may be completed electronically, and will be provided to the successful offeror, post-award, upon request.
Safety Attachments
1. UFGS 01 35 26 Governmental Safety Requirements (pdf)
2. UFGS 02 83 00 LEAD REMEDIATION (pdf)
3. Submittal Register for UFGS 02 83 00 LEAD REMEDIATION (pdf)
4. Accident Prevention Plan Checklist (pdf, doc)
5. Activity Hazard Analysis Form (electronically fillable pdf)
6. Accident Investigation Report – ENG Form 3394 (pdf, electronically fillable pdf)
7. Monthly Man Hour Exposure Report (pdf, xls)
8. Form 16-1 Certificate of Compliance for LHE and Rigging (pdf, doc)
Technical Attachments
A. Barge BC-6214 Drawings (See list of drawings in Special Provisions, pdf)
FY 22 Barge BC-6214 Drydocking DRYDOCKING
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
11/20 safety and occupational health requirements for the protection of Contractor and Government personnel, property, and resources